A farm pump that stops in the dry season, a mill that breaks on market day, a generator that will not start when the lights go out. Most of these breakdowns were visible days earlier. Maintenance management is the habit of seeing them early, planning the fix and writing it down.
Who it is for. People with no formal certificate, aged 18 or over. National Proficiency I is a bridging level for people with little or no formal education; holders do routine tasks under supervision. In Ghana, nobody under 18 may do hazardous work.
Why maintenance management
- Maintenance prevents problems, corrects faults and keeps equipment working. Fewer breakdowns mean less dangerous contact with machinery and better productivity.
- A Ghana study of manufacturers in Kumasi, Accra and Tema found that firms do maintain equipment, and the most preferred way was preventive maintenance. It also found weak organised training for maintenance staff, and that larger firms took maintenance more seriously than smaller ones. Small farms and workshops are where good habits are most needed.
- The law expects it. Under the Factories, Offices and Shops Act, 1970 (Act 328), guards on dangerous machinery must be constantly maintained and kept in position, and hoists and lifts must be properly maintained.
CTVET status. CTVET has competency-based training for many engineering trades, but its official standard for maintenance management was not found online. This module is not that curriculum. Ask CTVET or the regional Ghana TVET Service office for the current standard.
Ask a qualified expert. This module teaches management habits, not repair of electrical, gas, pressure, lifting or structural equipment. For electrical work use an Energy Commission-certified electrician. For lifting equipment, pressure vessels, structures or anything that could fall or burst, ask a GhIE-registered engineer. Do not attempt work you are not trained and authorised to do.
Sister manuals
This module links to other Hub manuals by title. For the safety law and your rights at work, see the Hub's Workplace Safety. For business basics, see Entrepreneurial Thinking. For specific machines, see Small Engines and Irrigation Pumps, Boreholes and Water Pumps, House Electrical Wiring and Basic Welding and Fabrication. This manual does not repeat them.
How the module works
Each unit has learning outcomes, performance criteria, the range and the evidence your assessor needs. You are judged Competent or Not Yet Competent by being watched at work, by your forms and records, by answering questions, and by your logbook. About 70% of the time is practical, following CTVET's Oil Palm programme, which uses about 30% in school and 70% at the workplace.
Unit 1 · Why maintenance matters, and stay safe
Every machine will fail one day. The only choice is whether it fails when you chose, or when you were not ready.
Competency standard
| Learning outcome | Performance criteria — the trainee… |
|---|---|
| 1.1 Name the kinds of maintenance | explains breakdown, preventive and corrective maintenance with a real example each |
| 1.2 Say who does what | names the roles of owner, supervisor, technician, operator and contractor |
| 1.3 Work safely around equipment | stops, isolates, locks out and tests before any hands-on job; refuses work outside their training |
| 1.4 Count the cost of a breakdown | lists lost time, lost sales and repair cost for one failure |
Range. Farm, workshop and small-factory equipment. Evidence. Oral questions; observed safety set-up; logbook.
Ask a qualified expert. For electrical, gas, pressure, lifting or other dangerous work, use an Energy Commission-certified electrician, a GhIE-registered engineer or a qualified safety officer. Do not attempt work you are not trained and authorised to do. For any injury or illness, see a doctor or nurse. This unit teaches awareness and good practice, not a safe-work procedure for any one machine.
Three kinds of maintenance
| Kind | Meaning | Farm example |
|---|---|---|
| Breakdown (run to failure) | You do nothing until it stops | The pump stops; you call a mechanic |
| Preventive | You service it on a schedule, before it fails | You change the pump oil every 100 running hours |
| Corrective | You repair a fault you found, on a planned date | You see the belt is cracked and replace it on Saturday |
Breakdown work is the most expensive because it happens at the worst time, with no parts ready. Preventive and corrective work is planned, so the parts and the people are ready. Good maintenance managers aim to plan most of their work.
What a breakdown costs
Add up three things: the repair (parts and labour), the lost work (water not pumped, maize not milled), and the knock-on (a customer who goes elsewhere). The repair is often the smallest.
Who does what
| Role | Duty |
|---|---|
| Owner or manager | Decides money and priorities; reads the monthly report |
| Maintenance supervisor (maybe you) | Plans work, issues work orders, keeps records |
| Technician | Does skilled repairs; is competent in that trade |
| Operator | Uses the machine; does simple daily checks; reports faults |
| Contractor | An outside business hired for jobs you cannot do |
Only competent people, given enough information, instruction and training, should do maintenance. High-risk or complex equipment may be best left to the maker or a specialist contractor.
Stay safe: stop, isolate, lock, test
Lockout and tagout are practices that protect workers from the unexpected start-up of a machine or release of energy during servicing. Energy can be electrical, mechanical, hydraulic, pneumatic, chemical or heat. Only trained, authorised workers lock out equipment, and everyone nearby must be told never to restart a locked or tagged machine. The UK Health and Safety Executive says the same in plain words: make sure moving plant has stopped, isolate electrical and other power, lock off where power could come back, release stored energy such as pressure, and support parts that could fall.
The steps below are good general practice; the sources above do not give a Ghana procedure.
The golden rule before any hands-on job
- Tell everyone nearby what you are about to do.
- Stop the machine the normal way.
- Isolate it: switch off and disconnect power; close fuel or water valves. Electrical isolation is for a certified electrician.
- Lock and tag: put your own padlock and a tag with your name and date on the switch or valve. Keep the key in your pocket.
- Release stored energy: pressure, springs, raised parts. Support anything that could fall.
- Test that it is dead: try the start button, with your hands clear.
- Do the job. When finished, clear tools, refit guards, remove your own lock, and tell everyone.
Tools and items: Unit 1
| Item | What it is and what it does | Also called | Size or type | Caution |
|---|---|---|---|---|
| Padlock | A lock with a U-shaped bar (shackle) and a key. It holds a switch or valve in the safe position. | Lockout padlock, safety padlock | One colour per person if possible; one key each | One lock, one person, one key |
| Lockout tag | A card tied to the lock. It says who locked the machine, when and why. | Danger tag, do-not-operate tag | Strong card with a tie; write in ink | Never remove another person's tag |
| Hasp | A folding plate with several holes. It covers the switch handle so several people can each add a lock. | Multi-lock hasp, lockout hasp | Hole size to fit your padlock shackle | Fit it only when the switch is already OFF |
| Isolator | A switch that cuts the power to one machine so it can be worked on. | Isolating switch, disconnector | Fixed on the wall near the machine | Installed and opened only by a certified electrician |
| Chock | A wedge placed against a wheel so a vehicle or trolley cannot roll. | Wheel chock, wheel stop | Wood or rubber wedge | Place it on the downhill side |
| Guard | A cover over belts, chains and shafts so hands cannot reach moving parts. | Machine guard, safety guard | Made for each machine | Never run with the guard off |
| Safety sign | A board or sticker that warns, forbids or directs (for example DANGER, DO NOT START). | Warning sign, notice | Bright colours, large letters | Replace a faded sign |
| Fire extinguisher | A cylinder that puts out a small fire. Types differ for wood and paper, fuel, and electrical fires. | Fire extinguisher | Ask the Ghana National Fire Service which type your site needs | Know where it is; do not fight a big fire |
| First-aid kit | A box of dressings and basic items for small injuries. | First-aid box | Check contents each month | For serious injury call 112 |
| PPE | Personal protective equipment: gloves, goggles, boots, ear defenders, dust mask. | Safety gear | Match to the job | Damaged PPE must be replaced |
| Torch | A hand light for reading dark corners and nameplates. | Flashlight | LED, with spare batteries | A torch near fuel must be a sealed type |
Parts and safety: Padlock, hasp and lockout tag
| No. | Part | What it does | Safety rule |
|---|---|---|---|
| 1 | Isolator box | Holds the switch that cuts the supply | Only a certified electrician fits or opens it |
| 2 | Switch handle | Turned to OFF to stop the power | Never force a handle that is locked |
| 3 | Hasp | A folding plate that covers the handle so it cannot be moved | Fit it only when the handle is at OFF |
| 4 | Lock holes | Several holes so each worker adds a lock | One person, one lock, one key |
| 5 | Shackle | The U-shaped bar that goes through the hole | Check it clicks fully shut |
| 6 | Padlock body | Holds the shackle shut; opens only with the key | Keep the key in your own pocket |
| 7 | Lockout tag | Shows name, date and reason | Write it in ink; never remove another person's tag |
Safety protocol: Lockout padlock, hasp and tag
Before. Tell everyone nearby. Stop the machine the normal way. Make sure the switch is at OFF. Wear gloves and boots. Check the padlock works and the tag is filled in.
While you work. Keep the key on you. Test that the machine will not start, with your hands clear. If a second person joins the job, they add their own lock to the hasp. Do not borrow another person's lock, do not use a lock with a spare key lying about, do not work on a machine with only a tag and no lock if a lock can be fitted.
After. Clear tools, refit guards, count people, remove your own lock and tag, tell everyone, then restart the machine. Hang the padlock back on the board. Report a damaged padlock or hasp.
Emergency. If someone is hurt, call 112. If a person is in contact with live electrical equipment, do not touch them; switch off at the isolator if it is safe to do so, or call 112 and the electrician. Give first aid only if trained.
You are a manager, not a hero. If you do not know how to isolate a machine safely, stop and ask the technician or a GhIE-registered engineer. Never take a lock off for someone else.
Safety walk
- Walk round your site with a notebook and a torch.
- For six machines, note: is there a guard? Is there a way to switch it off in an emergency? Where would you put a lock?
- Write three things that are unsafe and who you will tell.
- Record in your logbook.
One breakdown story
Ask a farmer, mill owner or workshop owner about a breakdown they remember. Write what stopped, how long it was down, what it cost, and what could have warned them. Do not touch any machine.
Check yourself
- Name the three kinds of maintenance.
- What are the last two steps before starting a locked-out job?
- Who may take your lock off?
Unit 2 · Know your equipment
You cannot look after what you have not listed.
Competency standard
| Learning outcome | Performance criteria — the trainee… |
|---|---|
| 2.1 Make an equipment list | lists every machine with a tag number, place, maker, model, serial number and date bought |
| 2.2 Read a nameplate | copies power, voltage, speed, and flow or capacity correctly |
| 2.3 Find the manual | finds or requests the maker's manual and files it |
| 2.4 Mark critical equipment | marks which machines stop the business if they fail |
Range. At least ten items on a farm, workshop or mill. Evidence. Completed equipment list; observation; oral questions.
Ask a qualified expert. Do not open electrical panels, pressure vessels or lifting gear to copy details. Read only the outside plate. For electrical or pressure equipment ask an Energy Commission-certified electrician or a GhIE-registered engineer.
The equipment list (asset register)
An asset is anything you must keep working: a pump, a generator, a mill, a freezer, a welding machine, a vehicle. The list is your first maintenance tool.
| Tag | Item | Place | Maker and model | Serial no. | Bought | Critical? |
|---|---|---|---|---|---|---|
| P-01 | Irrigation pump | Pump house | (nameplate) | (nameplate) | 2024 | Yes |
| G-01 | Generator | Store | (nameplate) | (nameplate) | 2023 | Yes |
| M-01 | Maize mill | Mill shed | (nameplate) | (nameplate) | 2022 | Yes |
A tag number is a short code you paint or stick on the machine: a letter for the type and a number. Choose a code that is easy to read: P for pump, G for generator, M for mill, V for vehicle, T for tool.
The nameplate
Most machines carry a metal plate with the maker, model, serial number, power, voltage, speed or flow. Copy it exactly, and take a photo. Keep the list in two places: paper in the office and a copy on a phone or computer.
Manuals
The maker's manual says what to check, how often and which oil or parts to use. The HSE says plan maintenance using the manufacturer's instructions. If the manual is lost, look up the model online or ask the dealer. If you cannot find it, write "no manual" in the list and ask a technician what to check.
Critical or not
Ask three questions for each machine: If it stops, does the business stop? Is anybody at risk if it fails? Is there a spare or a quick workaround? Mark A (critical), B (important) or C (can wait). Look after A machines first.
Tools and items: Unit 2
| Item | What it is and what it does | Also called | Size or type | Caution |
|---|---|---|---|---|
| Nameplate | A metal or sticker plate on the machine that gives its maker, model, serial number and ratings. | Rating plate, data plate | Fixed by the maker | Read the outside only; do not open a machine to find it |
| Tag label | A paint-pen mark or sticker with the tag number, for example P-01. | Asset tag, equipment tag | Letters at least 2 cm high | Stick it where it can be seen, not on a moving part |
| Paint pen | A marker that writes on metal, dirt or oil. | Paint marker | White or yellow | Keep the cap on; do not breathe the fumes |
| Clipboard | A board with a clip for a form, so you can write while standing. | Writing board | A4 | None |
| Phone camera | Takes a photo of the nameplate so the details are not lost. | Camera | Any | Do not climb or lean over a machine to take the photo |
| Box file | A card or plastic file that keeps the manual and papers of one machine together. | Lever-arch file | A4 | Keep it dry |
| Manual | The maker's book: what to check, how often, which oil and parts. | Owner's manual, operator's manual | Paper or PDF | Keep a second copy |
Parts and safety: The nameplate
| No. | Field | What it tells you | Safety rule |
|---|---|---|---|
| 1 | Maker | Who built the machine, so you know whom to ask for the manual and parts | Copy it exactly |
| 2 | Model and serial number | Model is the type; serial number is this one machine. Parts and the manual are chosen by these | Write both in the asset list |
| 3 | kW, V, A, Hz | Power, supply voltage, current and supply frequency the machine is made for | A machine on the wrong voltage can burn; ask an electrician |
| 4 | rpm, IP, insulation class | rpm is shaft speed. IP is a code for how well the case keeps out dust and water. The insulation class letter says the heat the winding insulation is made for | Read the manual for what the code means; do not guess |
| 5 | Year and mass | When it was made and how heavy it is | Never lift a heavy machine by hand; check the mass first |
| 6 | Fixing rivet | Holds the plate on | Do not remove the plate |
Safety protocol: Copying a nameplate
Before. Make sure the machine is stopped and locked out (Unit 1). Wear gloves and boots. Switch on a torch if it is dark.
While you work. Read the outside plate only. Keep hands and sleeves away from belts, fans and shafts. Do not open covers or panels. Photograph the plate straight on.
After. Write the details in the asset list, file the photo, tell the supervisor if the plate is missing or unreadable.
Emergency. If you touch a tingling or hot case, step back, switch off at the isolator if safe, tell your supervisor and the electrician. Call 112 for serious injury.
Make the asset list
- Walk the site with a clipboard. Pick at least ten items.
- Give each a tag number; label it with a paint pen or sticker.
- Copy the nameplate details; photograph the plate.
- Mark A, B or C and write one reason.
- Find the manual for each A machine; file them in a box file.
- Type or copy the list so there are two copies.
List your own tools
At home or at work, list ten tools or machines with a tag, where they are kept and who uses them. Note which one you could not work without.
Check yourself
- What is a tag number for?
- Name three things on a nameplate.
- Which machines do you look after first?
Unit 3 · The work order
If it is not written down, it is not a job. It is a rumour.
Competency standard
| Learning outcome | Performance criteria — the trainee… |
|---|---|
| 3.1 Raise a request | writes a clear fault report with tag, place, what was seen and by whom |
| 3.2 Prioritise | ranks jobs as emergency, urgent, routine using the safety and business test |
| 3.3 Issue a job card | fills a work order with job, parts, tools, safety and who |
| 3.4 Close the job | records work done, time, parts used, date and a check by the supervisor |
Range. Paper forms or a simple spreadsheet. Evidence. Five completed work orders; observation; oral questions.
Ask a qualified expert. A work order is a record, not a permission to do dangerous work. Where a job touches electricity, gas, lifting, pressure or structures, the order must name an Energy Commission-certified electrician or a GhIE-registered engineer as the person who does or approves it.
The five steps
- Request: someone sees a fault and reports it.
- Review: the supervisor checks it, sets the priority and decides who and when.
- Plan: parts, tools, safety steps and time are listed on the job card.
- Do: the technician does the job and writes what was done.
- Close: the supervisor checks the work, signs, and files the card.
Priorities
| Priority | Test | Target |
|---|---|---|
| Emergency | Danger to people or the environment, or a critical machine is down | Start now; make safe first |
| Urgent | A critical machine is failing, or a B machine is down | This week |
| Routine | Wear that can wait | Next planned slot |
Danger always comes first. A guard that is missing is an emergency.
A job card
| Field | Example |
|---|---|
| WO number | 2026-014 |
| Date and requested by | 3 Nov, operator Kofi |
| Tag and place | P-01, pump house |
| Fault seen | Pump leaks water at the seal, motor hot |
| Priority | Urgent |
| Planned: parts, tools, safety | Seal kit (check size), spanners; isolate and lock out first |
| Who and when | Technician Yaw, Saturday morning |
| Work done | (written by technician) |
| Time taken, parts used | (written by technician) |
| Checked by and date | (supervisor) |
A work order stays open until it is checked and closed. Keep numbers in order so none is lost.
Tools and items: Unit 3
| Item | What it is and what it does | Also called | Size or type | Caution |
|---|---|---|---|---|
| Work request | A short note that says a fault was seen, where and by whom. | Fault report, repair request | Half a page | Write what you saw, not what you think the cause is |
| Work order | The numbered job card that plans, records and closes the job. | Job card, job ticket | One A4 page | Keep the numbers in order |
| Priority card | A small card that lists the emergency, urgent and routine tests. | Priority key | Wall card | None |
| Job file | A box or folder where open and closed cards are kept. | Work order file | A4 box file | Do not lose open cards |
Parts and safety: The job card
| No. | Box | What to write | Rule |
|---|---|---|---|
| 1 | Date and requested by | The date, and the name of the person who saw the fault | Never leave blank |
| 2 | Tag and place | The tag number (P-01) and where the machine is | Use the tag, not "the old pump" |
| 3 | Fault seen | What was seen, heard or smelled | Facts only |
| 4 | Priority | Emergency, urgent or routine (page of priorities above) | Danger to people is always emergency |
| 5 | Who and when | The person doing the job and the date | An electrician where electricity is involved |
| 6 | Planned: parts, tools, safety | Parts, tools, and the lockout and PPE steps | Write the isolation step here, before the job |
| 7 | Time taken, parts used | Written by the technician after the job | Write real minutes and real parts |
| 8 | Checked by and date | The supervisor's signature after looking at the work | Sign only after you look |
How to fill, in one line each: boxes 1 to 5 before the job, box 6 with the technician, boxes 7 and 8 after the job.
Safety protocol: Using a work order
Before. Read the safety box. If the job touches electricity, gas, lifting or pressure, the order must name the certified person who does it.
While you work. The technician locks out first and follows box 6. If new danger appears, stop and write a new work order.
After. The technician fills boxes 7 and 8; the supervisor checks the machine runs and guards are back, then signs. File the card.
Emergency. Danger to people stops everything: make safe, call 112 if anyone is hurt, report afterwards.
Prioritise
Rank these as emergency, urgent or routine: (1) the guard on the mill belt has fallen off; (2) a paint chip on a gate; (3) the only borehole pump makes a loud noise but still works; (4) a spare drill has a worn chuck.
Run five work orders
- Make a blank job card (copy the table above).
- Choose a fault or small job on your site, or a planted fault set by the trainer.
- Write the request, set the priority, and plan parts and safety.
- Have a technician or trainer do or simulate the job; record time and parts.
- Close the card and file it. Repeat to five.
Spot and report
Find three small faults at home or in your community (a dripping tap, a loose gate hinge, a flickering bulb). Write each as a request: what, where, who saw it, how urgent. Do not repair electrical faults.
Check yourself
- Name the five steps of a work order.
- Which priority comes first, always?
- When can a work order be closed?
Unit 4 · Preventive maintenance routines
A little attention often beats a big repair once.
Competency standard
| Learning outcome | Performance criteria — the trainee… |
|---|---|
| 4.1 Do operator checks | does a daily look, listen, smell and feel check and records it |
| 4.2 Make a schedule | lists tasks with how often, by time or running hours, taken from the manual |
| 4.3 Lubricate and clean | applies the right oil or grease in the right amount, as the manual says |
| 4.4 Record and follow up | ticks the checklist and raises a work order for any fault found |
Range. Engine-driven and electric machines on the site. Evidence. Completed checklists for a month; observation; oral questions.
Ask a qualified expert. Operator checks are done with the machine stopped and locked out, unless the manual says a check must be done while running, in which case a trained technician does it. Do not open electrical enclosures. For fuel, gas, pressure and electrical equipment ask an Energy Commission-certified electrician or a GhIE-registered engineer. Fuel is a fire hazard; ask the Ghana National Fire Service for guidance on storage.
Look, listen, smell, feel
An operator can find most early faults with four senses, with the machine stopped and locked out unless the manual says otherwise.
- Look: leaks, cracks, loose or missing bolts, worn belts, rust, dirt, low oil.
- Listen: a new rattle, squeal or knock.
- Smell: burning, fuel, overheated oil.
- Feel (stopped and cool): looseness, play, free movement.
Time-based and use-based
Some tasks are done by the calendar (daily, weekly, monthly), others by use, such as hours run. An engine may need oil after a set number of running hours; read the figure in the manual, not from memory or a neighbour. Keep a running-hours record for important machines.
A daily checklist
| Check | OK | Fault | Note |
|---|---|---|---|
| Oil level | |||
| Fuel level; no leaks | |||
| Belts and guards in place | |||
| Bolts tight; no new noise | |||
| Area clean and tidy |
Ask the operator to tick or write on it every day. A tick on a form with no look is worse than no form: teach honesty.
A simple schedule
| Task | Machine | How often | Who | Time (min) |
|---|---|---|---|---|
| Daily check | all A machines | daily | operator | 5 |
| Grease points | mill | weekly | technician | 15 |
| Change oil (as the manual says) | pump engine | by hours in the manual | technician | 45 |
| Check wiring, earth and guards | house and mill | monthly | certified electrician and supervisor | 60 |
Put the schedule on the wall as a calendar and tick off each task.
Lubrication
Lubrication is among the biggest single causes of premature bearing failure, according to a figure that is widely quoted from SKF training. It is about 36% of premature failures, but it also covers too much grease, not only too little. This is a foreign figure and applies to bearings only. Use the type and amount the manual gives. More grease is not better.
Do it every time
Preventive work fails when it is skipped in busy weeks. Block the time on the calendar, tell the owner, and do the A machines first.
Oil, grease and fuel in plain words
- Oil is a thin liquid that coats moving metal so it does not wear. Grease is oil held in a thick soap-like carrier so it stays in a bearing. Use oil where it can be poured and kept in, grease where it must stay put.
- SAE number (for example 10W-30) is only the thickness of the oil. The SAE system says nothing about the quality of the oil. API letters (for example SP) say the quality class. A good oil must match both the thickness and the class that the manual asks for.
- NLGI number is the grease thickness, from 000 (almost liquid) to 6 (very stiff). Grade 2 is the common general-purpose grade for bearings; stiffer grades suit hot places and softer grades suit cold ones. The manual gives the grade for each bearing.
- Never mix greases unless the maker says they are compatible. Keep each tin labelled and closed. Keep oil and grease tins off the ground and out of dust and water.
- Fuel (petrol, diesel) is a fire hazard. Store it in a labelled approved container away from sparks. Ask the Ghana National Fire Service for guidance.
Tools and items: Unit 4
| Item | What it is and what it does | Also called | Size or type | Caution |
|---|---|---|---|---|
| Grease gun | A hand pump that pushes grease into a bearing through a fitting. | Grease pump | Lever type or pistol type | Pump only until the manual's amount; too much can burst a seal |
| Grease nipple | A small valve on the bearing housing where the gun clips on. | Grease fitting, zerk fitting | Common types are standard; check the machine | Wipe it clean before and after |
| Oil can | A can with a spout for putting small amounts of oil on a joint. | Oiler | 250 to 500 ml | Do not over-fill |
| Funnel | A cone that guides oil into a filler hole. | Filling funnel | Clean, labelled for one fluid | Keep for one fluid only |
| Rags | Cotton cloths for wiping oil and dirt. | Wiping cloths | Lint-free if possible | Oily rags can catch fire; store in a closed metal bin |
| Dipstick | A rod that shows the oil level in an engine or gearbox. | Oil level stick | Part of the engine | Wipe, push in, pull out, read |
| Infrared thermometer | A hand device that reads surface temperature from a distance by a beam of light. | IR thermometer, temperature gun | Handheld | Reads the surface only; shiny metal reads low |
| Hour meter | A small meter that counts the running hours of an engine or motor. | Running-hours counter | Fitted to the machine | Write the reading on the history card |
| Hand spanner set | Open-ended and ring spanners that fit bolts and nuts. | Wrench set | Metric or inch, to fit the machine | Use the correct size; do not use a pipe on the handle |
| Screwdriver | A tool to turn screws; flat and cross-head (Phillips). | Slotted and Phillips driver | Match the screw head | Do not use as a chisel |
| Tape measure | A rolled steel ruler for lengths. | Measuring tape | 3 or 5 m | Retract slowly |
| Test lamp | A lamp with two leads that glows when voltage is present. | Test light | Low-voltage type | Not a safe tester for mains. Certified electricians use proper testers |
Parts and safety: Hand grease gun
| No. | Part | What it does | Safety rule |
|---|---|---|---|
| 1 | Follower rod knob | Pulled back to load a grease tube | Release slowly; the spring pushes back |
| 2 | Air bleed vent | Lets trapped air escape from the barrel | Hold a rag over it when bleeding |
| 3 | Pump lever | Squeezed to push grease out | Do not squeeze after the bearing is full |
| 4 | Barrel | Holds the grease tube | Check the barrel for cracks |
| 5 | Gun head | Holds the pump and a one-way valve | Do not strike it |
| 6 | Coupler | Clips onto the grease nipple | Press on straight; do not use sideways |
| 7 | Nozzle tip | Delivers grease into the fitting | Keep clean |
| 8 | Rear cap | Closes the barrel | Refit tight |
Safety protocol: Grease gun
Before. Stop and lock out the machine (Unit 1). Wear gloves and glasses. Wipe the nipple. Check the gun and hose for leaks.
While you work. Give the number of strokes the manual says, then stop. Watch for old grease coming out; wipe it away. Do not point the gun at skin: grease under pressure can injure the skin and needs a doctor.
After. Wipe the nipple and gun, store the gun with the cap on, record the greasing on the schedule.
Emergency. If grease is injected into skin, do not wait: go to a doctor or clinic, or call 112 for serious injury.
Parts and safety: Ball bearing (for example 6205)
| No. | Part | What it does | Safety rule |
|---|---|---|---|
| 1 | Outer ring | The fixed outer part; it sits in the housing | Do not hammer it |
| 2 | Ball | Rolls between the rings so the shaft turns easily | A cracked ball means replace the bearing |
| 3 | Raceway | The groove each ring has, where the balls run | Dirt in the groove ruins it |
| 4 | Inner ring | Fits tightly on the shaft | Never reuse a loose inner ring |
| 5 | Bore | The hole that fits the shaft | Size comes from the bearing number; check the maker's catalogue |
| 6 | Cage | Keeps the balls evenly spaced | Do not bend it |
A bearing number such as 6205 is a code. In common maker catalogues the first digit shows the bearing family and the last two digits show the bore size. Always check the maker's catalogue and the old bearing before you buy. Fake bearings are sold; buy from a supplier you trust.
Safety protocol: Looking at a bearing
Before. Machine stopped and locked out. Let hot parts cool.
While you work. Look for heat colour, leaked grease, rust and noise. Do not put your fingers near a shaft. Report, do not strip, unless you are trained.
After. Record the finding on a work order and the history card.
Emergency. A burn or crush injury: step away, call 112 for serious injury.
Parts and safety: Small generator set
| No. | Part | What it does | Safety rule |
|---|---|---|---|
| 1 | Fuel tank cap | Closes the fuel tank | Never refuel a hot or running engine |
| 2 | Fuel tank | Holds the petrol or diesel | Fuel is a fire hazard; no smoking |
| 3 | Engine switch, choke and pull starter | Starts and stops the engine | Use the stop switch, not the choke, to stop |
| 4 | Output panel | Sockets that give the electricity | Do not plug in more than the rating |
| 5 | Breaker and earth terminal | A breaker trips when overloaded; the earth terminal connects to the earth | Connection to the house wiring only by a certified electrician |
| 6 | Silencer (exhaust) | Quietens the engine and sends the gas out | It stays hot; fumes can kill, so run outdoors |
| 7 | Air filter | Cleans the air the engine breathes | Clean as the manual says |
| 8 | Frame and feet | Hold the machine on level ground | Place it on firm, level ground |
| 9 | Oil dipstick and drain | Show and change the engine oil | Check with the engine stopped and level |
Safety protocol: Generator set (daily check and use)
Before. Place it outdoors, away from windows and doors. Stop the engine, let it cool, and check oil, fuel level and leaks. Wear gloves and boots. Keep a fire extinguisher close.
While you work. Run it outdoors only, never in a closed room: the exhaust has a poisonous gas (carbon monoxide). Keep fuel away. Do not touch the silencer. Do not connect it to the house wiring yourself: a wrong connection can send power back into the grid and kill a line worker. A certified electrician fits a changeover switch.
After. Switch off the load, then the engine. Let it cool. Wipe it, refill fuel only when cool, record the running hours.
Emergency. Fire: use the extinguisher only on a small fire and call 112. Dizziness, headache or confusion near a running engine: get into fresh air at once and call 112.
Parts and safety: Infrared thermometer
| No. | Part | What it does | Safety rule |
|---|---|---|---|
| 1 | Body | Holds the electronics | Keep dry |
| 2 | Display | Shows the temperature | Read the unit (C or F) |
| 3 | Trigger and handle | Squeeze to measure | Hold steady |
| 4 | Battery compartment | Holds the batteries | Remove batteries if stored long |
| 5 | Laser aiming dot | Shows where the device is aiming | Never point at anyone's eyes |
| 6 | Sensor lens | Collects the heat radiation | Keep clean and uncovered |
| 7 | Measured spot | The area it reads; it grows with distance | Get close enough; shiny metal reads low |
Safety protocol: Infrared thermometer
Before. Check the lens is clean. Machine guards stay in place; do not reach in. Stand clear of moving parts.
While you work. Aim at a dull part of the surface, not shiny metal. Compare the reading with the same point on a similar machine or last week's reading. Do not touch a hot part to check.
After. Write the reading and the date on the history card. Store the device in its case.
Emergency. If a laser beam enters an eye, rest the eye and see a doctor.
Build a PM sheet
- Choose one A machine. Find its manual or ask a technician what to check and how often.
- List five tasks with how often and who does them.
- Make a one-page daily checklist for the operator.
- Run it for ten working days. Record every fault in a work order.
- Review: what did the checks find? What would have happened if no one had looked?
Care for something at home
Choose a bicycle, a sewing machine or a gas cooker. Write a weekly care list with five checks. For the gas cooker, write only checks that need no tools and ask an adult or a technician about any smell of gas.
Check yourself
- Name the four senses an operator uses to check a machine.
- Where do you find how often to change the oil?
- What do you do when a check finds a fault?
Unit 5 · Spare parts, tools and stores
A good store is where the right part is found in two minutes, not two days.
Competency standard
| Learning outcome | Performance criteria — the trainee… |
|---|---|
| 5.1 Set up a store | arranges, labels and locks a small store with a bin or shelf location for every item |
| 5.2 Keep a stock card | records every part in and out with date, work order number and balance |
| 5.3 Set minimum and maximum | sets a reorder level and a maximum for common parts from usage and delivery time |
| 5.4 Control tools | keeps a tool list and a sign-out book |
Range. A small store of 20 or more items. Evidence. Stock cards; stock count; observation; oral questions.
Ask a qualified expert. Store fuel, oil, batteries, chemicals and gas cylinders as their labels and the Ghana National Fire Service guidance say; ask a qualified safety officer. Do not stack heavy items high; ask a GhIE-registered engineer about shelves that carry heavy loads. Check with a qualified accountant before you record the value of stock in your business accounts.
What goes in the store
- Spare parts you expect to need: belts, filters, seals, bearings, fuses, bulbs, spark plugs.
- Consumables: grease, oil, cleaning rags, gloves, nuts and bolts.
- Tools you lend out: spanner sets, grease guns, test lamps, ladders.
Do not store scrap in the same place. Keep the store clean, dry and locked. Only one or two people hold keys.
Make it findable
- Give each shelf or bin a code (A1, A2, B1).
- Label each item with its name and its part number from the manual.
- Put heavy things low. Keep similar things together.
- Write the bin code on the stock card.
The stock card
| Part | Bearing 6205 (example), bin A2 | Min 2 | Max 6 |
|---|---|---|---|
| Date | Work order | In | Out |
| 3 Oct | opening count | ||
| 9 Oct | 2026-009 | 1 | |
| 15 Oct | 2026-011 | 1 | |
| 16 Oct | order made | ||
| 28 Oct | received | 4 |
The card tells you how much is left, when it was used and for which job.
Minimum and maximum
The minimum (reorder level) is the stock at which you order again. A simple rule: usage during the delivery time plus a small safety amount. The maximum is the most you want to hold, so money is not tied up. Stock-control guides say the reorder level is the usage during the lead time plus a safety buffer, and that critical parts need a larger buffer even if they are cheap. They also say to review the levels from time to time.
Worked example. Grease cartridges: you use 4 a month. The shop in town takes 1 month to supply them. Safety stock 2. Minimum = 4 × 1 + 2 = 6. Maximum: choose 10.
Tools and borrowing
Keep a tool list and a sign-out book: date, tool, name, signature, returned date. Count the tools every month. Lost tools usually mean no one wrote them down.
Tools and items: Unit 5
| Item | What it is and what it does | Also called | Size or type | Caution |
|---|---|---|---|---|
| Shelf and bin | Rack and box that hold parts in a fixed place with a code. | Storage rack, parts bin | Steel or wood, with labels | Heavy parts low; do not overload |
| Stock card | A card for one part that records in, out and balance. | Bin card | One per part | Write at the time of the issue |
| Tool sign-out book | A book where borrowed tools are written with name and date. | Tool register | A4 | Count tools monthly |
| Bearing | A part with balls or rollers that lets a shaft turn smoothly. | Ball bearing | Number from the old one | Do not drop it |
| Seal kit | Rubber rings and washers that stop a leak at a pump or valve. | Gasket and O-ring kit | Made for the pump model | Fit the right size |
| V-belt | A rubber belt with a V-shaped cross-section that drives a pulley. | Drive belt, fan belt | Number printed on the belt | Replace a set together |
| Filter | A cartridge that cleans air, oil, fuel or water. | Air, oil, fuel or water filter | By part number | Fit only the right one |
| Fuse | A part that melts when current is too high and cuts the circuit. | Cartridge fuse, blade fuse | Rating in amps | Never replace with a wire or foil |
| Spark plug | A part that makes the spark that lights petrol in a small engine. | Plug | By part number | Only when the engine is cold |
| Bolt and nut | A threaded pin and its nut. Grade is marked on the head. | Fastener | By size and grade | Replace like with like |
| First-aid kit | See Unit 1. |
Safety protocol: Working in the store
Before. Keep the walkway clear. Wear boots. Check shelves are stable.
While you work. Lift heavy items with a bent knee or ask for help. Do not stand on a shelf. Keep fuel, oil and batteries as their labels say, away from sparks.
After. Lock the store, record issues on the stock cards.
Emergency. A fall or lifting injury: stop, call 112 for serious injury. Small fire: use an extinguisher if trained; call 112.
Stock sums
(1) A filter is used 3 a month, delivery takes 2 weeks (half a month), safety stock 1. What minimum? (2) A stock card shows balance 8, out 3, in 5. What is the new balance? (3) You hold 12 belts and use 2 a month. How many months will they last?
Set up a mini-store
- Collect 20 parts, consumables and tools from the site or workshop.
- Sort, label and place them in bins with codes.
- Make a stock card for each part and write the opening count.
- Set a minimum and maximum for five common parts.
- Run a sign-out book for tools for a week, then count everything. Do the numbers match? If not, find why.
Your kitchen store
Treat your kitchen or kiosk shelf as a store. List ten items with how much you use a month and how long it takes to buy more. Work out a minimum for three of them.
Check yourself
- Why keep a stock card?
- What is the minimum (reorder) level?
- Why write down who borrowed a tool?
Unit 6 · Logs, simple measures and reports
What you do not write down, you will repeat.
Competency standard
| Learning outcome | Performance criteria — the trainee… |
|---|---|
| 6.1 Keep an equipment history | writes each fault, repair and service on that machine's history card |
| 6.2 Count downtime | records start and end of every stop |
| 6.3 Work out simple measures | calculates breakdowns, MTBF, MTTR and the planned share |
| 6.4 Write a one-page report | summarises the month for the owner in plain words |
Range. One month of data for at least three machines. Evidence. History cards; calculations; one-page report.
Ask a qualified expert. Some records may be required by law. For example, under Act 328 a factory must keep a general register, report some accidents to the Inspector, and keep a register of lifting equipment. This is general information, not legal advice. Ask the Factories Inspectorate or a qualified lawyer what applies to your business. For a recorded injury, see a doctor or nurse.
The history card
Each A machine has one sheet or one spreadsheet tab: date, work order number, what happened, what was done, parts, hours, cost, signature. The HSE says to keep maintenance logs up to date and to act on reports of faults. Over time the card shows a pattern: the same bearing every 6 months, or a pump that fails after every power cut.
Downtime
Write the time the machine stopped and the time it was back at work. Downtime is the time it could not do its job. Add it up for the month.
Four simple measures
| Measure | What it tells you | How |
|---|---|---|
| Breakdowns (failures) | How often it fails | Count stops that were not planned |
| MTBF (mean time between failures) | How long it runs before failing | Operating time ÷ number of failures |
| MTTR (mean time to repair) | How fast you fix it | Total repair time ÷ number of repairs |
| Planned share | How much work you planned | Planned hours ÷ total maintenance hours × 100 |
These formulas are standard in maintenance management.
Worked example (all numbers are examples). An irrigation pump was scheduled for 240 hours in a month. It failed 3 times. Total repair time was 9 hours.
- MTBF = 240 ÷ 3 = 80 hours
- MTTR = 9 ÷ 3 = 3 hours
- Availability = (240 - 9) ÷ 240 × 100 = 96.25%
- Maintenance hours that month: 30 planned and 10 breakdown, 40 total. Planned share = 30 ÷ 40 × 100 = 75%
A source gives 70% to 85% as a typical range for the planned share, with some sources aiming for 85% or 90%. Targets differ between sources, so compare your own month with your own last month.
A one-page report
| Section | Content |
|---|---|
| Headline | One sentence: what the month looked like |
| Numbers | Breakdowns, downtime, MTBF, MTTR, planned share |
| Biggest problem | Which machine, why, what you will do |
| Money | Cost of repairs and parts this month |
| Needs from the owner | Decision, money or time you need |
Use plain words. A report that the owner does not read is wasted; keep it to one page.
Tools and items: Unit 6
| Item | What it is and what it does | Also called | Size or type | Caution |
|---|---|---|---|---|
| History card | One sheet or spreadsheet tab for one machine that lists every fault and service. | Equipment history, machine log | A4 or a tab | Keep it up to date |
| Downtime log | A list of every stop with start and end times. | Stop log | A4 | Write the time at once |
| Stopwatch or phone clock | Measures the minutes of a stop or a job. | Timer | Any | None |
| Calculator | A small device for the sums. | Any | Check each answer twice | |
| Spreadsheet | A computer or phone table that adds and calculates for you. | Excel, Sheets | Any | Keep a paper copy |
| Monthly report | One page that tells the owner the numbers and needs. | One-page report | A4 | Plain words |
(See Appendix B for the formula card with worked examples.)
Measures
A mill was scheduled to run 200 hours. It failed 4 times, with repair times of 2, 3, 1 and 2 hours. (1) MTBF? (2) MTTR? (3) Availability? (4) Of 25 maintenance hours, 20 were planned. Planned share?
Month-end report
- Take your history cards and work orders for the month.
- Count breakdowns and downtime for three machines.
- Calculate MTBF, MTTR and the planned share for one machine.
- Write the one-page report.
- Present it to your trainer in two minutes and answer one question.
Measure a stop
Ask a shopkeeper or farmer how long their machine, freezer or phone charger was out of use in the last month. Work out the percentage of time it was available.
Check yourself
- What is downtime?
- A machine ran 100 hours and failed 2 times. What is the MTBF?
- What goes at the top of a one-page report?
Unit 7 · Plan a small job, work with others and earn
Planning a job takes an hour. Not planning one can take a week.
Competency standard
| Learning outcome | Performance criteria — the trainee… |
|---|---|
| 7.1 Plan a small job | lists tasks, order, people, parts, time and safety for a one-to-three-day job |
| 7.2 Brief technicians and contractors | gives a clear written scope and checks who does what |
| 7.3 Handover | inspects the finished job against the scope and signs only when satisfied |
| 7.4 Find paid work | names a service, a customer group, a location and a way to market it |
Range. One small job on a farm, in a workshop or at a small mill. Evidence. Job plan; written scope; business idea sheet.
Ask a qualified expert. This unit contains money, legal and registration points. This is general information, not legal advice or tax advice. Ask a qualified lawyer, GRA or a qualified accountant before you act. Electrical, lifting, gas, pressure and structural work must be done or approved by an Energy Commission-certified electrician or a GhIE-registered engineer. Practising engineering in Ghana without being registered is not allowed under the Engineering Council Act.
Plan a small job
A job plan answers: what, in what order, who, with what, how long, how safe.
- Write the goal in one line: "Replace the pump seal and test the pump."
- List the tasks in order: isolate and lock out, drain, remove, fit new seal, refit, test, clean up.
- Estimate the time for each task, and add a little for surprises.
- List the people, parts and tools; check the store.
- Write the safety steps and who is in charge.
- Set a date when the machine is not needed, for example after harvest or early on a quiet day.
- Tell everyone affected.
Work with technicians and contractors
A technician is a skilled worker; a contractor is an outside business. HSE guidance on managing contractors describes five steps: plan the work, choose the contractor, control the work on site, keep a check, and review afterwards. Apply them in a small way:
- Choose by skill and record, not only by price. Ask to see earlier work and ask a past customer.
- Write the scope: what is included, what is not, the date, the price and who buys parts.
- Agree the price before work starts and write it down.
- Check the work as it goes and at the end. Use the scope as the checklist.
- Pay fairly and on time, after you are satisfied. Keep the receipt.
Registered engineers and artisans in Ghana
The Engineering Council Act, 2011 (Act 819) sets up registers for engineering practitioners, and the Engineering Council says that practising engineering without registration is prohibited. The Ghana Institution of Engineers has also inducted and licensed artisans and craftsmen, including 118 in Takoradi. The full rules were not read here. Ask the Engineering Council or GhIE what applies to the work you want to do or hire.
Earn from maintenance
Many farms, schools, hotels and small factories have equipment and no one who manages it. You can offer:
- a monthly equipment check round with a report;
- a register and schedule set-up service;
- stores set-up and stock counts;
- managing contractors for an owner who is away.
Where to work. Choose a place with many small businesses close together that run machines: a market, a fishing community, a farming belt or an industrial area. Takoradi has many workshops and mills. Start with people who already know you.
Market yourself. Use a WhatsApp Business profile, a Google Business Profile, a neat sign and business card, and referrals. Show before and after photos with the owner's permission, a sample report with the names removed, and a short testimonial.
Staying inside the law. At this level you manage and plan. Do not do electrical, gas, lifting or pressure work yourself unless you are authorised, and do not describe yourself as an engineer unless you are registered.
Registering a small business
You register a business name at the Office of the Registrar of Companies for GH¢130, and renewal is GH¢70 a year (2026 fees). Your Ghana Card number is your tax number (TIN). Ask the Assembly about an operating permit; the Sekondi-Takoradi Metropolitan Assembly says master artisans must register their trainees.
Tools and items: Unit 7
| Item | What it is and what it does | Also called | Size or type | Caution |
|---|---|---|---|---|
| Job plan | A page that lists goal, tasks, people, parts, time and safety. | Work plan | A4 | Write before you start |
| Scope of work | The written list of what the job includes and excludes. | Work scope, brief | Half a page | Both sides sign |
| Quotation | A written price from a supplier or contractor. | Quote, estimate | One page | Ask for it before the work |
| Receipt | Proof of payment. | Payment slip | Numbered book | Keep it |
| Business card | A small card with your name, service and number. | Visiting card | Standard | Neat and clear |
Price a monthly check service (all prices are examples)
You offer a monthly check round to 6 small farms at GH¢250 each. Each visit costs you GH¢40 transport and GH¢20 consumables. You spend half a day per farm. (1) Monthly income? (2) Monthly costs? (3) Profit before your own pay? (4) If you work 3 days a month on this, what is the profit per day?
Accessibility
The Persons with Disability Act, 2006 bans job discrimination. Planning, work orders, stock cards, records and reports are desk work and suit wheelchair users and many people with limited mobility. Deaf people need visual signs and written orders for lockout and permits. Adjustments such as a store with wide aisles, labels in large print, and a phone list of contractors help everyone. The tasks near running machines need a careful risk check for each person.
Plan a small job
- Pick a real job from your site: a pump service, a gate repair or a store tidy-up.
- Write the plan: goal, tasks in order, time, people, parts, safety, date.
- Write a half-page scope for a technician or contractor.
- Do the job or role-play the handover; check the work against the scope.
- Write one business idea for yourself: service, customers, place, price and how you will market it.
Ask three questions
Ask a local mechanic, electrician or technician three questions: what do customers usually forget, what parts are hardest to get, what do they wish owners wrote down. Write the answers.
Check yourself
- Name four things a job plan answers.
- What should a written scope include?
- Can you call yourself an engineer after this module?
Glossary
| Term | Meaning |
|---|---|
| Asset | Anything you must keep working, such as a pump or a mill |
| Availability | The share of scheduled time a machine could work |
| Bench card | A one-side reference card kept at the workbench |
| Criticality | How badly the business is hurt if the machine stops (A, B or C) |
| Daily check | A short look, listen, smell and feel check by the operator |
| Grease | Oil in a thick carrier that stays in a bearing |
| History card | The list of faults and services for one machine |
| Isolate | Cut the energy supply so the machine cannot start |
| Lead time | Time from ordering to delivery |
| Nameplate | The plate on a machine with maker, model and ratings |
| Near miss | An event that could have hurt someone but did not |
| NLGI | A number for how thick (stiff) a grease is |
| PM schedule | The list of preventive tasks and how often they are done |
| PPE | Personal protective equipment |
| SAE | A number for how thick an oil is; it does not show quality |
| Spare part | A part kept in store to replace a worn one |
| Tag number | A short code that names a machine, for example P-01 |
| Uptime | Time a machine is able to do its job |
| Breakdown | An unplanned stop |
| Contractor | An outside business hired for a job |
| Corrective maintenance | Repairing a fault you found, on a planned date |
| Critical equipment | A machine that stops the business if it fails |
| Downtime | Time a machine cannot do its job |
| Lockout | Putting your own lock on the energy source |
| MTBF | Mean time between failures |
| MTTR | Mean time to repair |
| Preventive maintenance | Servicing on a schedule before failure |
| Scope | A written list of what a job includes |
| Stock card | A record of parts in and out |
| Work order | A written job instruction and record |
A note on names. Local names for tools differ from town to town. Use the standard name given in this book, in the Tools and items tables and in Appendix H, when you order or ask for help, and show the picture. Appendix H is the full Tools and Items Glossary.
Logbook
Copy these pages into an exercise book. Your logbook is part of your assessment evidence.
- Unit 1: safety walk notes; breakdown story
- Unit 2: asset list with tags and A, B, C marks
- Unit 3: five closed work orders
- Unit 4: PM sheet; ten days of daily checklists
- Unit 5: stock cards; stock count result; tool sign-out book
- Unit 6: history cards; measures; one-page report
- Unit 7: job plan; written scope; business idea sheet
- Every homework, dated
Self-check quiz
- Name the three kinds of maintenance.
- List the golden rule steps before a hands-on job.
- Who may remove your lock?
- What is a tag number?
- Which priority always comes first?
- Name the five steps of a work order.
- Where do you find how often to change oil?
- Why keep a stock card?
- A part is used 4 a month, delivery takes half a month, safety stock 1. What minimum?
- A machine ran 90 hours and failed 3 times. What is the MTBF?
- Name three things in a written scope for a contractor.
- Why must you not call yourself an engineer unless registered?
Appendix A · Forms to copy
Copy a form into an exercise book or a spreadsheet. A form is a record, not a permit to do dangerous work. Black and white A4 is enough.
Ask a qualified expert. Forms record work; they do not make a job safe. For electrical, gas, pressure, lifting and structural work ask an Energy Commission-certified electrician or a GhIE-registered engineer. Some records may be required by law; ask the Factories Inspectorate or a qualified lawyer what applies to you.
A1 · Work request and work order
Use the job card in Unit 3. How to fill: boxes 1 to 5 before the job, box 6 with the technician, boxes 7 and 8 after.
A2 · Equipment register (asset list)
| Tag | Item | Place | Maker | Model | Serial no. | Rating (kW, V, A) | Date installed | Manual filed Y/N | A, B or C | Spares list link |
|---|---|---|---|---|---|---|---|---|---|---|
How to fill: one line per machine; copy the plate exactly; A if the business stops when it fails, B if it hurts, C if it can wait.
A3 · PM schedule card (one per machine)
| Task | How often (days or hours; whichever comes first) | Who | Minutes | Tools and parts | Last done | Next due |
|---|---|---|---|---|---|---|
How to fill: take tasks and intervals from the manual. "Whichever comes first" means the calendar or the running hours, whichever is reached first.
A4 · Daily operator check
| Date | Machine tag | Oil or fluid level | Leaks | Guards on | New noise or smell | Hours reading | Operator sign |
|---|---|---|---|---|---|---|---|
How to fill: look, listen, smell and feel with the machine stopped and locked out. Write a real answer. A fault means a work order.
A5 · Downtime log
| Date | Tag | Stop time | Start time | Planned or unplanned | Cause (short) | Reported by |
|---|---|---|---|---|---|---|
How to fill: write the stop and restart times at once. Downtime = start time minus stop time.
A6 · Equipment history card
| Date | Work order no. | What happened | What was done | Parts used | Hours | Cost | Sign |
|---|---|---|---|---|---|---|---|
How to fill: one line per event. Over a year the card shows patterns.
A7 · One-page monthly report
| Section | What to write |
|---|---|
| Headline | One sentence |
| Numbers | Breakdowns, downtime hours, MTBF, MTTR, planned share |
| Biggest problem and plan | Machine, cause, action |
| Money | Cost of parts and repairs |
| Needs from the owner | Decision, money, time |
A8 · Stock card and tool sign-out
Stock card: date, work order, in, out, balance, with part, bin, min and max at the top (Unit 5). Tool sign-out: date, tool, name, signature, returned date.
A9 · Near-miss or incident note
| Date and time | Place | What happened (facts only) | Who was involved (no blame words) | What could have happened | What we will change | Reported to |
|---|---|---|---|---|---|---|
How to fill: write it the same day. A near miss costs nothing and teaches a lot.
Appendix B · Formula card and conversions
All numbers are examples. Each result was checked by script.
| Measure | Formula | Worked example |
|---|---|---|
| MTBF | Operating time ÷ number of failures | 240 h ÷ 3 = 80 h |
| MTTR | Total repair time ÷ number of repairs | 9 h ÷ 3 = 3 h |
| Availability | (Scheduled time - downtime) ÷ scheduled time × 100 | (240 - 9) ÷ 240 × 100 = 96.25% |
| Planned share | Planned maintenance hours ÷ all maintenance hours × 100 | 30 ÷ 40 × 100 = 75% |
| Reorder level | Usage during lead time + safety stock | 4 a month × 0.5 month + 1 = 3 |
| Failure rate | 1 ÷ MTBF | 1 ÷ 80 = 0.0125 per hour |
| Cost of one stop | Lost sales per hour × hours + repair cost | GH¢200 × 5 + GH¢300 = GH¢1,300 (all prices are examples) |
| Grease top-up (bearing, typical) | 0.005 × outside diameter (mm) × width (mm) = grams | 0.005 × 52 × 15 = 3.9 g for a 6205 |
Define uptime and downtime before you count. Write on one line what counts as down: for example "any time the machine cannot do its job, including waiting for a part". Use the same line every month.
The grease formula is a re-greasing shot, not a first fill, and is secondary-source typical; the bearing maker's figure always wins. Ask a bearing supplier or a GhIE-registered engineer for the exact quantity.
| Convert | Factor |
|---|---|
| 1 inch | 25.4 mm |
| 1 US gallon | 3.785 litres |
| 1 imperial gallon | 4.546 litres |
| 1 bar | 14.5 psi (about) |
| 1 hp (mechanical) | 0.7457 kW |
| Fahrenheit | °C × 9 ÷ 5 + 32 |
(Conversion factors are from the SI definitions of the units; check against a standard table.)
Appendix C · Bench cards
Ask a qualified expert. Cards are reminders only. Do not use a card instead of the maker's manual, or instead of an electrician, engineer or safety officer where the job needs one.
Card 1 · Golden rule
Tell, stop, isolate, lock and tag, release stored energy, test, work, refit guards, remove your own lock, tell everyone.
Card 2 · Priority
| Priority | Test | Target |
|---|---|---|
| Emergency | Danger to people, or a critical machine is down | Start now; make safe first |
| Urgent | A critical machine is failing, or a B machine is down | This week |
| Routine | Wear that can wait | Next planned slot |
Card 3 · Tag and colour key
Letter plus number: P pump, G generator, M mill, V vehicle, T tool. Colours are your own choice but must be the same everywhere. Example: red tag = out of service, green = ready, yellow = waiting for a part. Write the key on the wall.
Card 4 · Oil and grease chooser
Look in the manual for the thickness (SAE or NLGI), and the class (API for engine oil). Match both. Never mix greases. Label every tin. When in doubt, ask a technician or the dealer.
Card 5 · What is on a nameplate
kW is power; V is voltage; A is current; Hz is frequency; rpm is speed; IP is dust and water protection; insulation class is heat withstand. See Unit 2.
Card 6 · When I stop and call a qualified person
I stop when: the job touches mains electricity, gas, lifting, pressure or a structure; I cannot lock out; I do not know the machine; a guard is missing and cannot be fitted; someone is hurt (call 112).
Appendix D · Who regulates what in Ghana
Ask a qualified expert. This table is general information from public pages read in November 2026, not legal advice. Ask each office in writing before you act, and ask a qualified lawyer what applies to your business. Laws change; check the current text.
| Subject | Who | What we found (reported) | What to ask |
|---|---|---|---|
| Electrical wiring | Energy Commission | Ghana Electrical Wiring Regulations: no wiring on premises unless certified; materials not approved by the Ghana Standards Authority are prohibited. Sources give the law number as L.I. 2008. | Which maintenance jobs need a certified electrician |
| Fire | Ghana National Fire Service | Fire Precaution (Premises) Regulations 2003 (L.I. 1724): fire certificate for workshops, hotels, fuel stations and companies; applications online. | Fuel storage and extinguisher types |
| Factories and plant | Department of Factories Inspectorate | Supervises statutory examination of potentially hazardous plant; issues a yearly certificate under Act 328. The examination schedule was not found. | Which of my machines need examination, how often |
| Working conditions | Labour Act 651 | The employer must provide a safe system of work and safe plant. | What applies to my workers |
| Measuring instruments | Ghana Standards Authority Metrology | Calibration of weighing instruments is done through GSA Metrology. | Calibration of gauges and scales |
| Environment and used oil | Environmental Protection Authority | The Environmental Protection Act 2025 (Act 1124) replaced the earlier Act. Used-oil rules were not found. | How to dispose of used oil, batteries, filters |
| Engineers | Engineering Council | Four registers are reported; practising without registration is not allowed. | Which register fits me |
| Business names | Registrar of Companies, GRA, Assembly | See Unit 7 |
Appendix E · Daily checks by machine type
Ask a qualified expert. Check with the machine stopped and locked out unless the manual says otherwise. Do not open electrical panels, pressure parts or lifting gear. The maker's manual wins.
| Machine | Look | Listen, smell and feel | Why |
|---|---|---|---|
| Water pump | Leaks at the seal, base bolts, guard | New noise; heat at the bearing (use the infrared thermometer) | A leaking seal and a noisy bearing warn days ahead |
| Engine or generator | Oil level, fuel level, leaks, air filter | Unusual smoke, knock or smell | Low oil destroys an engine fast |
| Maize or hammer mill | Belts, guards, screen, bolts | Rattle, vibration, burning smell | A loose guard or belt can injure |
| Vehicle | Tyres, lights, oil, water, leaks | Brake feel, new noises | Failure on the road is dangerous |
| Freezer or cold room | Door seal, ice build-up, temperature | Compressor noise | Stock is lost if it warms |
| Welding machine | Cables, clamps, cover | Hot smell | Damaged cables cause shocks |
| Compressor | Oil level, belt, guard, leaks | Noise, hot casing | A burst tank is a serious hazard; only qualified people repair it |
Appendix F · Common mistakes
| Mistake | Why it hurts | Do this instead |
|---|---|---|
| Wrong grease, or too much grease | Over-greasing can blow a seal | Use the manual's type and amount |
| Replacing the part, not the cause | The fault returns | Ask why it failed |
| No spare for a cheap, vital part | A cheap part stops a big machine | Keep a minimum |
| Losing the manual | You guess intervals | File it; keep a copy |
| Lock removed by someone else | A person may be hurt | Only the owner removes the lock |
| Guard left off after a job | Hands can be caught | Check guards before restart |
| Skipping the daily check | Small faults grow | Block the time |
| Ticking the form without looking | The record lies | Teach honesty |
| Buying on the lowest price | Fake or poor parts | Choose by quality and record |
| No handover | Nobody knows the job is done | Check against the scope and sign |
Appendix G · Short cases
These cases come from public reports. They are not from the author's own files, and no living person is named.
- A tractor fleet. A study of tractor owners in Ghana reported that most faced long breakdowns linked to limited mechanical knowledge, few trained mechanics and hard-to-find spare parts. A farm centre was reported to have ploughed 200 hectares with nine tractors in 2008 and only 40 hectares with two working tractors in 2014. Lesson: a machine that stops for want of a part is a machine you did not manage.
- A school corn mill. A report in February 2026 said low voltage and fluctuations damaged a school corn mill in the Oti Region. Another report found long hours of overvoltage and low voltage in parts of Accra in 2024. Lesson: protect machines from supply faults; ask an Energy Commission-certified electrician about protection.
- A pump seal. A seal leaks again and again because the suction valve is shut when the pump starts. Asking "why" five times finds the cause (Level 2, Unit 4). Lesson: repair the cause, not the leak.
Appendix H · Tools and Items Glossary
Local names for tools differ from town to town. Use the standard name given here when you order or ask for help, and show the picture.
| Name | Meaning | Also called | Used for | Warning | Unit |
|---|---|---|---|---|---|
| Asset register | List of every machine with tag and plate details | Equipment list | Knowing what you must keep working | Keep two copies | 2 |
| Bearing | Ball or roller part that lets a shaft turn | Ball bearing | Reduces friction | Buy trusted, not fake | 4, 5 |
| Bolt and nut | Threaded pin and its nut | Fastener | Joining parts | Use the same grade | 5 |
| Chock | Wedge that stops a wheel rolling | Wheel stop | Holding vehicles | Place on the downhill side | 1 |
| Clamp meter | Meter that reads current by clamping round a wire | Tong tester | Electrician's current check | Electrician use for mains | 4 |
| Downtime log | List of stops with times | Stop log | Counting downtime | Write at once | 6 |
| Dipstick | Rod that shows oil level | Oil level stick | Checking oil | Engine stopped | 4 |
| Filter | Cartridge that cleans air, oil, fuel or water | Protecting the engine or pump | Right part number | 5 | |
| First-aid kit | Box of dressings | First-aid box | Small injuries | Check monthly | 1 |
| Fuse | Part that melts on overload | Cartridge fuse | Protecting a circuit | Same rating only | 5 |
| Grease gun | Hand pump for grease | Grease pump | Greasing bearings | Do not over-grease | 4 |
| Grease nipple | Valve on a bearing for the gun | Zerk fitting | Entry for grease | Clean first | 4 |
| Guard | Cover over moving parts | Safety guard | Keeping hands out | Never remove while running | 1 |
| Hasp | Folding plate for several locks | Lockout hasp | Group lockout | At OFF only | 1 |
| Hour meter | Counter of running hours | Hours counter | Setting service times | Record on card | 4 |
| Infrared thermometer | Non-contact surface thermometer | Temperature gun | Spotting hot bearings | Shiny metal reads low | 4 |
| Isolator | Switch that cuts power to one machine | Disconnector | Safe isolation | Electrician fits it | 1 |
| Job card | Numbered work order | Work order | Planning and recording | Check and sign | 3 |
| Lockout tag | Card that says who locked it | Danger tag | Warning others | Ink, name, date | 1 |
| Manual | The maker's book | Owner's manual | Intervals and parts | Keep a copy | 2 |
| Nameplate | Plate with maker and ratings | Rating plate | Identifying a machine | Do not remove | 2 |
| Oil can and funnel | Small spout can and a cone | Oiler | Adding small amounts of oil | One fluid per funnel | 4 |
| Padlock | Lock with a key | Safety padlock | Locking out | One key each | 1 |
| PPE | Gloves, goggles, boots, ear defenders, dust mask | Safety gear | Protecting the body | Replace if damaged | 1 |
| Rags | Cotton cloths | Wiping cloths | Cleaning | Oily rags can ignite | 4 |
| Seal kit | Rings and washers for a pump | Gasket kit | Stopping a leak | Right model | 5 |
| Spark plug | Part that lights petrol in an engine | Plug | Starting a petrol engine | Cold engine | 5 |
| Spanner set | Tools that turn nuts | Wrench set | Tightening | Right size | 4 |
| Stock card | Record of a part's in and out | Bin card | Stock control | Write at issue | 5 |
| Test lamp | Lamp with two leads | Test light | Simple low-voltage check | Not for mains | 4 |
| Torch | Hand light | Flashlight | Light | Sealed type near fuel | 1 |
| V-belt | Rubber belt with a V shape | Drive belt | Driving a pulley | Replace as a set | 5 |
Appendix I · Index and where to look
| Look for | Where |
|---|---|
| Lockout and isolation | Unit 1, Card 1, Appendix C |
| Asset list, nameplate | Unit 2, Appendix A2 |
| Work order, priorities | Unit 3, Card 2 |
| Daily checks, greasing | Unit 4, Appendix E |
| Stock card, reorder | Unit 5, Appendix B |
| MTBF, MTTR, report | Unit 6, Appendices A7, B |
| Regulators | Appendix D |
| Pumps, engines, wiring, welding | The sister manuals named at the start |
Further reading and sources
Best next reads: your machines' own manuals; the HSE's free page on maintenance of work equipment; the free HSE guide on managing contractors.
What this module does not cover: repair of any particular machine; electrical, gas, lifting and pressure work; civil works, site supervision, quantity estimating and permits (these belong to Civil Engineering); computer maintenance software; and Ghana prices for parts, labour and contractors (not found; all prices here are examples).
Every source used in this manual is listed, with links, in the Teacher Copy.