← All training manualsEngineering Project and Maintenance Management Level 3 · read-onlyGet the PDF with Teacher Copy (GH¢50)
Level 3 · Advanced · CTVET formatTrainee Manual

Engineering Project and Maintenance Management Level 3

Strategy, shutdowns and your own business. Plan asset care, run a shutdown, report with numbers, lead safe work and a team, then register, keep the books and grow a maintenance business.

A technician with a clipboard beside a pump, a tool store and a wall planner A technician in a helmet and overalls holds a clipboard with a work order checklist beside a water pump on a concrete base. To the left, a wall planner with a monthly grid and ticks. To the right, a parts shelf with labelled boxes and a spanner rack. PLAN · SCHEDULEWORK ORDER · LOGSPARE PARTS STORE
Trainee name
Training centre
Business or site
Start date
Prepared by De-Graft Afful · Version 1.1.0 · November 2026
01

About this module

At Level 2 you ran a programme. At Level 3 you are trusted with the whole picture: what to look after and how, what it costs, what the numbers say, and how to earn from it.

Who it is for. People who have finished Engineering Project and Maintenance Management Level 2, or who can show the same skills. In Ghana's framework, National Proficiency II leads to National Certificate I. This module is written at about that level and works out which of the skills you already have. It is not a CTVET curriculum.

CTVET status. CTVET has competency-based training for many engineering trades, but its unit list for maintenance management was not found online. This module is not that curriculum, and it does not certify you as an engineer, technician or inspector. Ask CTVET or the regional Ghana TVET Service office for the current standard.

Ask a qualified expert. This module teaches management. For electrical work use an Energy Commission-certified electrician. For lifting equipment, pressure vessels, structures, or anything that could fall or burst, ask a GhIE-registered engineer. For law, tax and money questions ask a qualified lawyer, GRA or a qualified accountant.

Bridge from Level 2: what you already know

  • Criticality scores, failure modes, RPN and preventive tasks with intervals
  • Task lists, critical path, float, bar chart, budget with contingency, permit to work
  • The work order register, backlog in weeks, overdue share, the weekly planning meeting
  • 5 whys, fishbone, failure reports and cost of a repeat failure
  • ABC stock classes, critical spares, reorder points, quotes, receiving
  • In-house or contractor, scopes, staged payment, acceptance
  • Pricing a maintenance service with a margin; WhatsApp Business, Google Business Profile, portfolio

Level 2 did not teach choosing a strategy by equipment class, life-cycle cost, shutdown planning with risk registers, trend reports and cost per operating hour, a lockout programme and compliance register, training matrices, registering and employing for a business, the accounts of a business, or the capstone plan. This manual does. For general bookkeeping and business skills see the Hub's Money Skills Level 2 and Entrepreneurial Thinking Level 2; this book goes deeper and stays in maintenance.

How the module works

Each unit has learning outcomes, performance criteria, the range and the evidence your assessor needs. You are judged Competent or Not Yet Competent. About 70% of the time is practical, following CTVET's Oil Palm programme split of about 30% school and 70% workplace.

02

Unit 1 · Maintenance strategy and asset care plans

The right care for each machine is different. A strategy says which care for which machine, and why.

Competency standard

Learning outcome Performance criteria — the trainee…
1.1 Choose a strategy per class picks run-to-failure, time-based, condition-based or redesign for each equipment class and justifies it
1.2 Write an asset care plan writes a one-page plan with tasks, spares, skills, safety and measures for each A asset
1.3 Compare life-cycle cost adds purchase, running, maintenance and resale value for two options
1.4 Decide repair or replace uses cost, risk and availability to recommend

Range. At least three A assets and one buying decision. Evidence. Strategy table; care plans; life-cycle sums.

Ask a qualified expert. Strategy does not override the law or the maker's instructions. Lifting equipment, pressure vessels and structures need a GhIE-registered engineer; electrical equipment needs an Energy Commission-certified electrician. Where a cost sum conflicts with safety, safety wins. For asset values in accounts, check with a qualified accountant.

Four strategies

Strategy Use when Example
Run to failure Cheap, easy to replace, no safety risk, no stock problem Office fan, standard bulb
Time or use-based preventive Wear is predictable and the task is cheap Oil change every set hours; belt every season
Condition-based A warning sign appears before failure Heat, noise, vibration or leaks trended on the card
Redesign or improve The same failure keeps happening Add a guard, a filter or a better support

Your Level 2 criticality ranking and root-cause work tell you which class each machine is in. A Ghana study of manufacturers found that preventive shutdown maintenance was the most preferred approach, but also weak organised staff training and little use of high-end tools. Many small sites can move from "wait for it to fail" to simple condition checks without costly tools.

Asset management in one paragraph

ISO 55000 is an international overview standard for asset management, and its 2024 edition applies to organisations of any size; ISO 55001 holds the requirements and ISO 55002 the guidance. A small business does not need to certify. The idea to take is that assets exist to deliver value: you decide what to maintain, replace or improve by looking at cost, risk and performance together. This module does not teach the standard in detail.

Operators care too

A common approach called total productive maintenance gets operators to do basic cleaning, checks and lubrication so that technicians can do the skilled work. This is general maintenance practice and is not verified in a source here. In practice it is your Level 1 daily check, made normal for everyone.

The asset care plan

One page per A asset:

Section Content
Asset and tag; owner Name, tag, who is responsible
Why it is critical Safety, production, repair effort scores
Failure modes and risks Top three, with RPN
Tasks Daily operator check; scheduled tasks; condition checks
Spares Critical spares, minimum, supplier, lead time
Skills Who can do the work; who is a specialist; contractor name
Safety Isolation points, permit needed, hazards
Measures Availability, MTBF, MTTR; target and trend
Review date When the plan is reviewed

Life-cycle cost

The cheapest machine to buy is not always the cheapest to own. Add: purchase price + running and maintenance costs over the life, minus resale (salvage) value. This simple sum ignores the time value of money and fuel or power price changes; for a large purchase ask a qualified accountant.

Example (all numbers are examples). Option A: price GH¢8,000, running and maintenance GH¢2,000 a year, life 5 years, resale GH¢1,000. Option B: price GH¢6,000, running and maintenance GH¢3,200 a year, life 5 years, resale GH¢500.

  • A: 8,000 + 5 × 2,000 - 1,000 = GH¢17,000, or GH¢3,400 a year.
  • B: 6,000 + 5 × 3,200 - 500 = GH¢21,500, or GH¢4,300 a year.

Option A costs GH¢2,000 more to buy but GH¢4,500 less over five years.

Repair or replace

Ask: What does the repair cost, and how long will it last? How often has this machine failed (history card)? What would a new one cost, and does it fail less? Is a safe, available spare part still on sale? What does downtime cost per day? Some people use a rule of thumb that replacement should be considered when repair cost passes about half of the cost of a new machine; this is not verified here, so treat it as a prompt for discussion, not a law.

Strategy decision table: which task for which failure

Failure type Choose Example
Warning sign appears before failure On-condition task (inspect, measure, trend) Bearing heat and noise
Failure is age-related, task is cheap Scheduled replacement Belt every season
A hidden protective device may have failed and you would not know Failure-finding task (test the device) Test a trip or alarm
Same failure keeps coming back Redesign or improve Add a filter or a guard
Cheap, safe and easy to replace Run to failure Bulb

Failure patterns. Nowlan and Heap's 1978 reliability-centred maintenance study for the US Department of Defense described six patterns of failure over time. Only a small minority of items showed a clear wear-out age, and the other patterns have none, so replacing parts by the calendar often wastes money. The percentages differ between secondary sources and the primary report was not opened; the data came from aircraft, so do not apply it blindly to farm machines.

Risk matrix (5 × 5). Score likelihood 1 to 5 and impact 1 to 5, multiply. Example: L4 × I3 = 12. Rank assets by the score instead of by guess. A safety risk is never ranked below a money risk.

Total productive maintenance (TPM). TPM is a Japanese approach in which operators share the care of the machine. The list of its pillars was not verified here; check a TPM text before teaching it.

Terms. EN 13306 defines the maintenance words (preventive, corrective, condition-based, predetermined and others); the standard text was not opened, so the exact wording is not quoted.

Tools and items: Unit 1

Item What it is and what it does Also called Size or type Caution
Insulation tester A meter that applies a test voltage to find if insulation is breaking down. Megger, insulation resistance tester Hand-held, with test voltages set by the maker Used only by an Energy Commission-certified electrician
Phase failure relay A device that cuts a three-phase motor when a phase is lost. Phase monitor, voltage guard Panel mounted Fitted by a certified electrician
Surge protection device A device that diverts a voltage spike away from a machine. Surge arrester Panel or socket type Fitted by a certified electrician
Power quality meter A meter that records voltage, current and supply faults over days. Power analyser Portable Use only with an electrician
Earth tester A meter that measures the resistance of an earth connection. Earth resistance tester Portable Certified electrician only
Thermography survey A check of hot spots using a thermal camera. Thermal imaging Camera Done by a trained person
Oil analysis kit A lab test of a used-oil sample for wear metals and dirt. Oil sample kit Sample bottles Label samples
Asset care plan A one-page plan for each A asset. Care plan One page Review yearly

Parts and safety: Insulation tester (method only)

Insulation tester (megger) Insulation resistance tester with leads, numbered parts 1 2 3 4 5 6 7
An insulation tester. Numbers on the picture match the table below.
No. Part What it does Safety rule
1 Display Shows the resistance reading Read after the time the maker says
2 Range or voltage selector Chooses the test voltage Choose the voltage the maker gives
3 Test button Applies the test voltage Press only when the circuit is isolated and dead
4 Dial or hold Holds or steps the reading Do not touch the leads during the test
5 Terminals Where the leads connect Check lead insulation
6 Line lead Goes to the conductor Clip on while the instrument is off
7 Earth lead Goes to the frame or earth Clip on first

Method (no limits are printed). (1) The certified electrician isolates, locks out and proves the circuit dead. (2) The machine is disconnected from electronic parts. (3) The leads are connected. (4) The test voltage the maker or the electrician names is applied. (5) The reading is taken at the time given (often one minute) and the winding temperature is noted. (6) The circuit is discharged before the leads are removed. (7) The reading is compared with the maker's figure and with the machine's own earlier readings. Sources on the minimum values conflict, so no minimum is printed. Read the motor maker's figure, or ask an Energy Commission-certified electrician.

Safety protocol: Insulation tester

Before. Only an Energy Commission-certified electrician does this. Isolate and lock out, prove dead, and discharge. Wear insulated gloves and boots.

While you work. Do not touch the leads or the machine during the test. Keep others away. Keep the test short.

After. Discharge the circuit, remove the leads, reconnect the machine only after the electrician says so, record the reading.

Emergency. If a person gets a shock, do not touch them; switch off at the isolator if safe; call 112.

Parts and safety: Phase failure and voltage relay

Phase failure and voltage relay Three-phase monitoring relay with numbered parts 3-phase supply Contactor coil 1 2 3 4 5 6 7 8
A phase failure relay. Numbers on the picture match the table below.
No. Part What it does Safety rule
1 Three-phase supply terminals Take the three supply lines Isolate before touching
2 Phase indicator lamps Show each phase present Dark lamp means a phase is lost
3 Contactor coil terminals Switch the motor starter coil Wired by an electrician
4 Voltage setting dial Sets the low and high voltage limits Set to the machine's rating
5 Delay dial Waits before restarting after the supply returns Do not set to zero
6 Reset Restarts after a trip Look for the cause first
7 Earth and cover Safe cover and earth Never run without the cover
8 Mounting clip Holds it in the panel Check it is firm

Reports say Ghana's low voltage and overvoltage damaged machines in 2024 and 2026. A relay is one protection among others; ask a certified electrician what suits your supply.

Safety protocol: Phase failure relay

Before. Isolate and lock out. Only a certified electrician opens the panel.

While you work. Do not bypass the relay to keep a machine running. Set limits from the machine rating.

After. Test with the electrician, record the settings on the asset care plan.

Emergency. Burning smell or sparks: switch off at the main isolator if safe, keep away, call the electrician and 112 if fire.

Parts and safety: The asset care plan form

Asset care plan form A one page asset care plan with numbered boxes ASSET CARE PLAN 1 2 3 4 5 6 7
An asset care plan. Numbers on the picture match the table below.
No. Box What to write Rule
1 Asset, tag and owner Name, tag, person responsible One owner
2 Why critical Safety, production and repair scores Give the score
3 Failure modes and risks Top three, with scores Use the 5 × 5 matrix
4 Tasks Operator check, scheduled tasks, condition checks From the manual
5 Spares and skills Critical spares, supplier, who can do it Name the contractor
6 Safety Isolation, permit, hazards Link the lockout sheet
7 Measures and review Availability, MTBF, MTTR, trend, review date Review yearly

Repair or replace: worked form

Line Repair Replace
Cost now
Expected extra life (years)
Running and maintenance per year
Downtime per year (hours)
Resale
Life-cycle cost per year

Rule. If a safety limit is met, stop and replace or call a GhIE-registered engineer, whatever the cost sum says. The "half the cost of a new one" rule stays not verified.

Compare two machines (example numbers)

Pump X: price GH¢4,000; running and maintenance GH¢1,500 a year; life 6 years; resale GH¢400. Pump Y: price GH¢3,000; running and maintenance GH¢2,100 a year; life 6 years; resale GH¢200. (1) Life-cycle cost of each? (2) Cost per year? (3) Which is cheaper to own and by how much over the life?

Write a strategy and two care plans

  1. List your equipment classes (pumps, engines, mills, electrical, tools, vehicles).
  2. Choose a strategy for each class; write one line of reasons.
  3. Write a one-page care plan for two A assets.
  4. Work out the life-cycle cost for a real buying decision.
  5. Present your strategy to a visitor or the trainer for five minutes.

Own it for five years

Pick something you own or plan to buy (phone, bicycle, generator). Estimate price, yearly running cost and resale value. What does it cost over five years?

Check yourself

  1. Name the four strategies.
  2. What goes into life-cycle cost?
  3. Does a cost sum override a safety rule?
03

Unit 2 · Plan shutdowns and equipment projects

A shutdown is a few days when everything must go right. The plan is the work.

Competency standard

Learning outcome Performance criteria — the trainee…
2.1 Define the scope writes a work list, freezes it by a date and records changes
2.2 Load resources and schedule matches hours of work to people and days available
2.3 Budget and risk prepares a budget with contingency and a risk register
2.4 Commission and hand over tests, records results and hands over with documents

Range. A shutdown or equipment replacement of 2 to 10 days. Evidence. Work list; schedule; budget; risk register; handover pack.

Ask a qualified expert. Shutdown work concentrates danger: many people, locked-out machines and hot work. Electrical work needs an Energy Commission-certified electrician. Lifting, pressure and structural work needs a GhIE-registered engineer. Plan work for downtime so it does not clash with production, and use signs and barriers to protect others. This module does not teach building or civil works planning, which belongs to Civil Engineering.

Scope and the work list

A shutdown is a planned stop of a plant or part of it so that work can be done. Collect jobs from: the work order register, preventive tasks due, condition-check findings, and requests from operators. Check each is real; decide in or out; write estimated hours, parts, skills and any permit. Freeze the list a set time before the shutdown (for example one week) so late additions go through a change decision, not a quiet squeeze.

Load the resources

Compare hours of work with hours of people available. Planning guides break a job into tasks, estimate each and then fit them into a schedule using the critical path and float. Then add the people: if the work is more than the hours, you must add people, add days, or cut work.

Example (all numbers are examples). A 2-day plant shutdown. In-house work list: mill bearings 12 h; drive belts 6 h; pump overhaul 16 h; generator service 8 h; guard repairs 6 h; cleaning 10 h. A certified electrician does an electrical inspection separately (8 h, contractor).

  • In-house total = 12 + 6 + 16 + 8 + 6 + 10 = 58 hours.
  • Available: 4 technicians × 8 hours × 2 days = 64 hours. Loading = 58 ÷ 64 = 90.6%.
  • Add 15% for surprises: 58 × 1.15 = 66.7 hours. This is more than 64, so the shutdown needs a third day, one more person, or a job moved out.
  • Labour cost at GH¢150 per person-day: 58 ÷ 8 = 7.25 person-days × 150 = GH¢1,087.50.

The budget

Parts and materials; labour (own and contract); hire (a hoist or special tools; ask a registered engineer about lifting); transport; consumables; permits and inspections; contingency (about 10 to 15%, a rule of thumb); and the cost of lost production if the plant is stopped. Compare the cost of the shutdown with the cost of the breakdowns it prevents, using your history cards.

The risk register

A risk register lists what could go wrong, how likely (1 to 5), how bad (1 to 5), the score (likelihood × impact), what you will do, and who owns it.

Risk L I Score Action Owner
Spare bearing arrives late 3 4 12 Order now; ask supplier for a date; keep the old one Stores
Rain delays outdoor work 3 2 6 Plan indoor tasks first; tent Supervisor
Technician injured 2 5 10 Lockout, permits, PPE, first-aid kit Supervisor
Electrician unavailable 2 4 8 Book early in writing; second name Manager

Review it daily during the shutdown.

Daily control

Run a 10-minute meeting each morning and evening: what was done, what is late, what changed, safety issues. Update the bar chart. Keep a log of changes and who approved them.

Commissioning and handover

Before the machine returns to work: remove tools and rubbish; refit guards; remove locks one by one by their owners; check the area; test run in stages (empty, then load); record readings (temperature, noise, leaks, current if an electrician measures it). Hand over to operators with a written note of what changed and any new checks, update the history cards and spares, and hold a short review: what went well, what to change.

Tools and items: Unit 2

Item What it is and what it does Also called Size or type Caution
Chain block A hand hoist with a chain loop that lifts a load by pulling the chain. Chain hoist, hand hoist Rated in tonnes Never exceed the safe working load
Sling A strap, rope or chain loop that holds a load for lifting. Lifting sling Rated Inspect before use; never use a damaged one
Shackle A U-shaped link with a pin that joins slings and hooks. Bow shackle Rated Pin fully screwed
Hook The lifting hook with a safety latch. Lifting hook Rated Latch must close
SWL tag A tag that states the safe working load. Safe working load tag Metal tag Do not lift above it
Register of lifting equipment A list of every lifting item with its tag and examination dates. Lifting register Book or sheet Required in each factory under Act 328 s.47
Work list The frozen list of jobs for a shutdown. Job list Spreadsheet Freeze, then control changes
Risk register A table of risks with scores and owners. Risk log One page Review each day
Commissioning checklist A list of checks before handing a machine back. Handover checklist One page Sign each line
Handover pack Manuals, drawings, readings and a change note given to operators. As-built pack Folder Update history cards

Parts and safety: Chain block and sling

Chain block hoist with sling Hand chain block, hook, sling and shackle, numbered parts tag SWL ____ 1 2 3 4 5 6 7 8
A chain block with a sling and shackle. Numbers on the picture match the table below.
No. Part What it does Safety rule
1 Anchor beam Fixed support the hoist hangs from A GhIE-registered engineer confirms it can carry the load
2 Top hook Hangs the block from the beam Latch closed
3 Block body Holds the gears and wheel Check for cracks
4 Hand chain Pulled to lift or lower Pull smoothly, stand clear
5 Load chain Carries the load Check for stretch, twists and rust
6 Bottom hook Holds the sling Latch closed
7 Sling and shackle Hold the load Rated and inspected
8 SWL tag States the limit Never lift above it

Safety protocol: Chain block and sling

Before. Check the SWL tag and the load weight. Inspect chain, hooks, latches, sling and shackle. Clear the area below. Ask a GhIE-registered engineer about the support.

While you work. Lift a little, stop and check. Keep everyone out from under the load. Do not lift people. Do not side-pull. No sudden jerks.

After. Lower the load to firm support before unhooking. Store the block and slings dry. Record in the lifting register. Report damage and take it out of use.

Emergency. A load that slips: stand clear, raise the alarm, call 112 for injury. Do not walk under a suspended load.

Shutdown work list and risk register

No. Job Tag Hours Skills Parts Permit needed Risk score

Risk register. Risk; cause; likelihood (1 to 5); impact (1 to 5); score; action; owner; due date.

Commissioning checklist. Tools and rubbish removed; guards refitted; locks removed by their owners; area clear; empty run; run under load; readings noted; leaks checked; operators briefed; history card updated; spares and manuals handed over; sign-off by operator and supervisor.

Handover pack. Change note; as-built details; manual set; test readings; new checks; spare parts list; review date.

Load the shutdown

A 3-day shutdown. Work list (in-house): 10 h, 14 h, 20 h, 6 h, 12 h, 8 h. Crew: 3 technicians, 8 h a day. (1) Total hours? (2) Hours available? (3) Loading %? (4) Total with 10% contingency, and does it fit? (5) A risk is scored L4 and I3. Score?

Plan a shutdown

  1. Collect a work list from the register and PM schedule.
  2. Estimate hours, parts, skills and permits for each job.
  3. Freeze the list; load resources; adjust.
  4. Draw the bar chart; mark the critical path.
  5. Write the budget and a risk register of at least five risks.
  6. Plan the commissioning and handover; present the plan.

Spring clean as a shutdown

Plan a one-day deep clean of your home or room like a shutdown: work list, people, hours, risks and a finish check.

Check yourself

  1. Why freeze the work list?
  2. What do you do if the work is more than the hours available?
  3. How is a risk score worked out?
04

Unit 3 · Measures, data and management reports

Numbers do not repair machines. They tell you where to point the people who do.

Competency standard

Learning outcome Performance criteria — the trainee…
3.1 Gather clean data records downtime, hours, work orders and costs the same way every time
3.2 Calculate measures works out MTBF, MTTR, availability, planned share, PM compliance and cost per hour
3.3 Read the trend compares three months and explains the change
3.4 Report to management writes a one-to-two-page report with a decision request

Range. Three months of data for at least two A assets. Evidence. Calculation sheet; report; oral defence.

Ask a qualified expert. Cost records feed your accounts and tax returns. This is general information, not tax or financial advice. Check with GRA or a qualified accountant. Measures are not a reason to skip safety work: a good-looking number never overrides a missing guard or an unsafe machine.

The measures

Measure Formula
MTBF Operating time ÷ number of failures
MTTR Total repair time ÷ number of repairs
Availability (Scheduled time - downtime) ÷ scheduled time × 100
Planned share (PMP) Planned maintenance hours ÷ total maintenance hours × 100
PM compliance Preventive tasks done on time ÷ tasks scheduled × 100
Overdue share Overdue work orders ÷ open work orders × 100
Maintenance cost per operating hour Total maintenance cost ÷ operating hours

The first four formulas, PM compliance and the overdue share are described on a maintenance metrics page; PM compliance and the overdue formula are stated there as standard usage rather than given on the page. Targets differ between sources: one source gives 70% to 85% for the planned share, others quote above 85% or 90% for world-class, and MTTR and availability targets vary too. So compare your own months with each other.

Leading and lagging. PM compliance and planned share look forward: they predict trouble. MTBF, MTTR and downtime look back: they say what already happened.

A three-month example (all numbers are examples)

An irrigation pump scheduled 240 hours a month.

Month 1 Month 2 Month 3
Failures 4 3 1
Downtime (h) 16 9 2
Planned hours 20 30 36
Total maintenance hours 50 45 44
Maintenance cost (GH¢) 2,400 1,900 1,300
Result Month 1 Month 2 Month 3
MTBF (240 ÷ failures) 60 h 80 h 240 h
MTTR (downtime ÷ failures) 4 h 3 h 2 h
Availability 93.3% 96.25% 99.2%
Planned share 40% 66.7% 81.8%
Operating hours (240 - downtime) 224 231 238
Cost per operating hour GH¢10.71 GH¢8.23 GH¢5.46

Reading it. As the planned share rose from 40% to about 82%, failures fell from 4 to 1, downtime from 16 to 2 hours and the cost per operating hour about halved. This is one machine and three months, so it suggests that planning helps; it does not prove it. Check for other causes, such as a new operator or a rainy month.

Report to management

Two pages at most. Headline (one sentence). Numbers with last month and a short trend chart. What went well. What went wrong and why. Money: spent and saved. Risks and next month. Decision needed: what you ask the owner to approve, with the cost and the benefit.

Data discipline

Use the same definitions every time: when does downtime start, who writes it down, which hours are "planned". Write them on one page and stick it above the register. If the data is guesswork, say so in the report.

Series, parallel and OEE (checked by script)

All numbers are examples.

Case Formula Example
Machines in a line (series) Multiply the availabilities 0.95 × 0.90 × 0.98 = 0.838 (83.8%)
One duty and one standby (parallel) 1 - (1 - A1) × (1 - A2) 1 - 0.1 × 0.1 = 0.99 (99%)
OEE Availability × performance × quality 0.90 × 0.95 × 0.99 = 84.6%
Cost of downtime (Lost margin per hour + idle labour per hour) × hours (150 + 40) × 6 = GH¢1,140
Maintenance cost per operating hour Total maintenance cost ÷ operating hours 3,000 ÷ 240 = GH¢12.50

OEE traps. The "ideal cycle time" must be the nameplate speed; one published case showed OEE fall from 81% to 65.9% once the ideal cycle time was reset to nameplate. The 85% mark is a vendor-linked benchmark for discrete manufacturing, not a Ghana standard.

Define uptime and downtime on one page before you count. PM compliance counts work orders done by their due date; schedule compliance counts hours done as scheduled. They are not the same, so name which one you report.

Work out the measures

A mill was scheduled 300 hours. It failed 5 times; total downtime was 20 hours; planned maintenance 30 hours and breakdown work 10 hours; maintenance cost GH¢2,660. (1) MTBF? (2) MTTR? (3) Availability? (4) Planned share? (5) Cost per operating hour? (6) 36 of 40 scheduled PM tasks done on time: PM compliance?

Three-month report

  1. Collect three months of downtime, hours, work orders and costs for two assets.
  2. Calculate all seven measures for each month.
  3. Draw a simple chart of one measure.
  4. Write the two-page report with a decision request.
  5. Defend it for five minutes; answer questions on what else might explain the change.

Track a habit

Track one personal measure for three weeks (for example hours of phone use, or days a bike was working). Calculate an average and describe the trend.

Check yourself

  1. Is PM compliance leading or lagging?
  2. Give the formula for availability.
  3. Why not copy another firm's target?
05

Unit 4 · Safety, compliance and leading a team

A manager who skips safety is borrowing someone else's life.

Competency standard

Learning outcome Performance criteria — the trainee…
4.1 Run a lockout programme writes machine-specific lockout steps, issues locks and checks they are used
4.2 Run a permit system issues and closes permits to work and checks the hazards and precautions
4.3 Keep the compliance register lists legal records and examinations and who is responsible
4.4 Supervise and develop people delegates, checks competence, uses a training matrix and investigates incidents

Range. A site with at least six machines and three workers. Evidence. Lockout sheets; permit samples; compliance register; training matrix; incident note.

Ask a qualified expert. This unit contains safety and legal points. It is general information, not legal advice. Ask the Factories Inspectorate or a qualified lawyer what applies to your site. Electrical isolation must be done by an Energy Commission-certified electrician. Lifting, pressure and structural equipment needs a GhIE-registered engineer. For injuries, call 112 and see a doctor or nurse.

Lockout programme

Lockout and tagout protect workers from unexpected start-up or release of hazardous energy during servicing. Only trained, authorised workers lock out, and everyone nearby is instructed never to restart a locked or tagged machine; retraining is required to keep skills up to date. The HSE advises isolating all energy sources, locking off where power could return, releasing stored energy and supporting parts that could fall. Build a machine-specific sheet for each machine (good practice, not a Ghana rule):

Machine Energy sources Isolation point Release stored energy Test
Mill M-01 Electric motor Mill isolator (electrician confirms) Let flywheel stop; block the hopper Try start; clear hands
Pump P-01 Electric motor; water pressure Isolator and discharge valve Open drain; release pressure Try start; check gauge zero

Issue each authorised person their own padlock and tag, with a key held only by them. If a job passes to the next shift, the first person's lock stays until the next person puts on theirs. Audit once a month: watch a lockout from start to finish and note gaps.

Permit to work

For high-risk work a formal permit may be required. A permit says what the job is, what the hazards are, what isolation was done, the precautions, who is in charge and when the permit ends. A permit does not by itself make the job safe; preparers, supervisors and workers must all act on it.

Compliance register

Under the Factories, Offices and Shops Act, 1970 (Act 328), as read in a public copy, these points matter for a maintenance manager:

Point Section What it says (plain words)
General register s.6, s.7 Keep the prescribed general register; keep records available for two years after the last entry
Accident notice s.10 Written notice to the Inspector if an accident causes a death or disables a worker for more than three days
Fencing of dangerous machinery s.38 Dangerous parts must be securely fenced
Fencing kept in place s.40 Guards must be of substantial construction and constantly maintained and kept in position
Hoists and lifts s.44 Must be sound and properly maintained
Lifting tackle s.45, s.46 Chains, ropes and lifting machines sound; safe working loads marked
Register of lifting equipment s.47 A register must be kept in each factory

Section 51 allows the Minister to make regulations for regular examination of lifts and cranes. The Act itself sets no schedule, and the examination schedule that applies to your equipment was not found. Ask the Factories Inspectorate and a GhIE-registered engineer. A different copy or a later amendment may differ, so check the current text with the Inspectorate.

The Engineering Council. Act 819 sets up registers of engineering practitioners, and a Council notice warns against practising or endorsing engineering documents without registration. Practitioners register through a licensed body, GhIE or IET-Ghana. GhIE has also licensed artisans and craftsmen. Do not call yourself an engineer or sign engineering documents unless you are registered. For which of your tasks need registration, ask the Council or GhIE.

Add to your register: your Assembly operating permit, fire safety guidance from the Ghana National Fire Service, insurance renewals, calibration or test dates for gauges and meters, and training dates. Write the owner, the date due and the date done.

Supervise and develop people

  1. Delegate clearly: what, by when, how well, who to ask.
  2. Check competence before trust: watch the person do the task, then sign them off. Only competent people, given enough information, instruction and training, should do maintenance.
  3. Use a training matrix: names down the side, skills along the top, one of "not yet", "supervised", "can do alone".
  4. Give feedback: soon, specific and kind, then follow up.
  5. Hold a toolbox talk of five minutes each week on one safety point.
  6. Investigate incidents with the 5 whys, looking for the system cause, not only blame. Write the report and the fix.

Training matrix example.

Skill Kofi Ama Yaw Esi Kwame
Lockout Alone Alone Supervised Alone Not yet
Lubrication Alone Alone Alone Supervised Supervised
Work order writing Alone Alone Supervised Alone Alone
Stock count Alone Supervised Alone Alone Supervised
Permit to work Supervised Alone Not yet Supervised Not yet
Fault finding Alone Alone Supervised Not yet Supervised

Count the "Alone" cells: Kofi 4, Ama 4, Yaw 2, Esi 3, Kwame 1 = 14 of 30 = 46.7%. Plan training for the "Not yet" cells first, and keep a person who is "Not yet" away from that task.

Ghana regulator register (extended compliance register)

Ask a qualified expert. The rows below are general information from public pages read in November 2026, not legal advice. Ask each office in writing and ask a qualified lawyer and a qualified safety officer to read the final register. Check current texts.

Subject Body What was found (reported) Owner Certificate no. Due Done
Wiring Energy Commission No wiring on premises unless certified; materials not approved by the Ghana Standards Authority prohibited; sources give L.I. 2008 and a later L.I. 2478 for wiring cables and accessories
Fire Ghana National Fire Service L.I. 1724 fire permit and certificate; certificates reported renewed yearly; applications through an online system
Plant Factories Inspectorate Supervises statutory examination of hazardous plant; examination schedule not found
Labour Labour Act 651 Employer provides safe plant and system of work
Measures GSA Metrology Calibration through GSA Metrology
Environment Environmental Protection Authority Act 1124 replaced the earlier Act; used-oil rules not found
OSH Bill Parliament Reported not yet law; check status
Engineers Engineering Council Four registers (professional engineers, technologists, technicians, craftsmen); practising without registration prohibited

Training matrix and lockout audit sheet

Person Lockout Permit to work Lifting First aid Machine A Machine B Date reviewed

Mark each box N (not trained), T (training), C (competent), and record the date. Lockout audit sheet: date; machine; auditor; steps seen; gaps; action; due.

Incident note and 5 whys

Use the near-miss note in Level 1. Add: injury Y/N; immediate cause; root cause by 5 whys; action; owner; date closed. Do not use names of living people in shared records outside the incident file.

Training matrix sums

A matrix has 4 workers and 5 skills (20 cells). 9 cells are "Alone", 7 "Supervised" and 4 "Not yet". (1) What percent are "Alone"? (2) What percent need training or supervision? (3) A worker with "Not yet" in lockout is asked to service the mill. What do you do?

Safety system

  1. Write lockout sheets for three machines and test them.
  2. Fill a permit to work for a real or simulated job; close it properly.
  3. Build the compliance register with owner and date due for each item.
  4. Make a training matrix for your team; plan training for the "Not yet" cells.
  5. Investigate a real or simulated incident with the 5 whys.

Safety at home

Check one room at home: electric sockets, exits, fire extinguisher or sand, first-aid kit, loose cables. Write three actions; do not touch electrical faults, but report them to an adult or electrician.

Check yourself

  1. Who removes a lock?
  2. Does a permit make a job safe by itself?
  3. Which section of Act 328 says guards must be kept in position?
06

Unit 5 · Establish your maintenance business

A good manager of other people's machines can also manage a business, if the paperwork is done right.

Competency standard

Learning outcome Performance criteria — the trainee…
5.1 Choose a legal form compares sole proprietor, partnership, company and cooperative
5.2 Register lists each step, body and fee for the chosen form, with tax and permits
5.3 Plan the start budgets start-up costs and finance and writes a one-page plan
5.4 Employ and insure explains hiring basics and insurance
5.5 Include everyone notes accessibility adjustments

Range. A maintenance service business for farms, workshops and small factories. Evidence. Registration checklist; start-up budget; one-page plan; pitch.

Ask a qualified expert. This unit contains law, tax and money information. It is general information, not legal or tax advice. Ask a qualified lawyer about forms, contracts and liability. Check with GRA or a qualified accountant about tax numbers, VAT, withholding and employer duties. Ask a licensed financial adviser, your bank or the National Insurance Commission about loans and insurance. Fees below were read on official pages in October 2026 and may change; confirm before you pay. For engineering work, work with a registered practitioner and do not do electrical, lifting or pressure work yourself unless authorised.

Choose a legal form

Form ORC fee (2026) Notes
Sole proprietor (business name) GH¢130; renewal GH¢70 a year You and the business are one; unlimited liability
Partnership GH¢270; renewal GH¢100 a year 2 to 20 partners; written agreement stamped by the Lands Commission (Valuation Division)
Company limited by shares GH¢585 plus a capital duty (rate stated as 1% of stated capital, not settled; check) At least 2 directors and a secretary; consent letter from an ICAG chartered accountant
Company limited by guarantee GH¢490 For non-profit bodies such as NGOs and churches
Cooperative Not registered at ORC Get an organisational TIN from GRA; the Department of Co-operatives route was not verified

Source for the fees in general:. Companies must also file an annual return: GH¢175 a year, with late fees of GH¢1,000 or GH¢2,000. Most one-person maintenance services start as a business name and become a company when they take on staff, larger contracts or investors. Unlimited liability means your own property can be at risk if a job goes badly wrong, so ask a lawyer and an insurer.

Tax identity and tax

  • Your Ghana Card PIN is your individual tax number (TIN); a company gets a TIN from GRA after registering.
  • Modified Taxation Scheme: for residents with business income only who are not VAT-registered: up to GH¢20,000 turnover fixed instalments; GH¢20,001 to GH¢750,000 at 3% of turnover or modified cash basis. The ceiling was raised from GH¢500,000 to GH¢750,000 by the Income Tax (Amendment) Act 2026, but GRA's page still showed the old figure on 8 October 2026. Professionals, owners of several outlets and partners are excluded. Whether a maintenance consultant counts as a professional was not verified; ask GRA.
  • VAT from 1 January 2026: 15% plus NHIL 2.5% and GETFund 2.5%, 20% in total. The registration threshold for goods rose to GH¢750,000, but services have no turnover threshold: a business making taxable supplies of services must register within 30 days of starting. A VAT-registered business cannot use the Modified Taxation Scheme. Because a maintenance service is mostly a service, ask GRA or an accountant at the start whether you must register for VAT.
  • Withholding tax: when a customer pays you for works or services the customer may withhold tax (rates for goods 3%, works 5%, services 7.5%); ask for the withholding certificate. Which rate applies to your job is a question for GRA.
  • Keep records in Ghana for at least six years.

Permits and insurance

Ask the Sekondi-Takoradi Metropolitan Assembly about the business operating permit through its portal; the fees were set in its fee-fixing resolution, and the fee for your kind of business was not found. Insurance must come from a company licensed by the National Insurance Commission; check on its website. Which covers are compulsory for your business was not verified; ask the Commission or a broker. Think about public liability (if your advice or work causes loss), tools cover and, if you employ people, injury cover.

Premises and location

Start from home or a shared office with a phone, a spreadsheet and a means of transport; most of your work is at your customers' sites. Choose a base with easy access to your customers: near an industrial area or main road for Takoradi's workshops and mills, or in a farming town for farms. Rent only when you have steady agreements to pay for it.

Start-up budget (all prices are examples)

Item GH¢
Phone or laptop 3,500
Hand tools and measuring tools 2,500
PPE (boots, gloves, glasses, helmet) 600
Printing, signs, cards, receipt books 300
Business name registration (2026 fee) 130
Assembly permit (not verified; placeholder) 300
Working capital for three months 3,000
Total 10,330

Check: 3,500 + 2,500 + 600 + 300 + 130 + 300 + 3,000 = 10,330.

Financing

Savings; a susu group or village savings and loan group; microfinance; banks; and public support. The Ghana Enterprises Agency lists SME programmes and has business advisory centres in Takoradi, Shama, Effia-Kwesimintsim, Mpohor and Ahanta West. The 2026 Budget names GH¢170 million for a National Apprenticeship Programme and GH¢160 million for Adwumawura; how to apply was not verified. The Assemblies' disability fund (5%) may support skills and devices, but its current rules were not verified here. Be careful with loans: ask a licensed financial adviser, your bank or a qualified accountant before borrowing. Keep records a lender can read (Unit 6).

The one-page business plan

Box Write
Customers Who: farms, schools, hotels; where
Offer Audit, monthly check, PM set-up, stores, contractor management
Why us Skills, registration, references
Price Monthly and yearly, with margin
Marketing WhatsApp Business, Google Business Profile, signs, referrals
Costs Fixed and variable per month
Money Start-up cash, funding, 12-month forecast
Risks Late payers, safety incident, one big customer leaves
First 90 days Three actions with dates

Practise a three-minute pitch: the problem, your offer, the price, the proof and the ask.

Hiring and supervising

Hire a helper or apprentice only when you have regular work to pay for. The Labour Act 2003 (Act 651) gives points a new employer must know: a written contract for work of six months or more (s.12), a written statement of terms within two months (s.13), 15 working days of paid leave (s.20), and full minimum pay for each day for casual workers (s.74). The 2026 minimum wage is GH¢21.77 a day. For employees, SSNIT contributions are 5.5% from the employee and 13% from the employer, 18.5% in all; register workers on hiring and pay on time. PAYE applies to employees' pay; the tax-free band is GH¢588 a month, and the bands and the 15th-of-the-month due date are on GRA's page. Master artisans in Takoradi must register their trainees with the Assembly. Use the Level 2 training matrix and the lockout rules for your team.

Accessibility

The Persons with Disability Act, 2006 bans job discrimination. Most of this business is planning, records, reports, quotes, phone calls and supervising: work that suits wheelchair users and many people with limited mobility. Deaf people can lead audits and reports using written orders, messaging and visual lockout and permit signals. People with low vision can use large print and screen readers. Visits to machines need a person-by-person risk check; a colleague can do the physical walk-round while you review the records.

Tools and items: Unit 5

Item What it is and what it does Also called Size or type Caution
Business plan A one-page plan of service, customers, price and money. Plan One page Update yearly
Service agreement Written contract for regular service. Maintenance contract Two pages Have a lawyer read it
Insurance policy Paper that promises payment for covered losses. Cover note Policy Ask a broker what is covered
Quotation template Blank form for prices. Quote form One page Number each quote

Registration and start-up sums

(1) You register a business name now and renew it for two more years. Total ORC fees? (2) You hire a casual helper for 10 days at the minimum wage of GH¢21.77 a day. Minimum pay? (3) Your start-up budget is GH¢10,330. You have GH¢6,500 of savings. How much more do you need? (4) A partner joins and you move to a partnership at GH¢270. How much more than a business name is the first fee?

Register on paper

  1. Choose a legal form; write why.
  2. Make a checklist: ORC, GRA TIN, VAT question, Assembly permit, insurance; with the body, cost and date.
  3. Write a start-up budget and funding plan.
  4. Draft the one-page business plan.
  5. Pitch it in three minutes and answer two questions.

Ask the Assembly

Ask (or look up) how a business operating permit is applied for in your Assembly and what documents are needed. Write what you found and what is still unclear.

Check yourself

  1. What is the ORC fee for a business name, and the yearly renewal?
  2. Do services have a VAT turnover threshold?
  3. Why must you not call yourself an engineer unless registered?
07

Unit 6 · Bookkeeping and accounting for a maintenance business

If you cannot see the money, you cannot manage it.

Competency standard

Learning outcome Performance criteria — the trainee…
6.1 Keep the records keeps a cash book, receipts, invoices, petty cash, stock and debtor records
6.2 Price and cost works out an hourly rate, break-even and margin vs mark-up
6.3 Close the month produces a simple profit and loss statement and balance sheet
6.4 Forecast cash prepares a cash-flow forecast
6.5 Reconcile and file reconciles bank and mobile money and lists tax records and dates

Range. One month of transactions and a 3-month forecast. Evidence. Cash book; statements; forecast; reconciliation.

Ask a qualified expert. This unit teaches simple bookkeeping. It is general information, not tax or accounting advice. Check with GRA or a qualified accountant about what to file and when, and about VAT, withholding and PAYE. Ask a qualified accountant before you rely on these statements for a loan or tax return. All figures in this unit are examples.

The records

  • Cash book: every cash, bank and mobile money movement, in date order, with a running balance.
  • Receipts and invoices: give a receipt for every payment; send an invoice for work done on credit. Number them in order. VAT-registered businesses use e-VAT invoices.
  • Petty cash: a small float for small spends; keep a slip for each; top up to the float.
  • Stock record: your stock cards from Level 1; the value of parts you hold.
  • Debtors and creditors: who owes you, and whom you owe, with dates.
  • Ledger: a page per account (sales, transport, tools); the cash book feeds it.

Double-entry means every transaction has a debit and a credit, so that assets = liabilities + equity. For a small business, the cash book plus a ledger summary is enough to start; a trial balance is a partial check, not a guarantee. A spreadsheet or Google Sheets is enough; Zoho Books has a free plan for one user with limits.

A worked month (all figures are examples)

Business: an example maintenance service. On 1 March the owner puts in GH¢5,000 cash and GH¢2,500 of tools.

Cash book, March (GH¢):

Date Detail In Out Balance
1 Mar Opening cash (owner's capital) 5,000 5,000
2 Mar Mill audit, customer A 600 5,600
5 Mar Monthly check, farm B (MoMo) 360 5,960
9 Mar Monthly check, farm C (MoMo) 360 6,320
10 Mar Transport 280 6,040
11 Mar Consumables and stationery 150 5,890
12 Mar Phone data 80 5,810
14 Mar Stores set-up, guest house D (bank) 900 6,710
15 Mar Office share rent 300 6,410
20 Mar Contractor management, customer E (MoMo) 750 7,160
25 Mar Casual assistant, 8 days at GH¢60 480 6,680
30 Mar Owner's drawings 500 6,180

Not yet in the cash book: on 28 March a PM programme for school F was done and invoiced for GH¢1,200, unpaid at month end (a debtor).

Closing cash = GH¢6,180. Check: 5,000 + in 2,970 - out 1,790 = 6,180. (In: 600 + 360 + 360 + 900 + 750 = 2,970. Out: 280 + 150 + 80 + 300 + 480 + 500 = 1,790, of which drawings 500.)

Depreciation spreads the cost of tools over their life. Straight-line = (cost - salvage) ÷ useful life. Tools: cost 2,500; salvage 500; life 5 years: (2,500 - 500) ÷ 5 = GH¢400 a year = GH¢33.33 a month.

Profit and loss, March:

GH¢
Revenue earned (2,970 received + 1,200 invoiced) 4,170.00
Transport 280.00
Consumables 150.00
Phone data 80.00
Office share rent 300.00
Casual assistant 480.00
Depreciation of tools 33.33
Total expenses 1,323.33
Profit for March 2,846.67

Drawings of GH¢500 are not an expense: they are the owner taking out profit.

Balance sheet, 31 March:

Assets GH¢ Liabilities and equity GH¢
Cash 6,180.00 Owner's capital (5,000 + 2,500) 7,500.00
Debtor (school F) 1,200.00 Profit for March 2,846.67
Tools (2,500 - 33.33) 2,466.67 Less drawings (500.00)
Total assets 9,846.67 Total equity 9,846.67

Both sides are equal, so the check works. There are no creditors (money owed) in this example.

Separate owner and business money

Open a separate bank or mobile money account for the business. Pay yourself a set drawing on a set day. Never pay a personal bill from the business without recording it as drawings. This is the habit lenders and tax officers like best.

Cost, hourly rate and break-even

Fixed costs a month (example): office share 300; data 80; tool depreciation 33; owner's target pay 2,000. Total GH¢2,413 (rounded). Variable cost per billable hour (example): transport and consumables, GH¢15. Price per billable hour (example): GH¢90. Contribution per hour = 90 - 15 = GH¢75.

Break-even hours = fixed costs ÷ contribution per hour = 2,413 ÷ 75 = 32.2, so about 33 billable hours a month. Below that you lose money or underpay yourself.

Margin vs mark-up. Cost GH¢60, price GH¢80. Mark-up = (80 - 60) ÷ 60 = 33.3%. Margin = (80 - 60) ÷ 80 = 25%. They are not the same: a 25% margin needs a 33.3% mark-up. Say which you mean.

Cash-flow forecast

A forecast lists the cash you expect in and out each month. Profit is not cash: in March the profit was GH¢2,846.67 but the cash from trading was less because school F had not paid.

Three-month forecast (examples). Opening cash GH¢6,180 (March close). April inflow includes the GH¢1,200 from school F.

April May June
Opening cash 6,180 7,680 9,680
Cash in 3,600 4,200 4,800
Cash out (costs) 1,600 1,700 1,800
Drawings 500 500 500
Closing cash 7,680 9,680 12,180

The month-end routine (30 minutes)

  1. Total the cash book; count the cash and compare.
  2. Reconcile the bank and mobile money statements to the cash book (below).
  3. List invoices unpaid; chase those over 14 days.
  4. Update stock values from your stock cards.
  5. Record depreciation.
  6. Draw up the profit and loss and balance sheet.
  7. Check: assets = liabilities + equity.
  8. Look at the forecast for the next three months; act on any month where cash is low.
  9. File documents in date order.

Reconcile bank and mobile money

Put the statement and your cash book side by side. Tick each line that matches. List what is in one but not the other: a cheque or payment not yet cleared, a fee you did not record, a payment you forgot. Adjust the cash book for charges and errors until the two agree, or the differences are explained.

Tax records and dates

Keep records for at least six years. The calendar of due dates: SSNIT contributions by the 14th; PAYE and withholding tax by the 15th; VAT by the last working day of the next month; provisional tax quarterly for companies; the annual return within four months of year-end; ORC annual return and renewal yearly. Confirm every date with GRA or an accountant. The IFRS for SMEs standard in its 2025 edition applies from 1 January 2027 for those who use it; a tiny business does not need it, but your accountant may.

Tools and items: Unit 6

Item What it is and what it does Also called Size or type Caution
Ledger A book or sheet that groups all money records by account. Account book Book or spreadsheet Post daily
Cash book A record of money in and money out. Daily cash record Book Balance daily
Receipt book Numbered receipts you give customers. Receipt pad Book Keep copies
Bank reconciliation A check that matches your records to the bank statement. Bank rec One page Monthly
Mobile money statement The provider's list of your transactions. Wallet statement Printout Match to the cash book

One month (example numbers)

Opening cash GH¢2,000 (owner's money). Cash received: GH¢1,500, GH¢900 and GH¢600. Paid: transport 250, data 70, consumables 130. Drawings 400. An invoice of GH¢700 is unpaid at month end. Tools cost GH¢1,800 with salvage GH¢300 and a life of 5 years. (1) Closing cash? (2) Revenue earned? (3) Monthly depreciation? (4) Profit for the month? (5) Break-even hours if fixed costs are GH¢1,800 and contribution is GH¢60 an hour?

Close a month

  1. Write a cash book for a month of at least 12 transactions (use your own business idea).
  2. Record one unpaid invoice and one piece of equipment with depreciation.
  3. Prepare the profit and loss and the balance sheet; check both sides match.
  4. Reconcile with a sample statement.
  5. Write a 3-month cash-flow forecast.
  6. Work out your break-even hours.

Your own cash book

Keep a one-week cash book of your own money in and out. Total it and note the biggest spend.

Check yourself

  1. Is owner's drawing an expense?
  2. Give the straight-line depreciation formula.
  3. Why is profit not the same as cash?
08

Unit 7 · Grow and sustain the business

A business that grows too fast without cash, or too slow without customers, closes. Growth is a plan.

Competency standard

Learning outcome Performance criteria — the trainee…
7.1 Build quality and customer care writes standard checklists, a feedback form and a complaint routine
7.2 Set a pricing and growth strategy chooses prices, offers and a growth path
7.3 Use partnerships, contracts and tenders explains how to find, quote and win larger work
7.4 Keep loan-ready records keeps records a lender can read
7.5 Present the capstone presents a one-page plan and a 12-month cash forecast to a panel

Range. One business plan. Evidence. Plan; forecast; panel presentation.

Ask a qualified expert. Contracts, tenders, loans and succession involve law, tax and money. This is general information, not legal advice. Ask a qualified lawyer before you sign a contract or a loan agreement, check with GRA or a qualified accountant about tax, and ask a licensed financial adviser, your bank or the National Insurance Commission before you borrow or insure. For engineering sign-off work with a GhIE-registered engineer; for electrical work use an Energy Commission-certified electrician.

Quality and customer care

  • Standard checklists for each service, so a visit is the same whoever does it.
  • Written reports after every visit within two days.
  • Feedback: ask each customer three questions: what went well, what was missed, would you recommend us.
  • Complaints: answer within a day, listen, fix, record, and note the cause.
  • Records of faults found and fixed, so the customer sees the value you add.

Pricing and growth

Compare your price with local rates by asking customers and other providers; do not copy a price you cannot afford. Options: a base monthly fee plus extras; packages (bronze, silver, gold) with more visits and a stock review; an annual discount if the customer pays in advance. Grow in steps: more customers of the same kind, then more services to the same customers, then a second technician. Each step needs cash first (see the forecast).

Partnerships, contracts and tenders

Partner with a registered engineer for sign-off work, an electrician for electrical work, and suppliers for parts. Write each partnership down: who does what, who is paid how, and who is responsible when something goes wrong. For larger customers you may be asked for quotes or tenders: read the request, check you meet every condition, price carefully using your cost sheet, include your registration documents and references, and deliver on time. Rules for public tenders and the Public Procurement Authority were not researched; ask the Assembly, the Authority and a lawyer.

Loan-ready records

A lender wants to see: the business registration; a TIN; bank or mobile money statements for at least 6 to 12 months; your cash book; profit and loss and balance sheet for the last months; a forecast; a list of customers with agreements; and an explanation of what the loan buys and how it will be repaid. Keep records for at least six years. Do not borrow for an expense that does not make money.

Ethics, succession and sustaining

Tell customers when a job is beyond you or needs a registered engineer; do not sign documents you are not entitled to sign; do not take a commission to recommend a supplier without telling the customer; do not hide a safety defect to keep a job. For succession, write down your customers, procedures, contacts and passwords in a safe place, train a second person, and think about whether your family or staff could run the business. Review the plan every year.

Capstone

You present a one-page business plan with a 12-month cash-flow forecast to a panel of two or three people. Prepare:

  1. The one-page plan from Unit 5.
  2. A 12-month forecast: opening cash, cash in, cash out, drawings, closing cash for each month.
  3. Your break-even hours and the hours you expect to bill.
  4. One risk and how you will handle it.
  5. A five-minute talk and a five-minute question time.

Panel marking (suggested; 100 marks). Clear customer and offer, 15; prices and break-even correct, 15; forecast arithmetic correct and cash never negative or the shortfall funded, 20; legal, tax and registration steps correct with sources, 15; safety and limits stated (no unauthorised electrical, lifting or pressure work; engineer registration respected), 15; records and quality, 10; presentation and answers, 10. A pass is 60 or more and no safety limit crossed.

Worked 12-month forecast (all numbers are examples). Opening cash GH¢6,000. Four monthly agreements at GH¢360 in month 1, then one new agreement every month (month m has 3 + m agreements). A one-off project of GH¢800 every second month. Costs: fixed GH¢1,200 a month plus GH¢120 per agreement a month. Drawings GH¢1,500 a month.

Month Agreements Cash in Cash out incl. drawings Closing cash
1 4 1,440 3,180 4,260
2 5 2,600 3,300 3,560
3 6 2,160 3,420 2,300
4 7 3,320 3,540 2,080
5 8 2,880 3,660 1,300
6 9 4,040 3,780 1,560
7 10 3,600 3,900 1,260
8 11 4,760 4,020 2,000
9 12 4,320 4,140 2,180
10 13 5,480 4,260 3,400
11 14 5,040 4,380 4,060
12 15 6,200 4,500 5,760

Reading it. Cash stays positive but falls to its lowest, GH¢1,260, in month 7, even though the business grows. That is the time to arrange a small buffer (savings or a short, affordable arrangement agreed in advance) or to cut drawings. Cash in month 1 is 4 × 360 = 1,440; month 2 is 5 × 360 + 800 = 2,600.

Tools and items: Unit 7

Item What it is and what it does Also called Size or type Caution
Customer satisfaction note A short note asking what went well or badly. Feedback form Half a page Act on it
Tender document A request to bid for a job. Bid paper Varies Read the rules
Loan-ready record pack Accounts, bank statements and plans a lender asks for. Loan file Folder Keep it current
Succession note A page that says who takes over. Handover plan One page Review yearly

Forecast check (example numbers)

Opening cash GH¢3,000. Month 1: cash in GH¢2,000; costs GH¢1,200; drawings GH¢600. Month 2: cash in GH¢1,500; costs GH¢1,300; drawings GH¢600. Month 3: cash in GH¢2,800; costs GH¢1,400; drawings GH¢600. (1) Closing cash each month? (2) In which month is cash lowest? (3) If drawings were cut by GH¢200 a month, what is the month 3 closing cash?

Capstone preparation

  1. Finish your one-page plan and your 12-month forecast; check the arithmetic by a second method.
  2. Work out your break-even hours.
  3. Write your one risk and response.
  4. Practise your five-minute talk twice, with a timer.
  5. Present to the panel; take notes of the questions; write what you would change.

Ask for feedback

Ask a customer, a teacher or a friend to read your one-page plan and say what is unclear. Write three changes.

Check yourself

  1. Name two items a lender wants to see.
  2. What is the 12-month forecast for?
  3. Name one ethical rule from this unit.
09

Glossary

Term Meaning
Availability Share of scheduled time a machine is ready to work
Chain block A hand hoist that lifts with a chain loop
Failure-finding task A test of a hidden protective device
Insulation tester A meter that checks winding insulation; electrician only
OEE Availability × performance × quality
On-condition task A task done when a measure shows a need
Phase failure relay A device that stops a motor when a phase is lost
Risk matrix A grid that scores likelihood times impact
Safe working load The most a lifting item may lift
Schedule compliance Hours done as scheduled ÷ hours scheduled
Series availability Availabilities multiplied for machines in a line
Break-even Billable hours or sales at which profit is zero
Contribution Price minus variable cost per hour
Debtor A customer who owes you
Depreciation Spreading the cost of equipment over its life
Drawings Money the owner takes from the business
Life-cycle cost Purchase plus running costs minus resale value
Margin Profit as a share of the price
Mark-up Profit as a share of the cost
PM compliance Preventive tasks done on time as a share of those scheduled
Planned share Planned maintenance hours as a share of all maintenance hours
Reconcile Match your records to the bank or mobile money statement
Risk register A list of risks with scores, actions and owners
Shutdown A planned stop to do maintenance work
Training matrix A grid of people and skills with competence levels

A note on names. Local names for tools differ from town to town. Use the standard name given in this book, in the Tools and items tables and in Appendix H, when you order or ask for help, and show the picture.

10

Logbook

Copy these pages into an exercise book. Your logbook is part of your assessment evidence.

  • Unit 1: strategy table; two care plans; life-cycle sums
  • Unit 2: work list; schedule; budget; risk register; handover note
  • Unit 3: three months of data; seven measures; two-page report
  • Unit 4: lockout sheets; permits; compliance register; training matrix; incident note
  • Unit 5: registration checklist; start-up budget; one-page plan
  • Unit 6: cash book; profit and loss; balance sheet; reconciliation; forecast
  • Unit 7: capstone plan, 12-month forecast, panel notes
  • Every homework, dated
11

Self-check quiz

  1. Name the four maintenance strategies.
  2. What goes into life-cycle cost?
  3. Why freeze the shutdown work list?
  4. How is a risk score worked out?
  5. Give the formulas for MTBF and availability.
  6. Is PM compliance a leading or lagging measure?
  7. Who removes a lock, and does a permit make a job safe by itself?
  8. What is the ORC fee for a business name, and the yearly renewal?
  9. Do services have a VAT turnover threshold in Ghana?
  10. Give the straight-line depreciation formula.
  11. A cost is GH¢60 and the price GH¢80. What is the margin and the mark-up?
  12. Why is profit not the same as cash?
12

Appendix A · Forms, cumulative

Ask a qualified expert. Forms record work and do not make it safe. Ask an Energy Commission-certified electrician, a GhIE-registered engineer, a qualified safety officer and a qualified lawyer where the job or the contract needs one.

Levels 1 and 2 forms continue in use. Level 3 adds: asset care plan (Unit 1), repair or replace worked form (Unit 1), shutdown work list and risk register, commissioning checklist and handover pack (Unit 2), training matrix, lockout audit sheet and compliance register (Unit 4), and a three-month report.

Three-month management report. Headline; availability, MTBF, MTTR, planned share, PM compliance, schedule compliance, backlog weeks, overdue share, cost per operating hour (each for each month); trend in words ("suggests, does not prove"); decisions needed.

Cash-flow forecast and service price templates are in Units 5 and 6 with the example numbers.

13

Appendix B · Formula sheet

Measure Formula Example
MTBF Operating time ÷ failures 240 ÷ 3 = 80 h
MTTR Repair time ÷ repairs 9 ÷ 3 = 3 h
Availability (Scheduled - downtime) ÷ scheduled 96.25%
Series availability Product 0.838
Parallel availability 1 - (1 - A1)(1 - A2) 0.99
OEE A × P × Q 84.6%
Backlog weeks Hours ÷ weekly capacity 3
Reorder point Lead time × usage + safety stock 9
Life-cycle cost Price + years × yearly cost - resale Unit 1
Cost per operating hour Cost ÷ hours GH¢12.50
14

Appendix C · Condition limits worked example

Ask a qualified expert. Limits belong to the standard or the maker. Do not use this example as a limit for your machine. Ask a GhIE-registered engineer and an Energy Commission-certified electrician to read your final text.

Vibration (example only). The old ISO 10816 Class I zones for small machines gave 0.71, 1.80 and 4.50 mm/s RMS as the A/B, B/C and C/D boundaries: A new, B acceptable long-term, C act, D dangerous. The ISO 20816 series replaced parts of that standard and the right part for machines under 15 kW was not confirmed; check the current standard.

Insulation resistance. Print no minimums. Use the method in Unit 1 and the maker's figure.

15

Appendix D · One-page asset management card

ISO 55000:2024 sets out principles (value, alignment, leadership) and outcomes (assurance, adaptability, sustainability) for asset management of any size; 55001 holds requirements and 55002 guidance; it gives no technical guidance for specific assets. A small business does not need to certify; the card asks: what do my assets do for me, what risk do I accept, who owns each one.

16

Appendix E · Common mistakes (strategy and management)

Mistake Fix
Replacing parts by calendar when failures are random Use conditions and history
Reporting PM compliance as schedule compliance Name the measure
Cutting a spares list to save cash without VED Rank by consequence
Skipping the permit "for one minute" Never
Pushing a shutdown list after freezing Control change
Believing a metric without a definition Write definitions
Never testing a protective device Failure-finding task
Mixing owner and business money Separate them (Unit 6)
17

Appendix F · Cases

  • Tractor fleet. Nine working tractors fell to two in a reported farm centre; poor spares and mechanics were named.
  • Low voltage and a school mill.
  • Shutdown overrun. A shutdown overran because the work list was not frozen; a typical lesson, from the method in Unit 2.
  • Lockout. A lock removed by someone else: the first rule of the lockout programme in Unit 4.
18

Appendix G · Further reading (with foreign flags)

See the sources list. Sources marked foreign or vendor give method, not Ghana law. Check international texts against the Ghana Standards Authority, Energy Commission or other Ghana text when read.

19

Appendix H · Tools and Items Glossary

Local names for tools differ from town to town. Use the standard name given here when you order or ask for help, and show the picture.

Name Meaning Also called Used for Warning Unit
Asset care plan One-page plan for an A asset Care plan Planning Review yearly 1
Bank reconciliation Match to the statement Bank rec Check Monthly 6
Cash book Money in and out Daily cash record Control Balance daily 6
Chain block Hand hoist Chain hoist Lifting Never exceed SWL 2
Commissioning checklist Checks before handback Handover checklist Sign-off Sign each line 2
Earth tester Measures earth resistance Earth resistance tester Earth checks Electrician only 1
Handover pack Records given to operators As-built pack Handover Update cards 2
Insulation tester Checks insulation Megger Winding test Electrician only 1
Ledger Groups money records Account book Accounts Post daily 6
Oil analysis kit Lab test of oil Oil sample kit Condition Label samples 1
Phase failure relay Cuts the motor on phase loss Phase monitor Protection Electrician fits 1
Power quality meter Records supply faults Power analyser Supply study With electrician 1
Register of lifting equipment List of lifting items Lifting register Compliance Keep current 2
Risk register Risks with scores Risk log Control Review daily 2
Shackle Joins slings and hooks Bow shackle Lifting Pin fully screwed 2
Sling Holds a load Lifting sling Lifting Inspect 2
Surge protection device Diverts spikes Surge arrester Protection Electrician fits 1
SWL tag Safe working load Load tag Limit Do not exceed 2
Thermography survey Thermal camera check Thermal imaging Hot spots Trained person 1
Training matrix Grid of people and skills Skills matrix Training Update 4
20

Further reading and sources

Best next reads: the free HSE guide on maintenance of work equipment; the HSE permit to work guide; the Ghana Enterprises Agency business advisory centres; GRA's pages on tax for small business; your accountant.

What this module does not cover: repair of particular machines; electrical, gas, lifting and pressure work; civil works, site supervision, quantity estimating and permits (Civil Engineering); public tender rules; computerised maintenance software; Zoho and spreadsheet set-up beyond the basics; and Ghana prices for parts, labour and contractors (not found; all prices here are examples).

Every source used in this manual is listed, with links, in the Teacher Copy.

One application of the Cold-Start Learning Kit, which stays general-purpose and can build a guide on any topic in any field. Written in CTVET format; not a CTVET curriculum.