← All training manualsEngineering Project and Maintenance Management Level 2 · read-onlyGet the PDF with Teacher Copy (GH¢50)
Level 2 · National Proficiency II · CTVET formatTrainee Manual

Engineering Project and Maintenance Management Level 2

From routine to programme. Rank your equipment, plan and schedule jobs, clear the backlog, find root causes, control stores and contractors, and price a maintenance service.

A technician with a clipboard beside a pump, a tool store and a wall planner A technician in a helmet and overalls holds a clipboard with a work order checklist beside a water pump on a concrete base. To the left, a wall planner with a monthly grid and ticks. To the right, a parts shelf with labelled boxes and a spanner rack. PLAN · SCHEDULEWORK ORDER · LOGSPARE PARTS STORE
Trainee name
Training centre
Site
Start date
Prepared by De-Graft Afful · Version 1.1.0 · November 2026
01

About this module

At Level 1 you kept things running. At Level 2 you decide what to look after first, plan the work so it fits around production, and find out why things fail.

Who it is for. People who have finished Engineering Project and Maintenance Management Level 1, or who can show the same skills. National Proficiency II is the level after NP I in Ghana's TVET framework; learners work with less supervision and handle some varied tasks.

CTVET status. CTVET has competency-based training for many engineering trades, but its unit list for maintenance management was not found online. This module is not that curriculum, and it does not certify you as an engineer, technician or inspector. Ask CTVET or the regional Ghana TVET Service office for the current standard.

Ask a qualified expert. This module teaches planning and management. For electrical work use an Energy Commission-certified electrician. For lifting equipment, pressure vessels, structures, or anything that could fall or burst, ask a GhIE-registered engineer. Do not attempt work you are not trained and authorised to do.

Bridge from Level 1: what you already know

  • Breakdown, preventive and corrective maintenance; the golden rule (tell, stop, isolate, lock, release, test)
  • The asset list with tag numbers, nameplates, manuals and A, B, C marks
  • The work order in five steps and the three priorities
  • Daily checklists, a simple schedule and correct lubrication
  • Stock cards, minimum and maximum, tool sign-out book
  • History cards, MTBF, MTTR, planned share, a one-page report
  • A small job plan, a written scope, handover and a first service idea

Level 1 did not teach ranking equipment by risk, scheduling with a critical path, backlog control, root-cause analysis, ABC stock classes, supplier quotes, permit to work, managing contractors, or pricing a service agreement. This manual does. See the Hub's Workplace Safety for the safety law and Entrepreneurial Thinking for business basics.

How the module works

Each unit has learning outcomes, performance criteria, the range and the evidence your assessor needs. You are judged Competent or Not Yet Competent. About 70% of the time is practical, following CTVET's Oil Palm programme split of about 30% school and 70% workplace.

02

Unit 1 · Build a maintenance programme

You cannot look after everything equally. Decide what matters most, then plan the care.

Competency standard

Learning outcome Performance criteria — the trainee…
1.1 Rank equipment scores each asset for safety, production and repair effort and ranks them
1.2 List failure modes lists how a critical machine can fail and the effect of each
1.3 Score and prioritise uses severity, occurrence and detection scores to rank failure modes
1.4 Design tasks writes preventive tasks with intervals, from the manual, for the top failure modes

Range. At least three critical machines. Evidence. Criticality table; failure mode table; programme sheet.

Ask a qualified expert. Scoring is a tool, not a replacement for judgment. Anything that can hurt people, such as a missing guard or a lifting device, is dealt with first, whatever its score. For electrical, lifting, pressure and structural items ask an Energy Commission-certified electrician or a GhIE-registered engineer.

Rank by criticality

Score each asset from 1 (low) to 5 (high) on three questions, then add them up. Safety: could a failure hurt someone? Production: does the business stop? Repair: how long and how costly is the repair or the wait for parts?

Asset Safety Production Repair Total Class
Borehole pump 2 5 4 11 A
Maize mill 4 5 3 12 A
Water tank float valve 1 3 1 5 C
Generator 3 4 3 10 A
Office fan 1 1 1 3 C

The cut-offs (for example A is 10 or more) are the manager's choice for the site. Maintenance guides recommend ranking assets first and analysing only the few whose failure stops production or creates a safety risk.

Failure modes and their scores

A failure mode is one way a part can fail. For each A machine, list them and score three things from 1 to 10: severity (how bad), occurrence (how often), detection (how hard to notice before it hurts, where 10 is hardest). Multiply them to get a risk priority number (RPN), so values run from 1 to 1,000. This method is called FMEA. Practitioners warn that identical totals can hide very different risks, so give a high-severity item attention even if its total is low.

Machine Failure mode S O D RPN
Mill Belt breaks 5 6 5 150
Mill Guard missing or loose 8 4 3 96
Mill Bearing seizes 9 2 2 36

Priority by RPN: belt (150), guard (96), bearing (36). But the guard and bearing have high severity, so check them too. Scores are the team's own judgment; write the reason beside each.

Turn it into tasks

For each high-priority failure mode, write a preventive task, an interval and a person.

Failure mode Task Interval Who
Belt breaks Check tension and cracks weekly Operator, stopped and locked out
Guard loose Check guard fixings and condition daily Operator
Bearing seizes Grease with the type and amount in the manual by manual Technician

Take the intervals from the maker's manual and from your own history cards. When a machine fails again and again, shorten the interval or change the task. When a task finds nothing for a long time, ask a technician whether to lengthen it.

Score and rank

Three failure modes of a pump: (A) seal leaks: S5, O6, D4; (B) motor overheats: S7, O3, D6; (C) suction pipe cracks: S4, O2, D3. (1) Work out each RPN. (2) Rank them. (3) Which would you check regardless of rank, and why?

Write a programme

  1. From your Level 1 asset list, score all assets and mark A, B, C.
  2. Choose three A machines and list at least three failure modes each.
  3. Score S, O and D with the technician; compute the RPNs.
  4. Write a task, interval and person for the top six.
  5. Put the tasks on a one-page programme sheet and a wall calendar.

Rank your house

Score ten things in your home (cooker, fridge, phone charger, gate lock) for safety, loss if it fails, and repair effort. Which three get first care?

Check yourself

  1. What does RPN stand for and how is it worked out?
  2. Why look at severity separately?
  3. Where do you take preventive intervals from?
03

Unit 2 · Plan and schedule small engineering jobs

A schedule is a promise you can keep, because you checked what depends on what.

Competency standard

Learning outcome Performance criteria — the trainee…
2.1 Break a job into tasks lists tasks with who, parts and time
2.2 Find the order marks which tasks must wait for others
2.3 Draw a bar chart and find the critical path draws the chart and shows the longest chain and the spare time
2.4 Budget and permit prices labour, parts and a contingency; arranges a permit to work and isolation

Range. Jobs of 2 to 15 working days with up to 12 tasks. Evidence. Task list; chart; budget; permit.

Ask a qualified expert. A schedule is not a safe system of work. For electrical, gas, lifting, pressure or structural jobs, the plan must be approved by an Energy Commission-certified electrician or a GhIE-registered engineer. A permit to work does not by itself make a job safe; everyone must act on it. This module does not teach building or civil works planning, which belongs to Civil Engineering.

The planning steps

Project planning guides give the same basic sequence: divide the job into tasks and estimate each; show the order in a diagram; find the critical path and float; then draw a bar (Gantt) chart. The critical path is the longest chain of tasks that must follow each other; its length is the shortest time the job can take. A task that is not on the critical path has float: spare time it can slip without delaying the end. For a small job, a task list and a simple bar chart on paper or in a spreadsheet are usually enough.

Worked example (times are examples)

A small mill service. Tasks, with days and what each waits for:

Code Task Days Waits for
A Plan and get approval 1 none
B Order and receive parts 3 A
C Isolate, lock out and strip the machine 1 A
D Fit new parts 1 B and C
E Test run 0.5 D
F Clean up and handover 0.5 E

Paths. A, B, D, E, F = 1 + 3 + 1 + 0.5 + 0.5 = 6 days. A, C, D, E, F = 1 + 1 + 1 + 0.5 + 0.5 = 4 days. The longest is the critical path: 6 days. Task C is not on it and has 2 days of float (it can start up to 2 days later without delaying the job). So do not strip the machine on day 2: that would stop the mill for 2 days longer than needed. Strip it on day 4, when the parts are due.

Bar chart (each column is half a day, X is work):

Task D1 D2 D3 D4 D5 D6
A Plan X
B Parts X X X
C Strip X
D Fit X
E Test X
F Handover X

(E and F share day 6, half a day each.)

Budget

List: parts, labour, transport, consumables, permit or inspection fees, and a contingency of about 10% for surprises. The 10% is a rule of thumb, not a law.

Example budget: parts GH¢1,200; labour 2 technicians × 2 days × GH¢150 = GH¢600; subtotal GH¢1,800; contingency 10% = GH¢180; total GH¢1,980. All prices are examples; get local quotes.

Permit to work and isolation

For high-risk jobs a formal system such as a permit to work may be required. A permit states the job, the hazards, the isolation done, the precautions, who is in charge, and when it ends. The HSE warns that a permit does not by itself make a job safe: the people who prepare it, supervise and do the work must all act on it. Plan work for downtime so it does not clash with production.

Tools and items: Unit 2

Item What it is and what it does Also called Size or type Caution
Permit to work form A written permission for a risky job that lists hazards, isolation, precautions, who is in charge and when it ends. Work permit One A4 page A permit does not make a job safe by itself
Isolation certificate A page that records which energy sources were isolated, where locks are, and who tested. Isolation record One A4 page Attach to the permit
Lockout station A wall board that holds padlocks, tags, hasps and signs in one place. Lockout board, lockout centre Wall board with hooks Count items every week
Bar chart A chart with tasks as bars on a time line, to show order and length. Gantt chart A4 or flip chart Update with real dates
Sticky notes Small paper squares to move tasks around on a wall. Post-it notes Any None
Flip chart A big paper pad on a stand for planning with a team. Chart pad A1 None
Contingency Extra money kept for surprises. Reserve 10% is an example Not for changing the scope

Parts and safety: Permit to work form

Permit to work form A blank permit to work form with numbered boxes PERMIT TO WORK 1 2 3 4 5 6 7
A blank permit to work form. Numbers on the picture match the table below.
No. Box What to write Rule
1 Job and place What the job is and where, with the tag number Be exact
2 Hazards What can hurt people (electricity, fall, fuel, heat, confined space) Think before writing
3 Isolation done Which energy sources were cut and where locks are The person who did it signs
4 Precautions and PPE Guards, barriers, signs, PPE, extinguisher, watcher Write what will be done
5 Person in charge The name of the person who controls the work One name only
6 Time limit Start and end time of the permit It ends when the time ends
7 Handback signature The person in charge hands the machine back and the supervisor accepts Sign only when guards are back and tools are out

How to fill, in one line each: box 1 to 4 before the job by the supervisor, box 5 and 6 on the day, box 7 at the end. A permit is only a record; the work must follow it. Ask a GhIE-registered engineer or a qualified safety officer to approve your permit form.

Safety protocol: Permit to work

Before. The supervisor and the person in charge walk to the machine together. They list hazards, agree the isolation, and check locks and tags. PPE is ready. All people who will work are briefed.

While you work. Work only inside the permit. If the job changes, stop and write a new permit. Keep the permit at the job. Nobody removes a lock that is not theirs.

After. Clear the area, count tools, refit guards, remove locks, hand back, sign box 7, file the permit.

Emergency. Stop work, make safe, raise the alarm, call 112 for injury or fire. Tell the supervisor before restarting.

Parts and safety: Lockout station board

Lockout station board Wall board with padlocks, tags, hasps and signs, numbered parts Isolation register 1 2 3 4 5 6
A wall lockout station. Numbers on the picture match the table below.
No. Part What it does Safety rule
1 Padlock rack Holds one lock for each authorised person Each lock has a name
2 Hasp store Holds multi-lock hasps Check they close
3 Tag board Holds blank lockout tags Keep a pen on a string
4 Sign board Holds DANGER and DO NOT START signs Replace faded signs
5 Isolation register Records who locked what, when and why Sign out and in
6 Notice Lists the lockout steps (golden rule) Keep it readable

Safety protocol: Lockout station

Before. Check every item is on the board and works. Check locks are labelled.

While you work. Take only your own lock. Write in the register. Never share keys.

After. Return locks and tags; write the register entry; report a missing item at once.

Emergency. A lock cannot be removed because the owner is away: do not cut it. Follow the written procedure of the site, and ask a GhIE-registered engineer or the safety officer.

Two tables for the supervisor

Cost sheet for a job (example, all prices are examples).

Item Quantity Unit price Total
Parts
Labour days
Contingency (10%)
Grand total

Schedule a pump overhaul (example numbers)

Tasks: A plan (1 day); B order seal kit (4 days, after A); C isolate and remove pump (1 day, after A); D fit kit and refit (1 day, after B and C); E test and handover (1 day, after D). (1) Length of each path? (2) Critical path and total time? (3) Float of C? (4) Budget: kit GH¢300, one technician 2 days at GH¢150 a day, 10% contingency.

Plan a real job

  1. Choose a real job of 3 to 10 days from your site.
  2. List tasks, durations and what each waits for.
  3. Find the critical path and the float; draw the bar chart.
  4. Make a budget with contingency.
  5. Write the isolation steps and fill a permit to work form for the risky tasks.
  6. Present to your trainer; change the plan if the trainer finds a problem.

Plan a small task at home

Plan a weekend job such as painting a fence or fixing a door. List tasks, times and the order. Which task is on the critical path?

Check yourself

  1. What is the critical path?
  2. What is float?
  3. Why add a contingency to a budget?
04

Unit 3 · Run the work order system

A work order system is only as good as its worst-kept list.

Competency standard

Learning outcome Performance criteria — the trainee…
3.1 Keep a register keeps every work order in one list with status, priority, due date and owner
3.2 Control backlog works out the backlog in weeks and the overdue share, and acts on them
3.3 Plan before doing prepares job plans with parts and tools ready before the technician starts
3.4 Hold a weekly meeting runs a 20-minute planning meeting and records decisions

Range. At least 15 work orders over 4 weeks. Evidence. Register; backlog calculation; meeting notes.

Ask a qualified expert. Registers may be inspected. Under Act 328 some records must be kept for set periods; the Act says the general register and required records must be kept available for two years after the last entry. This is general information, not legal advice. Ask the Factories Inspectorate or a qualified lawyer what applies. For jobs touching electricity, lifting, gas or pressure, name an Energy Commission-certified electrician or a GhIE-registered engineer on the order.

A spreadsheet register

A free spreadsheet can serve as your simple maintenance system. Useful columns: WO number, date raised, tag, fault, priority, type (preventive, corrective, emergency), estimated hours, owner, due date, status (open, planned, waiting for parts, done, closed), date closed, actual hours, cost.

Backlog

Backlog is work waiting. Measure it two ways.

  1. In weeks of work: estimated hours outstanding ÷ hours the crew can do in a week. Example: 120 hours outstanding; 2 technicians each give 30 productive hours a week = 60; backlog = 120 ÷ 60 = 2 weeks.
  2. Overdue share: overdue orders ÷ open orders × 100. A maintenance metrics page describes an overdue work order rate as the share of work orders past due. Example: 18 overdue of 60 open = 30%.

Do not hide old orders. Cancel those that no longer matter, with a reason. No firm Ghana or official target was found for a healthy backlog; watch your own trend.

Plan before you do

Technicians lose hours walking to the store, looking for tools and waiting for parts. A job plan lists the steps, parts with numbers, tools, safety and time before the technician starts. A short planning step saves long delays. The HSE advises planning the work in advance using the manufacturer's instructions.

The weekly planning meeting

Twenty minutes, same day each week: review emergency work from last week; check the list of work with parts ready; choose next week's jobs; check the PM tasks due; note what needs a decision from the owner. Keep notes: who, what, by when.

Wrench time

Wrench time is the share of a technician's day spent actually doing the work, not waiting or walking. A simple check: watch a technician for an hour and note how many minutes were spent on tools. If under half, plan better.

Tools and items: Unit 3

Item What it is and what it does Also called Size or type Caution
Work order register A table of every work order with status, priority, tag and dates. CMMS spreadsheet, job log Spreadsheet or book One owner updates it
Job plan Steps, parts, tools and safety written before the job. Work plan One page Written by a planner, not on the day
Planning board A wall board or chart that shows the week's jobs. Weekly schedule board Whiteboard Keep it current
Backlog Work waiting to be done, in hours. Work queue Number Measure it weekly

Work order register columns. WO number, date raised, tag, place, fault, priority, planned hours, status (waiting parts, planned, in progress, done, closed), who, due date, date done, hours used, cost.

Weekly planning agenda (30 minutes). (1) Review last week: what was done and what slipped. (2) Review the backlog by priority. (3) Choose next week's jobs and check parts and people. (4) Check lockout and permit needs. (5) Say who does what.

Formulas (all numbers are examples).

Measure Formula Example
Backlog in weeks Backlog hours ÷ weekly capacity hours 120 ÷ 40 = 3 weeks
Reactive work share Breakdown hours ÷ total maintenance hours × 100 10 ÷ 40 = 25%
Planned work share Planned hours ÷ total maintenance hours × 100 30 ÷ 40 = 75%
PM compliance PM work orders done by due date ÷ PM work orders due × 100 17 ÷ 20 = 85%
Schedule compliance Hours done as scheduled ÷ hours scheduled × 100 40 ÷ 50 = 80%

PM compliance and schedule compliance are different measures: one counts work orders, the other counts hours. Do not report one as the other. Commonly cited targets for planned work (about 80 to 90%) vary between sources and editions, so compare your own months.

Backlog sums

(1) 90 hours outstanding; crew gives 45 hours a week. Backlog in weeks? (2) 12 overdue of 48 open orders. Overdue share? (3) A technician was on tools for 24 minutes of an hour. Wrench time?

Run the register for four weeks

  1. Set up the spreadsheet columns above.
  2. Enter every work order for four weeks, from requests and PM tasks.
  3. Each week, calculate the backlog and overdue share.
  4. Hold the weekly meeting and write notes.
  5. At the end, write: what got better? What would you change?

Your own backlog

List what is waiting to be fixed in your home or room. Estimate the hours. If you could give 4 hours a week, how many weeks is the backlog?

Check yourself

  1. What is backlog?
  2. Give the formula for the overdue share.
  3. What goes on a job plan?
05

Unit 4 · Find the cause and stop repeat failures

Repair the part and the fault returns. Fix the cause and it stays fixed.

Competency standard

Learning outcome Performance criteria — the trainee…
4.1 Spot repeat failures finds machines with the same fault two or more times in the history cards
4.2 Use the 5 whys asks why until a cause that can be fixed is found
4.3 Use a fishbone groups possible causes under people, method, machine, material, environment
4.4 Fix the system and check changes the checklist, schedule, stock or training and checks it worked

Range. Three real or simulated failures. Evidence. Failure reports; fishbone; follow-up check.

Ask a qualified expert. Finding a cause may mean opening machines, touching electrical parts or working near pressure. Do it with the machine stopped and locked out, and only if you are trained. For electrical faults use an Energy Commission-certified electrician. For pressure, lifting or structural causes ask a GhIE-registered engineer. For injuries see a doctor or nurse.

The 5 whys

Keep asking why until you reach a cause you can fix. It works best for simple failures with one main cause, and the common mistake is to stop at a symptom.

Example (made-up). The pump seal failed. Why? It ran dry. Why? The suction valve was shut. Why? The operator did not know to open it. Why? The start-up checklist has no step for the valve. Root cause: the checklist. Fix: add the step, train the operators, check in one month. Replacing the seal alone would have failed again.

The fishbone

For failures with several possible causes, draw a fish: the fault at the head, and bones for people, method, machine, material, environment. Write possible causes on each bone, then test the most likely with facts. Using the fishbone first and the 5 whys on the likeliest bone is a common approach. Different teams may reach different conclusions, so check against records and the people on the floor.

Lubrication and wear

A widely quoted foreign training figure says lubrication problems account for about 36% of premature bearing failures, and that too much grease is also a cause. Another figure that circulates is much higher, but it depends on definitions, so do not use it. Check lubrication first when a bearing fails, and use the type and amount in the manual.

Early warning: condition checks

Early signs include rising heat, new noise, new vibration, leaks and changes in oil colour. Trending them on the history card shows trouble early. Tools such as vibration meters and ultrasound exist, but cost money; begin with your senses and a simple log, and ask a technician what to measure. Never touch a hot or moving part.

Failure report

One page: machine and tag; date; what happened; downtime; cost; 5 whys; root cause; action; who and when; check date.

Cost of a repeat failure (all numbers are examples). A bearing fails 4 times a year. Each failure costs GH¢350 for the part and labour plus 6 hours of lost work at GH¢120 an hour. Cost per failure = 350 + 6 × 120 = GH¢1,070. Four failures = GH¢4,280 a year. A fix (realign the shaft, add a grease step, fit a guard) costs GH¢900 once. The fix pays for itself in less than one year.

Lubrication reference

  • Grease or oil. Use oil where the machine has a sump or an oil bath. Use grease for sealed or slow bearings the manual says to grease.
  • Reading a can. SAE gives thickness; API gives quality class. NLGI gives grease stiffness.
  • NLGI grades (by cone penetration, ASTM D217 numbers, secondary source). 000 is 445 to 475; 00 is 400 to 430; 0 is 355 to 385; 1 is 310 to 340; 2 is 265 to 295; 3 is 220 to 250; 4 is 175 to 205; 5 is 130 to 160; 6 is 85 to 115. Grade 2 is the common general-purpose bearing grade. The standard itself was not opened; check the ASTM D217 text and the manual.
  • How much grease. A re-grease shot in grams is about 0.005 × outside diameter (mm) × width (mm); it is a top-up, not a first fill. The interval is not a calculation: read it from the bearing maker's chart, then shorten it for heat, a vertical shaft or dirt. The maker's figure wins.
  • Signs of too much grease: hot bearing, grease thrown from the seal. Too little: dry, noisy, hot bearing.
  • Clean handling. Wipe the nipple. Keep tins closed and labelled (a colour tag per grease). Never mix greases. Store used oil in a labelled closed drum; ask the Environmental Protection Authority how to dispose of it, because used-oil rules were not found.

Lubrication schedule form

Point Lubricant (name, grade) Method Quantity Interval Who Done

How to fill: copy lubricant name and grade from the manual; write the quantity as number of strokes or grams; tick on the date.

Tools and items: Unit 4

Item What it is and what it does Also called Size or type Caution
Clamp meter A meter whose jaws clamp round one wire and read the current without cutting it. Tong tester, clamp-on ammeter Hand-held Use only on cables you are allowed to measure; electrician for mains
Infrared thermometer See Level 1. Reads surface heat without touching. IR thermometer Hand-held Shiny metal reads low
Vibration pen or meter A device that shows how hard a machine shakes. Vibration meter Hand-held Use as a trend; compare with the machine's own baseline
Stethoscope (mechanic's) A rod or tube that carries bearing sound to the ear. Listening rod A long screwdriver also works Keep away from moving parts
Ultrasound detector A device that hears very high sounds from leaks and dry bearings. Ultrasonic leak detector Optional Needs training
Belt tension gauge A device that measures how hard a belt presses back. Belt tension tester Hand-held Use the belt maker's table
Straight edge A flat bar laid across two pulleys to check they line up. Alignment bar 1 m Lay it against the pulley faces
Torque wrench A wrench that clicks at a set tightness. Click wrench Set from the manual See the parts table below
Filter wrench A tool that grips a round filter to turn it. Oil filter wrench Strap or cup Engine cool
Bearing puller A tool with arms that draws a bearing off a shaft. Wheel puller By size Use the right size; do not hammer
Feeler gauge Thin steel blades of known thickness to measure a small gap. Thickness gauge Set of leaves Do not force
Dial indicator A gauge with a needle that shows a tiny movement. Dial gauge Hand-held Fix it firmly before use

Parts and safety: V-belt drive with guard

V-belt drive with guard Motor and driven machine with a V-belt, pulleys and guard, numbered parts 1 2 3 4 5 6 7 8
A motor driving a machine by V-belt, with a guard. Numbers on the picture match the table below.
No. Part What it does Safety rule
1 Motor Gives the turning power Locked out before any work
2 Motor pulley Carries the belt from the motor Check for chips and wear
3 Driven machine Receives the power Locked out too
4 Driven pulley Carries the belt to the machine Keep in line with the motor pulley
5 Deflection check Press the belt mid-span and measure the give Use the belt maker's table
6 V-belt Transmits the power by friction in the pulley grooves Replace the whole set together
7 Guard Covers belts and pulleys so hands cannot reach them Never run without it
8 Base and slots Let the motor slide to set the tension Re-tighten bolts after setting

Most belt problems start with the tension (too loose or too tight), then misalignment, then handling, hardware and the place. A trade source says a misalignment above about half a degree can shorten belt life, and that alignment should be checked before the final tension is set. This is a foreign trade article; read the belt maker's table.

V-belt checklist. (1) Machine locked out. (2) Guard off, kept safe. (3) Look for cracks, glazing, oil, frayed edges. (4) Pulleys: chips, wear, wobble. (5) Align pulleys with the straight edge. (6) Set the tension as the maker's table says. (7) Replace all belts of a set together. (8) Refit the guard before the restart.

Safety protocol: V-belt drive

Before. Stop and lock out (Unit 1). Release stored energy. Wear gloves. Let hot parts cool.

While you work. Take off the guard only when the machine is locked. Keep hands out of the pulley nip. Do not use a screwdriver to lever a belt over a pulley; slacken the motor instead. Do not over-tighten.

After. Refit the guard. Clear tools. Remove your lock. Run the machine for a minute and watch from a safe distance. Record the work.

Emergency. If a hand is caught, stop the machine at the emergency stop, call 112, do not try to pull it out.

Parts and safety: Clamp meter

Clamp meter Clamp meter with numbered parts 1 2 3 4 5
A clamp meter. Numbers on the picture match the table below.
No. Part What it does Safety rule
1 Jaws Clamp round one conductor to read the current Clamp one wire only, never a whole cable
2 Jaw trigger Opens the jaws Keep fingers behind the barrier
3 Display Shows the reading Read the unit
4 Range dial Chooses amps, volts or ohms Set before clamping
5 Hold button Freezes the reading Use when the reading is in a tight space

Safety protocol: Clamp meter

Before. Check the meter and leads for damage. Ask an Energy Commission-certified electrician to do or watch any measurement on mains wiring.

While you work. Do not open panels yourself. Keep one hand in your pocket if told to by the electrician. Do not exceed the meter's rating.

After. Switch off, store in its case, report damage.

Emergency. Electric shock: do not touch the person; switch off at the isolator if safe; call 112.

Parts and safety: Click-type torque wrench

Click-type torque wrench Click-type torque wrench with numbered parts 1 2 3 4 5 6
Click-type torque wrench (from the Auto Mechanics manual). Numbers on the picture match the table below.
No. Part What it does Safety rule
1 Handle (grip) Where you pull Pull smoothly; no pipe extension
2 Setting scale and barrel Shows and sets the torque Check the unit
3 Ratchet head Turns the socket and clicks Stop at the click
4 Square drive Holds the socket Match the drive size
5 Socket Fits the nut or bolt Right size
6 Lock ring Locks the setting Lock after setting

No torque number is printed in this book. Use only the maker's manual.

Safety protocol: Torque wrench

Before. Check the scale is readable and the wrench was stored at its lowest setting.

While you work. Set the value from the manual. Pull slowly and stop at the click. Do not use it to loosen, as a hammer or with a pipe.

After. Wind it back to the lowest setting and store it in its case.

Emergency. If a socket slips and hurts your hand, stop; for serious injury call 112.

Fault-finding trees (first checks only)

Isolate and lock out before any check. These give the order of first checks, not repair steps.

Symptom Check in this order
Does not start Is the supply on? Is the isolator on? Is the overload or breaker tripped (do not reset repeatedly)? Fuel and oil level? Is it jammed by hand? Call the electrician for electrical causes
Runs hot Oil or grease level, dirty cooling air, overload (current), belt too tight, blocked vents
Noisy Loose guard or bolts, dry bearing, belt slap, cavitation (pump), misalignment
Vibrates Loose base bolts, worn bearing, misalignment, an unbalanced part
Leaks Seal or gasket, loose fitting, cracked hose, overfull tank
Loses output Blocked filter or screen, worn belt slipping, air in the pump, low supply voltage
Trips the breaker Overload, damaged cable or motor, wet equipment; electrician only
Belt slips Tension, glazing, oil on the belt, worn pulley groove, overload

Failure modes by component (typical, ask the maker)

Component Typical failure modes Typical causes First check
Bearing Noise, heat, seizure Wrong or too little or too much grease, dirt, misalignment Grease, alignment, temperature
Belt Slip, crack, snap Wrong tension, misalignment, wear, oil Tension, alignment, look
Seal Leak Dry running, wear, wrong fit Suction valve, seal face
Coupling Wear, noise Misalignment, worn insert Gap, insert
Motor Hot, trips Overload, dirt, low voltage Current, vents, supply
Pump Low flow, noise Air, blockage, worn impeller Suction, strainer
Valve Sticks, leaks Dirt, wear Operation, seat
Hose Leak, burst Age, rubbing Look, replace
Filter Blocked Dirt Pressure drop, date
Battery Weak Age, low charge, bad terminals Terminals, voltage

5 whys and fishbone forms

Fishbone form A blank fishbone with six branches, numbered Effect People Method Machine Material Environment Measurement 1 2 3 4 5
A blank fishbone. Numbers on the picture match the table below.
No. Part What to write Rule
1 Upper bones People, method and machine causes Write facts, not blame
2 The spine The line that joins causes to the effect Draw it first
3 The effect (head) The fault in one line Name the fault, not a cause
4 Measurement bone Wrong or missing readings, bad gauges Check the instrument too
5 Lower bones Material and environment causes Circle the bone with the strongest facts, then ask five whys on it

Wrong way and right way. Wrong: "The pump failed. Why? The seal leaked. Fix: change the seal." (stopped at the symptom). Right: "Why did the seal leak? Ran dry. Why? Suction valve shut. Why? No step in the checklist. Fix: add the step." (stops at a cause you can fix, as in the example above).

5 whys form. Fault: ____. Why 1: ____. Why 2: ____. Why 3: ____. Why 4: ____. Why 5: ____. Root cause: ____. Action, who, date: ____. Check date: ____.

Condition-check trend sheet

Date Tag Temperature (point, C) Noise (word) Vibration (reading) Current (A) Pressure Hours Who

An alarm level is a change from the machine's own baseline. Take readings of a healthy machine first, then watch for a rising trend. Insulation testing and vibration limits are for qualified people and the maker's figures (see Level 3).

Find the cause

A mill belt snaps every month. Possible causes: wrong belt size; pulley out of line; belt too tight; no guard so dust gets in. (1) Put each cause under a fishbone bone. (2) Write a 5-whys chain starting from a belt that is too tight. (3) Cost: a snap costs GH¢80 for the belt and 3 hours at GH¢100 an hour. What is the yearly cost of 12 snaps?

Root cause investigation

  1. Pick a repeat fault from your history cards or a planted fault.
  2. Draw the fishbone with the team; list causes by bone.
  3. Choose the most likely cause and do a 5-whys chain.
  4. Check the facts: manual, records, parts, people.
  5. Write the failure report and the action.
  6. After two weeks, check if the fault has returned.

Why chain at home

Take a small repeat problem (the phone battery dies early, a tap drips). Write a 5-whys chain. What is the real cause, and what would you change?

Check yourself

  1. What is the common mistake with the 5 whys?
  2. Name three bones of a fishbone.
  3. Why trend heat and noise on the history card?
06

Unit 5 · Stores and buying

Money on the shelf is money you cannot use. A missing part is a machine you cannot use.

Competency standard

Learning outcome Performance criteria — the trainee…
5.1 Classify stock ranks items by yearly value and marks A, B, C
5.2 Mark critical spares holds a larger buffer for parts whose absence stops the business
5.3 Set reorder levels calculates a reorder point from usage, lead time and safety stock
5.4 Buy and receive compares quotes, issues a purchase order, checks goods in and records them

Range. At least 15 stock items. Evidence. ABC table; reorder levels; quotes comparison; receiving notes.

Ask a qualified expert. Fuel, oil, batteries, chemicals and gas cylinders need safe storage; ask a qualified safety officer and the Ghana National Fire Service. Fake or poor parts can cause fires or failures: for electrical parts ask an Energy Commission-certified electrician, and for lifting or pressure parts ask a GhIE-registered engineer. For tax on purchases (VAT), check with GRA or a qualified accountant.

ABC classes

Rank each item by annual value = yearly use × unit cost. Guides group items into bands, A with the highest value, and note that ABC class and criticality are two different things: a cheap C-class item can still be a critical spare.

Example (all figures examples).

Item Use a year Unit cost GH¢ Annual value GH¢ Share % Cumulative %
Bearings 20 50 1,000 22.7 22.7
Oil filters 30 30 900 20.5 43.2
Seal kits 6 120 720 16.4 59.5
V-belts 24 25 600 13.6 73.2
Grease cartridges 48 10 480 10.9 84.1
Fuses and bulbs 100 3 300 6.8 90.9
Gaskets 12 20 240 5.5 96.4
Assorted nuts and bolts 1 lot 160 160 3.6 100.0
Total 4,400

Our example cut-offs: A up to about 75% (bearings, filters, seals, belts); B to about 90% (grease, fuses); C the rest. Cut-offs vary between guides. Count A items often and keep tight records; count C items rarely.

Critical spares

A spare is critical if its absence stops an A machine for a long time, or its lead time is long. Keep at least one even if you have not used it yet. Critical parts need extra buffer even when cheap, and low-criticality parts with short lead times can have tighter buffers.

Reorder point

Reorder point = usage during lead time + safety stock. Keep the unit the same (months or weeks).

Example. Bearings: 20 a year = 1.67 a month. Lead time 3 weeks = 0.75 month. Usage in lead time = 1.67 × 0.75 = 1.25. Safety stock 2. Reorder point = 3.25, so order when 4 are left. Reviewing levels from time to time matters; the biggest mistake is setting them once and never again.

Quotes and purchase orders

For any buy above a limit you set, get three quotes in writing for the same item. Compare total cost delivered, not the shelf price: price plus transport, plus the quality and warranty offered.

Example (seal kit):

Supplier Price Transport Delivered total Delivery
1 GH¢110 GH¢20 GH¢130 3 days
2 GH¢120 included GH¢120 2 days
3 GH¢95 GH¢40 GH¢135 5 days

Supplier 2 is cheapest delivered and fastest. Prices are examples. A lower price is no bargain if the part is a poor copy; ask for the brand and the part number, and check them when the goods arrive.

A purchase order says what you ordered, from whom, quantity, price, delivery date and who approved. It stops "he said, she said".

Receiving

  1. Check the goods against the purchase order and the delivery note.
  2. Check the part number, quantity and condition. Reject damaged or wrong items.
  3. Record on the stock card; label and place in the bin.
  4. Keep the receipt and warranty paper with the work order or asset history.

Spare parts criticality (VED and lead time)

Classify each part by what happens if you have none: V vital (the machine or safety stops), E essential (output drops), D desirable (inconvenient). Then combine with lead time.

Short lead time Long lead time
High criticality (V) Keep a minimum; reorder on use Always keep stock
Low criticality (D) Order on demand Keep one if cheap; otherwise buy on demand

The long-lead insurance-spares rule is a vendor idea, not a standard.

Spares for a pump (example list). Seal kit, two bearings, impeller (if long lead), coupling insert, fuses, contactor, a spare belt set.

Spares criticality sheet.

Part Machine tag V, E or D Lead time (days) Min Max Supplier Bin

Reorder example (all numbers are examples). Use 2 a week, lead time 3 weeks, safety stock 3: reorder point = 2 × 3 + 3 = 9. Use real order-to-receipt times, not catalogue times.

Tools and items: Unit 5

Item What it is and what it does Also called Size or type Caution
Purchase order A written order to a supplier with items, quantity, price and date. PO One page Sign only with a quote
Goods received note A note that records what actually arrived and in what state. GRN One page Check against the order
Delivery note The supplier's list of what was sent. Waybill One page Compare, then sign
Quotation A written price. Quote One page Compare at least two
Warranty card A paper that states how long the supplier will fix faults. Guarantee Card Keep with the receipt
Stock count sheet A page to record counted stock against the card. Stocktake sheet One page Count with a second person
ABC table A list of parts sorted by yearly value. ABC list One page Review yearly
Reorder card A card that says when and how much to order. Min-max card Card Review
Critical spare tag A tag that marks a part that must not be used for anything else. Red tag Tag Replace at once after use

Reorder and ABC

(1) Filters: 30 a year (2.5 a month); lead time 2 weeks (0.5 month); safety stock 1. Reorder point? (2) Three quotes for a filter: GH¢28 + GH¢6 transport; GH¢30 delivered; GH¢25 + GH¢10 transport. Which is cheapest delivered? (3) Item X: 10 a year at GH¢40; item Y: 200 a year at GH¢2. Which has the higher annual value?

Classify and set levels

  1. List 15 stock items with yearly use and cost.
  2. Calculate annual values and rank them; mark A, B, C.
  3. Mark any critical spares, with a reason.
  4. Set reorder points for five items.
  5. Get three quotes for one part; make a comparison table; write a purchase order.
  6. Practice receiving goods against a delivery note.

Compare prices

Choose one item you buy often. Ask three shops for the price and note transport. Which is cheapest delivered? Which would you trust for quality?

Check yourself

  1. How do you work out annual value?
  2. What is the reorder point formula?
  3. Why compare delivered cost?
07

Unit 6 · Technicians and contractors

You are responsible for the job even when someone else does it.

Competency standard

Learning outcome Performance criteria — the trainee…
6.1 Decide in-house or contractor gives reasons based on skill, safety, equipment and cost
6.2 Write a scope and invite quotes writes a clear scope and compares at least three quotes
6.3 Control the work on site gives an induction, agrees isolation and a permit, and checks progress
6.4 Accept and close inspects against the scope, records defects and pays in stages

Range. One contracted job of 1 to 10 days. Evidence. Scope; quote comparison; induction record; acceptance form.

Ask a qualified expert. Contracts are legal documents. This is general information, not legal advice. Ask a qualified lawyer before you sign a contract of large value. Electrical work must be done by an Energy Commission-certified electrician. Engineering work in Ghana needs registered practitioners under the Engineering Council Act, and the Council notice warns against practising or endorsing engineering documents without registration. Lifting, pressure and structural work needs a GhIE-registered engineer. For taxes on payments (such as withholding tax), check with GRA or a qualified accountant.

In-house or contractor?

Decide whether specialist contractors should do the job, and do not take on work you are not prepared or competent for. High-risk or complex equipment may be best handled by the maker or a specialist contractor.

Question In-house Contractor
Do we have the skill? Yes No
Is it high-risk or specialist? No Yes
Is it a short job needing special tools? No Yes
Is it frequent and routine? Yes No

The five steps

HSE guidance on managing contractors gives five steps: plan the work, choose the contractor, work on site, keep a check, review.

  1. Plan. Write what you need and the risks.
  2. Choose. Ask for similar past work, references, proof that the person is competent (for example Energy Commission certification for electrical work, or Engineering Council or GhIE registration for engineering work). Do not choose only on price. Ask the Engineering Council or GhIE how to check registration; the full rules were not read here.
  3. On site. Give an induction: hazards, emergency exit, where to park, isolation, permit.
  4. Keep a check. Visit at agreed times; keep a daily note.
  5. Review. After the job, note what went well and badly, for the next time.

The scope of work

A good scope has: the goal; what is included; what is not; standards or manuals to follow; parts: who supplies; dates; price and payment stages; safety rules (isolation, permit, PPE); handover (tests, documents, clean-up); and a defect period during which the contractor fixes faults free.

Paying in stages

Example (all amounts are examples). A GH¢2,500 job. Pay 40% to start (GH¢1,000), 40% at a clear midpoint (GH¢1,000), and 20% (GH¢500) after you have inspected and accepted the work. Keep the last payment until the work passes the check. Get receipts.

Acceptance

Use the scope as a checklist. Test the machine under normal load, check the paperwork (manuals, warranty, test results), check the area is clean and safe, and write down any defects with a date to fix them. Sign only when satisfied. Do not use a repaired machine that has an open safety defect.

Tools and items: Unit 6

Item What it is and what it does Also called Size or type Caution
Scope of work A written list of what the job includes and excludes, the date and the price. Brief Half a page Both parties sign
Quote comparison sheet A table that puts quotes side by side. Bid comparison One page Compare like with like
Acceptance certificate A page the owner signs when the job matches the scope. Handover certificate One page Sign after the test run
Stage payment schedule A list of payments tied to finished stages. Payment plan One page Do not pay in full before the test
Contractor safety checklist A short check of the contractor's PPE, training and tools. Site induction One page Do it before work

Quote comparison sheet.

Item Contractor A Contractor B Contractor C
Price (example)
What is included
Start and finish dates
Past work seen
Warranty
Total and ranking

Acceptance certificate. Job and tag; scope items checked one by one; test run done (time); guards and signs back; tools removed; manuals and records handed over; punch list; signed by owner and contractor with date.

Compare quotes (example numbers)

Quote 1: GH¢2,400, 4 days, includes parts. Quote 2: GH¢1,900 labour only; parts about GH¢700 extra; 3 days. Quote 3: GH¢2,100 including parts; no references offered. (1) Total cost of quote 2? (2) Which is cheapest? (3) Which would you trouble to check further, and why? (4) Payment for 40, 40 and 20% on the cheapest total?

Run a contracted job

  1. Write a scope for a real or role-play job.
  2. Invite three quotes (role-play suppliers if needed) and compare them.
  3. Choose one and write why.
  4. Give an induction; agree isolation and a permit to work.
  5. Check progress; inspect at the end against the scope.
  6. Write the acceptance form and the review notes.

Scope for a small job

Write a half-page scope for a job at home, such as fixing a gate or painting a room. List what is included, what is not, dates, price and how you would pay.

Check yourself

  1. Name the five steps of managing a contractor.
  2. Why keep the last payment until acceptance?
  3. What does a scope say is NOT included?
08

Unit 7 · Maintenance as a service business

Many owners have machines and no time. Offer them peace of mind, in writing.

Competency standard

Learning outcome Performance criteria — the trainee…
7.1 Choose a location and customers names where and to whom a maintenance service can be sold
7.2 Package a service writes a monthly or yearly service offer with a clear scope
7.3 Price it works out costs and a price with a margin
7.4 Market it plans WhatsApp Business, Google Business Profile, signage, referrals and a portfolio
7.5 Plan for access notes accessibility adjustments

Range. One service offer for one customer type. Evidence. Service offer; price calculation; marketing plan.

Ask a qualified expert. This is general information on money, tax and law, not legal or tax advice. Ask a qualified lawyer about contracts and liability, check with GRA or a qualified accountant about tax and VAT, and ask your insurer or a financial adviser about insurance. For electrical, lifting, pressure and structural work refer to an Energy Commission-certified electrician or a GhIE-registered engineer; do not offer it yourself.

Location and customers

Good places have many machines and few maintenance managers: farms, hotels and guest houses, schools, clinics, bakeries and small mills, ice and water plants, workshops. In the Takoradi area, look at farms outside the city, fishing and processing sites, and the industrial and commercial areas. Check your Assembly's rules on where you can operate.

Service ideas

Service What you do
Equipment audit List equipment, mark A, B and C, report
Monthly check round Operator checks reviewed, history cards, one-page report
PM programme set-up Schedule, checklists and calendar
Stores set-up Label, stock cards, reorder levels
Contractor management Scopes, quotes, supervision and acceptance for an owner

Price it

Cost per visit = your time + transport + consumables. Price = cost ÷ (1 - margin). A 25% margin means you divide by 0.75.

Example (all numbers are examples). Annual agreement for a small mill: 12 visits a year, 3 hours each at GH¢60 an hour = GH¢2,160; consumables GH¢50 a visit = GH¢600; transport GH¢40 a visit = GH¢480. Total cost = GH¢3,240. Price at 25% margin = 3,240 ÷ 0.75 = GH¢4,320 a year = GH¢360 a month. Profit = 4,320 - 3,240 = GH¢1,080.

Do not underprice; repairs are extra and quoted separately. Say what is included (visits, report) and excluded (parts, major repairs, emergency calls).

Market yourself

  • WhatsApp Business: a profile with your services, hours and a catalogue.
  • Google Business Profile: your name, location, photos and reviews so people can find you.
  • Signage and a card: short, clear, with your service and name.
  • Referrals: ask satisfied customers for an introduction; thank them.
  • Portfolio: a one-page sample report (names removed), before and after photos with permission, and a short testimonial.

Registration

A business name at the Office of the Registrar of Companies costs GH¢130, with GH¢70 a year to renew (2026 fees). Ask the Assembly about an operating permit. For anything that needs engineering sign-off, work with a registered engineer.

Accessibility

The Persons with Disability Act, 2006 bans job discrimination. Audits, plans, registers, stock records, reports and customer contact are desk and phone work that suit wheelchair users and people with limited mobility. Deaf people can work with written orders, messaging and visual signals for lockout and permits. Adjustments help: large-print forms, a ground-floor store, and a clear route to machines. Tasks near running machines need a risk check person by person.

Tools and items: Unit 7

Item What it is and what it does Also called Size or type Caution
Service agreement A written contract for regular visits with price and scope. Maintenance contract Two pages Have a lawyer read it
Price list A sheet of your services and prices. Rate card One page Example prices only
Start-up costs sheet A table of what you must buy and pay to start. Budget One page Leave blank columns for real quotes
Invoice A bill sent to the customer. Bill Numbered Keep a copy

Start-up costs sheet (blank, Ghana quotes to be filled). Registration; Assembly permit; tools; PPE; transport; phone and data; insurance (ask a broker); first stock; sign and cards; working money for three months. Columns: item, quote from, date, price.

Price an agreement (example numbers)

A guest house wants a monthly check: 2 visits a month, 2 hours each at GH¢60 an hour, transport GH¢40 per visit, consumables GH¢30 per visit. (1) Monthly cost? (2) Price at 20% margin? (3) Yearly price?

Write a service offer

  1. Choose a customer type and a place.
  2. Write the offer in half a page: what is included and excluded.
  3. Calculate cost and price with a margin.
  4. Draft a WhatsApp Business profile text and a one-line sign.
  5. Pitch it to your trainer in two minutes.

Visit a customer

Visit a hotel, clinic or school (with permission) and ask who looks after the machines. Write what they would pay for.

Check yourself

  1. How do you calculate a price from a cost and a 25% margin?
  2. Name two things to leave out of a monthly agreement.
  3. Name two ways to market a maintenance service.
09

Glossary

Term Meaning
ABC classes Groups of stock by annual value
Acceptance certificate A signed page that says the job matches the scope
Alignment Two pulleys or shafts lying in one line
Condition-based task A task done when a measure shows a need
Isolation certificate A page that records the energy cut and the locks
NLGI grade The stiffness number of a grease
PM compliance PM work orders done on time ÷ PM work orders due
Reactive work Work done after a failure, not planned
Schedule compliance Hours done as scheduled ÷ hours scheduled
VED Vital, essential, desirable: how badly a stockout hurts
Backlog Work waiting to be done
Contingency Extra money kept for surprises
Critical path The longest chain of tasks that sets the job length
Failure mode One way a part can fail
FMEA A method that scores failure modes
Float Spare time a task can slip
Job plan Steps, parts, tools and safety prepared before work
Lead time Time from ordering to delivery
Permit to work A written permission with hazards and precautions
Reorder point Stock level at which you order again
Root cause The cause that, once fixed, stops the fault returning
RPN Severity × occurrence × detection
Scope A written list of what a job includes and excludes
Wrench time Share of the day a technician spends doing the job

A note on names. Local names for tools differ from town to town. Use the standard name given in this book, in the Tools and items tables and in Appendix H, when you order or ask for help, and show the picture.

10

Logbook

Copy these pages into an exercise book. Your logbook is part of your assessment evidence.

  • Unit 1: criticality table; failure mode table; programme sheet
  • Unit 2: task list; bar chart; critical path; budget; permit
  • Unit 3: register; weekly backlog sums; meeting notes
  • Unit 4: fishbone; 5 whys; failure report; follow-up
  • Unit 5: ABC table; reorder levels; quotes; purchase order
  • Unit 6: scope; quote comparison; induction; acceptance form
  • Unit 7: service offer; price calculation; marketing plan
  • Every homework, dated
11

Self-check quiz

  1. How is RPN worked out?
  2. Why look at severity on its own?
  3. What is the critical path?
  4. A task has 3 days of float. What does that mean?
  5. Give the formula for backlog in weeks.
  6. What is the common mistake with the 5 whys?
  7. What is annual value in ABC classes?
  8. Give the reorder point formula.
  9. Why compare delivered cost?
  10. Name the five steps for managing a contractor.
  11. Why keep the last payment until acceptance?
  12. A job costs GH¢3,000 and you want a 25% margin. What is the price?
12

Appendix A · Forms for the supervisor

Ask a qualified expert. Forms are records, not permission to do dangerous work. Electrical, gas, lifting, pressure and structural work needs an Energy Commission-certified electrician or a GhIE-registered engineer. Ask a qualified lawyer before you use a contract form.

Level 1 forms (work order, asset register, PM schedule, daily check, downtime log, history card, monthly report, stock card, near-miss note) stay in use. Level 2 adds:

  • Failure report. Machine and tag; date; what happened (failure mode: what was seen); cause (why); mechanism (the physical process such as wear, corrosion, fatigue); downtime; cost; 5 whys; root cause; action; who and when; check date.
  • Spares criticality sheet, lockout sheet, permit to work, quote comparison and acceptance certificate: in Units 2, 5 and 6.
  • Weekly planning agenda and work order register columns: in Unit 3.

Lockout sheet for one machine.

Tag Energy sources (electric, fuel, water, pressure, stored) Where to isolate Lock points Test method Who may lock out

How to fill: walk the machine with the technician; list every source; add a photo.

13

Appendix B · Formula sheet

Checked by script. All numbers are examples.

Measure Formula Example
Reactive work share Breakdown hours ÷ total maintenance hours × 100 10 ÷ 40 = 25%
OEE Availability × performance × quality 0.90 × 0.95 × 0.99 = 84.6%
Availability (OEE) Run time ÷ planned production time 0.90
Performance (OEE) Ideal cycle time × total count ÷ run time 0.95
Quality (OEE) Good count ÷ total count 0.99
Mean downtime (Repair time + waiting time) ÷ number of stops (9 + 3) ÷ 3 = 4 h
Failure rate 1 ÷ MTBF 1 ÷ 80 = 0.0125 per hour
Backlog weeks Backlog hours ÷ weekly capacity 120 ÷ 40 = 3
Reorder point Lead time × usage + safety stock 3 × 2 + 3 = 9
Repeat failure cost (Part + labour + lost hours × rate) × failures (350 + 6 × 120) × 4 = GH¢4,280

OEE is often quoted as 85% for "world-class" in discrete manufacturing; the idea is vendor-based and foreign. The ideal cycle time must be the nameplate speed; if you reset it you change the answer a lot. This is a trap.

14

Appendix C · Typical PM interval table

Ask a qualified expert. The maker's manual always wins. Do not use a figure from a table instead of the manual, or in place of an Energy Commission-certified electrician, a GhIE-registered engineer or the maker.

Machine Typical task Interval
Diesel generator (prime duty) Oil and filter change Commonly about 250 hours; typical only, check the engine manual
Diesel generator (standby) Oil and filter change About 250 to 500 hours or yearly; typical only
Generator on very light load Run under load Light load invites wet stacking; check the manual
Pump, mill, compressor, vehicle, freezer Task Read from the maker's manual; no figure from a vendor
15

Appendix D · Ghana equipment and failures

Public data on Ghana failure modes is thin. Items below are general; the checks are first checks only. De-Graft's own rules of thumb are not added here.

Site Typical assets Common Ghana conditions to plan for
Farm Borehole pump, irrigation pump and engine, tractor, sprayer, generator, freezer or cold room, feed mixer, maize mill, water tank, electric fence Dust, heat, poor fuel, low or high voltage, power cuts
Workshop Welding machine, grinder, drill press, compressor, lathe, hoist Dust, damp, voltage swings
Small factory Hammer or corn mill, packaging machine, boiler or steamer, conveyor, generator, main panel Dust, voltage swings, wear

Reports say that long breakdowns of Ghana's tractors came from limited mechanical knowledge, few trained mechanics and hard-to-find spare parts. Reports also say Accra districts had long hours of low voltage or overvoltage in 2024 and that low voltage damaged a school corn mill. Ask an Energy Commission-certified electrician about protection (a phase failure relay, voltage guard, surge protection).

16

Appendix E · Common mistakes (management)

Mistake Fix
Reporting PM compliance as schedule compliance Say which one
Stopping 5 whys at a symptom Ask until you reach a fixable cause
Tightening a belt too hard Use the maker's table
Buying on the lowest price Compare quotes by quality too
Paying in full before the test run Pay by stages
Not freezing the work list Freeze it and manage changes
Over-greasing Use the manual's amount
17

Appendix F · Cases

  • A repeat belt failure. A belt failed again and again. The fix was the tension and alignment, which a trade source ranks as the first and second causes of belt trouble.
  • A tractor fleet that fell from nine working machines to two shows what happens when spares and mechanics are missing.
  • A school mill damaged by low voltage shows why supply faults need protection.
18

Appendix G · Failure-mode word guide

Failure mode = what was seen. Cause = why. Mechanism = the physical process. Use all three so two failures with the same symptom are not confused. The standard text was not opened; check the exact words.

19

Appendix H · Tools and Items Glossary

Local names for tools differ from town to town. Use the standard name given here when you order or ask for help, and show the picture.

Name Meaning Also called Used for Warning Unit
Acceptance certificate A signed handover page Handover certificate Closing a contract job Sign after the test 6
Belt tension gauge Measures how hard a belt presses back Tension tester Setting belt tension Maker's table 4
Bearing puller Draws a bearing off a shaft Wheel puller Removing bearings Right size 4
Clamp meter Reads current round one wire Tong tester Current check Electrician for mains 4
Dial indicator Needle gauge for tiny movement Dial gauge Checking run-out Fix firmly 4
Delivery note Supplier's list of goods sent Waybill Checking deliveries Compare then sign 5
Feeler gauge Thin blades for gaps Thickness gauge Small gaps Do not force 4
Filter wrench Grips a filter Oil filter wrench Changing filters Engine cool 4
Flip chart Large paper pad Chart pad Planning None 2
Goods received note Record of what arrived GRN Receiving Check against order 5
Grease nipple Entry valve for grease Zerk fitting Greasing Clean first 4
Infrared thermometer Non-contact thermometer Temperature gun Heat check Shiny metal reads low 4
Isolation certificate Record of isolation Isolation record Safe work Attach to permit 2
Lockout station Wall board for locks and tags Lockout board Storing lockout items Count weekly 2
Permit to work Written permission for a risky job Work permit Controlled work Not safe by itself 2
Purchase order Written order to a supplier PO Buying Sign with a quote 5
Quotation Written price Quote Comparing Compare two or more 5
Stethoscope (mechanic's) Rod that carries bearing sound Listening rod Bearing sound Away from moving parts 4
Straight edge Flat bar for alignment Alignment bar Pulley alignment Against faces 4
Torque wrench Clicks at set tightness Click wrench Tightening to the maker's value Back to lowest setting 4
Ultrasound detector Hears high sounds from leaks Ultrasonic detector Leaks, dry bearings Needs training 4
Vibration meter Shows how hard a machine shakes Vibration pen Trend Compare to baseline 4
Warranty card Paper stating the guarantee Guarantee Claims Keep with receipt 5
20

Further reading and sources

Best next reads: the free HSE page on maintenance of work equipment; the HSE guide to managing contractors; your machines' own manuals.

What this module does not cover: repair of particular machines; electrical, gas, lifting and pressure work; civil works, site supervision, quantity estimating and permits (Civil Engineering); condition-monitoring instruments in depth; and Ghana prices for parts, labour and contractors (not found; all prices here are examples).

Every source used in this manual is listed, with links, in the Teacher Copy.

One application of the Cold-Start Learning Kit, which stays general-purpose and can build a guide on any topic in any field. Written in CTVET format; not a CTVET curriculum.