← All training manualsHouse Electrical Wiring Level 2 · read-onlyGet the PDF with Teacher Copy (GH¢50)
Level 2 · National Proficiency II · CTVET formatTrainee Manual

House Electrical Wiring Level 2

Understand why a circuit is built the way it is. Plan loads, learn earthing and RCDs, help inspect and test, and grow as a skilled helper on the way to certification.

A small house with its wiring: consumer unit, cable, socket, light and earth rod A cut-open single-storey house. Inside, a grey consumer unit with breaker switches on the left wall sends a cable along the wall to a socket and up to a ceiling light. To the right, a certified electrician in a hard hat and rubber boots tests a socket with a meter. Outside, a green and yellow earth rod is driven into the ground beside the house, and a tester and a bundle of cable lie on the ground. CIRCUITS · SOCKETS · LIGHTSEARTH RODTEST BEFORE YOU TOUCH
Trainee name
Training centre
Workshop
Start date
Prepared by De-Graft Afful · Version 1.1.0 · November 2026
01

About this module

Level 1 made you a safe helper who knows the parts. Level 2 makes you a helper who understands the reasons: why a socket circuit has a different cable from a lighting circuit, why the earth matters, and why the electrician tests before anything is switched on.

Who it is for. People who have finished House Electrical Wiring (Level 1), or who can show the same skills. National Proficiency II covers varied work, mostly routine, under limited supervision; it leads to National Certificate I.

The law has not changed. Wiring must be done by an Energy Commission-certified electrician under the Electrical Wiring Regulations, 2011 (L.I. 2008). Hiring an uncertified electrician can lead to a fine of up to 250 penalty units, up to two years in prison, or both. This module is not the certification syllabus, and nothing in it allows you to wire, test live or certify. Ask the Energy Commission for the current syllabus and rules.

Bridge from Level 1: what you already know

  • The four dangers: shock, burns, fire and falls
  • Isolate, lock out, test dead, and prove, test, prove
  • Who may wire in Ghana, the Installation Completion Certificate and the ECG meter route
  • Volts, amps, watts and kilowatt-hours; amps = watts ÷ volts
  • The parts: meter, main switch, consumer unit, breakers, circuits, cables, switches, sockets, lights, earth
  • Spotting substandard cable by its marks, length, magnet test and price
  • Assisting on dead circuits: marking, boxes, conduit, unconnected cable
  • Warning signs of wiring faults and what to do
  • The apprentice route and honest marketing

Level 1 did not cover load lists, cable and breaker ideas, earthing and RCDs in depth, switching arrangements, inspection and testing, or backup power. Level 2 covers these as ideas and assistant tasks. The certified electrician still chooses, connects, tests and certifies.

How the module works

Each unit has learning outcomes, performance criteria, the range and the evidence your assessor needs. You are judged Competent or Not Yet Competent. About 60% of the time is practical on a dead board or beside a certified electrician.

02

Unit 1 · Safe isolation and proving dead, in detail

The most dangerous words in this trade are "it is off". The safest are "I locked it, I tested it, I tested the tester."

Competency standard

Learning outcome Performance criteria — the trainee…
1.1 Describe safe isolation lists every step in order and gives a reason for each
1.2 Lock out properly fits personal lock and tag; keeps the key; checks other supplies
1.3 Explain prove-test-prove says why the tester is proved before and after
1.4 Refuse unsafe jobs stops and reports when isolation cannot be shown

Range. Single-phase house; the training board; the CEWP does the tests. Evidence. Observation; oral questions; lock-out record.

Ask a qualified expert. For all electrical work, hire an Energy Commission-certified electrician (CEWP). You never test or work on a live circuit. For any shock or burn, see a doctor or nurse; call 112 in an emergency. This is general information, not legal advice; ask the Energy Commission about the law.

The steps of safe isolation

  1. Identify which circuit and which breaker. Look at labels, but do not trust them: the CEWP checks.
  2. Switch off the breaker (and the main switch if the whole house is involved).
  3. Lock out with a personal padlock and tag. One lock per person, one key per lock.
  4. Prove the tester. The CEWP uses an approved voltage indicator on a known live source or a proving unit, to show that the tester works.
  5. Test between every pair of conductors that matter (live to neutral, live to earth, neutral to earth) at the point of work.
  6. Prove the tester again on the known source to show that it did not fail during the test.
  7. Only then may work on the dead circuit begin. Keep the lock on until the job is done, tools are out and everyone is clear.

This is the "prove, test, prove" method used in UK trade guidance based on HSE GS38; the guidance says that a non-contact detector shows live but does not prove dead, and that a multimeter should not be used to prove dead. US rules say live parts must be de-energised and that circuits are not de-energised until verified with test equipment. These are foreign sources; Ghana's own rules are in L.I. 2008, which was not read in full for this book.

Tools and items for this unit

Item What it is and what it does When you use it Size or type Also called Helper status
Two-pole voltage tester (approved voltage indicator) A tester with two probes and a lamp or display, used to prove a circuit dead In step 5 of isolation Short, shrouded probe tips (the UK guidance GS 38 asks for short exposed tips; foreign, not verified here); marked to IEC 61243-3 (international) voltage indicator, two-pole tester, voltage detector CEWP uses; you watch and read aloud
Proving unit A small box that gives a known voltage Before and after each test Pocket size proving stick, proving device CEWP uses
Lock-off kit A padlock, tag, hasp and breaker clips in one pouch Every isolation Personal lock, one key lockout kit, LOTO kit You use your own lock
Permit-to-work or isolation tag A written note of who isolated what and when On bigger jobs A5 card work permit, PTW You fill your part
Insulated gloves and mat Rubber gloves and a mat rated for electrical use For the CEWP's protection near live parts; they never make live work allowed Check the rating stamped on them electrical gloves, rubber gloves You do not rely on them

SAFETY PROTOCOL: safe isolation drill (hazardous task, CEWP-led).

Before: CEWP named and present; PPE on; lock-off kit (padlock, tag, hasp, register) checked; tester and proving unit checked and dry; the circuit and its supply identified on the board; the people in the house told.

While: Do isolate at the breaker, lock out, then prove the tester on the proving unit, test every conductor, and prove the tester again. Do read the tester aloud. Do not trust a switch position, a tripped breaker or a non-contact detector as proof. Do not remove another person's lock. Do not work if the tester fails the prove step.

After: all tools out and counted; the lock removed only by its owner after the CEWP agrees; sign the register; store the kit; report any faulty instrument or lock.

Emergency: if there is a shock, do not touch the person; switch off the supply; call 112; first aid as in Level 1. Isolate the whole supply at the main switch if needed.

Why "off" is not enough

  • A breaker may be mislabelled or may supply more than one circuit.
  • A second supply (a generator, a solar system, a borrowed feed) may still be live.
  • A tester can fail without warning, so it is proved before and after.
  • Another person may switch the breaker back on.

What the helper does

You do not do the test. You: bring the lock kit; fit your own lock when the CEWP says; stay at the board so nobody switches it on; watch the steps and say them aloud; keep the key. If you did not see the test, treat the circuit as live.

Is a voltage indicator with batteries acceptable? Trade pages disagree about batteries in an approved voltage indicator. The official GS38 text was not read for this book. Ask the CEWP which instrument they use, and why.

Put the steps in order

Your trainer gives you eight cards with the steps in a mixed order (identify, switch off, lock out, prove the tester, test, prove again, start work, remove lock when done). Put them in the right order and say why each step comes where it does.

Isolation drill on a dead board

  1. Put on boots, glasses and gloves.
  2. The CEWP names the circuit. You find its breaker and switch it off.
  3. Fit your lock and tag. Check the lock cannot be removed by hand.
  4. Watch the CEWP prove the tester, test and prove again. Say each step aloud.
  5. Fit a second tag: "Do not switch on. Person working."
  6. Remove your lock only when the CEWP agrees the job is complete.
  7. Record the drill: circuit, time, who tested, who locked.

Draw the sequence

Draw the isolation sequence as a flow chart with a one-line reason for each step. Explain it to a family member.

Check yourself

  1. Name the three tests that prove a tester works.
  2. Why is a switched-off breaker not proof?
  3. When may the lock be removed?
03

Unit 2 · Load lists, circuits, cable and breaker ideas

A circuit is a promise: this cable, this breaker and these appliances will work together without getting too hot.

Competency standard

Learning outcome Performance criteria — the trainee…
2.1 Make a load list lists appliances with watts and calculates amps
2.2 Explain cable and breaker pairing says why a cable and a breaker are chosen together
2.3 Group loads into circuits suggests circuits for a small house for the CEWP to check
2.4 Estimate materials lists cable lengths and counts for the CEWP to confirm

Range. Small single-phase house; examples; the CEWP confirms. Evidence. Load list; circuit sketch; materials list.

Ask a qualified expert. The sizes of cables and breakers, the number of circuits and the earthing arrangement are chosen by an Energy Commission-certified electrician under L.I. 2008 and GS 1009. The numbers in this unit teach ideas and are examples, not rules. This is general information, not legal advice.

The load list

For each appliance write the watts (from its label), divide by 230 volts to get amps, and add them up. This gives the biggest current the house could draw if everything ran at once. A real design allows for the fact that not everything runs at once, but the way to allow for that is the CEWP's job under the regulations (not covered here).

Why a cable and a breaker are chosen together

The cable carries the current. The breaker protects the cable by tripping before the cable overheats. A thin cable on a big breaker is dangerous because the breaker will not trip while the cable is cooking. A thick cable on a small breaker is safe but costs more than needed. So the CEWP picks them as a pair.

Examples from other countries (foreign, not Ghana rules)

A Malaysian wireman's guide gives, as a typical idea, 1.5 mm² cable for lighting protected by a 6 A breaker, 2.5 mm² for sockets, and a 16 A breaker for an air conditioner point. The sizes and breaker ratings differ between countries and the sources do not always agree. In Ghana the CEWP decides under L.I. 2008 and GS 1009, which were not read for this book.

From the field: the house that burnt

The moment. A house was burnt down within two years of use. The whole house and all its wiring were lost.

The problem. Three air conditioners were running on one cable. That cable was the same size as the one bringing the mains in from the electricity company.

The cause. The cable was too small for the load, so it overheated, the wires touched, and the spark started the fire.

What was done. Nothing could be saved. [[FLAG: author to confirm: any action taken afterwards, who inspected]]

The lesson. One small cable cannot carry three air conditioners.

Next time. 1. Add up the load before choosing the cable. 2. Give each big load its own correctly sized circuit and breaker. 3. Use good-quality cable and ask a qualified, certified electrician to check the design.

Told by De-Graft Afful, from his own site experience.

Technical note (international method, labelled). Each circuit is sized for its own load, and the breaker is chosen for the cable: the load current must not exceed the breaker rating, and the breaker rating must not exceed the cable's safe current. The service cable only brings the supply to the house; it does not size your circuits. An inspection before connection should have caught this. Ask a qualified expert: an Energy Commission-certified electrician (CEWP) sizes cables under L.I. 2008.

The sizing method in five steps (international, labelled; Ghana values by the CEWP)

  1. List the loads on the circuit and find the design current Ib = watts ÷ volts (add the power factor for motors).
  2. Choose the breaker In so that In is not less than Ib.
  3. Find the real cable rating needed: It ≥ In ÷ (Ca × Cg × Ci × Cc), where Ca is the ambient-temperature factor, Cg the grouping factor, Ci the thermal-insulation factor and Cc the factor for the type of protective device. Appendix C gives typical values.
  4. Pick the cable size from the current-carrying table (Appendix A) for the installation method that matches the job.
  5. Check voltage drop (Appendix B). If the drop is too big, use a larger cable.

Worked example: three air conditioners (example numbers, international method)

Three split air conditioners of 1,800 W each (example). Each draws 1,800 ÷ 230 = 7.83 A, together 23.5 A, and each has a start-up surge on top.

  • Wrong: one cable and one breaker for all three. Each conductor carries 23.5 A at all times plus surges.
  • Right: one circuit per air conditioner, each with its own breaker, for example 2.5 mm² copper with a 16 A breaker (Ib 7.83 A is not more than In 16 A, and 16 A is not more than the cable's safe current under Appendix A). If a shared feed to a small board is used, size it for the sum, 23.5 A, with a 32 A breaker and 6 mm² cable, and a separate protected branch to each unit.
  • Heat check (recalculated by script): a 2.5 mm² cable carrying 23.5 A loses 9.9 W in every metre as heat; 7.8 A loses only 1.1 W per metre.

The example teaches the method. The real cable and breaker for a real house are chosen by the CEWP under L.I. 2008 and GS 1009, whose tables were not found free online.

Separate circuits

Typical groups for a house: lights; sockets; air conditioners (one per unit); water heater; cooker. Separate circuits mean one fault does not put out the whole house, and heavy appliances do not share a thin cable with lamps.

Load list for a small house

Example appliances: 8 LED lamps at 10 W; a fridge 150 W; a TV 100 W; 2 fans at 60 W each; an iron 1,500 W; a kettle 2,000 W; an air conditioner 1,100 W; a water heater 3,000 W. Supply 230 V. (1) Find the amps for each appliance or group. (2) Find the total watts and total amps if everything ran at once. (3) The 13 A plug on the iron and the kettle on one extension lead: could they be used together safely? A 13 A plug carries about 13 × 230 watts at most.

Load list and circuit sketch

  1. List every appliance in a two-bedroom house plan given by the instructor with its watts.
  2. Calculate amps for each; add them.
  3. Group them into circuits (lights, sockets, AC, heater) on a sketch.
  4. Estimate the cable length for each circuit from the plan scale (the CEWP will correct you).
  5. Present your sketch to the instructor and note the corrections.

Your own load list

List ten appliances in your home with their watts. Find the total amps if all ran at once. Say which three you would put on a separate circuit.

Check yourself

  1. Why is a thin cable with a large breaker dangerous?
  2. What is the formula for amps?
  3. Who decides cable and breaker sizes in Ghana?
04

Unit 3 · Earthing, bonding and RCDs

The earth wire is the quiet hero. You never notice it until the day it saves a life.

Competency standard

Learning outcome Performance criteria — the trainee…
3.1 Explain earthing says how the earth path makes breakers trip and protects people
3.2 Name the parts names the earth electrode, earth conductor, main earthing terminal and protective conductors
3.3 Explain an RCD says what an RCD senses and what the test button does
3.4 Spot earthing problems identifies missing earth pins, loose clamps and damaged conductors

Range. Single-phase house; earthing ideas; dead board. Evidence. Drawing; oral questions; visual inspection record.

Ask a qualified expert. Earthing and RCD work is done, tested and certified by an Energy Commission-certified electrician. Never remove, bypass or "fix" an earth, and never tape over an RCD. For shock injuries, see a doctor or nurse.

What the earth does

The earth gives fault current a low-resistance path back, so that a large current flows and the breaker trips quickly. Without it, a faulty metal case stays live and you become the path. The earth electrode, a rod, plate or mesh, passes current into the soil, which should be damp across the seasons. The quality of the earth is measured with a tester, not assumed.

From the field: the old house with the dead earth

The moment. A house more than thirty years old. The owner was getting shocks from most metal surfaces, and the power use was high.

The problem. The earth was completely out of order.

The cause. An old earth and old wiring that had been left too long.

What was done. A new earth was built and the old wiring was changed. The shocks stopped.

The lesson. A shock from metal means the earth has failed.

Next time. 1. Treat any shock from metal as an emergency and switch off. 2. Have a qualified electrician test the earth. 3. Replace old wiring, not just the earth.

Told by De-Graft Afful, from his own site experience.

Technical note (international, labelled). A broken or very high-resistance earth cannot carry fault current away, so a faulty metal case stays live and a person touching it takes the shock. Old insulation also leaks, which adds to the bill. The cure is to test and rebuild the earth and replace the old wiring. The target resistance depends on the earthing system and the protective device (Appendix E; international rule, Ghana value to be checked). Ask a qualified expert: an Energy Commission-certified electrician.

A study of 1,004 homes in the Sunyani Municipality reported that 96.64% had earth electrode resistance above the value accepted by the Energy Commission (the value was not shown in the summary I could read). The Electricity Company of Ghana also trained electrical contractors on earthing in 2023.

Parts of the earth system

Labelled parts of a house earth system A house in section with a consumer unit, an earthing conductor running down through the ground to an earth rod in an inspection chamber, a bonding conductor to a water pipe, and the soil around the rod. CU 1 2 3 4 5 6 7
Parts of a house earth system
No. Part What it does Safety rule
1 Earth electrode (rod) Passes fault current into the soil Never remove; keep the soil around it damp
2 Earth clamp Joins the earthing conductor to the rod Tight and corrosion-free; CEWP only
3 Earth inspection chamber A covered pit for testing and inspection Keep the cover on and clear of litter
4 Earthing conductor Green-and-yellow wire to the main earthing terminal Never cut or join it
5 Consumer unit with main earthing terminal Where the earth and bonding wires meet Never open
6 Bonding conductor to the water pipe Keeps pipes and the earth at the same level Never remove a bonding clamp
7 Soil The medium that takes the current Dry soil gives a poor earth
Part Job
Earth electrode (for example a rod) Passes fault current into the ground
Earthing conductor Joins the electrode to the main earthing terminal
Main earthing terminal The meeting point at the consumer unit
Protective conductors (the earth wires in cables) Carry fault current from sockets, lights and appliances
Bonding conductors Join metal pipes and parts so they stay at the same level

SAFETY PROTOCOL: installing an earth rod and chamber (digging and hammering).

Before: the CEWP has marked the position; check for buried pipes and cables (ask the plumber and the electricity company before digging); glasses, gloves, boots, ear protection; a rod driver (sleeve) or a heavy hammer with a sound handle.

While: Do drive straight with a second person steadying only with a tool, never with a hand. Do keep away from any live line above. Do not drive into an unknown buried object; do not work in water or in heavy rain.

After: fit the clamp and the chamber cover as the CEWP directs; clean up; return tools; the CEWP tests the earth.

Emergency: for a hit cable or pipe, stop, keep away, call the CEWP; for injury or shock call 112.

Earthing systems and the 50 volt rule (international, labelled)

International standards describe the earthing arrangement of a supply by letters. TN systems return fault current to the supply along a conductor (the supply company provides the earth return). TT systems return fault current through the ground, so the house's own earth electrode matters very much. Which one Ghana's domestic supply uses is not confirmed: one weak source suggests TT. Ghana's earthing system: to be checked with ECG and in GS 1009. Do not assume.

The international touch-voltage rule for a TT installation is that the electrode resistance in ohms times the rated trip current of the RCD in amps must not exceed 50 volts. With a 30 mA RCD this gives at most 50 ÷ 0.03 = 1,667 ohms on paper, but good practice asks for a much lower electrode resistance, because soil dries and electrodes corrode (international practice; not verified in a source read for this book). The CEWP measures the real value with an earth tester. See Appendix E for the full one-page note.

Tools and items for this unit

Item What it is and what it does When you use it Size or type Also called Helper status
Earth electrode (rod, plate or mesh) A metal conductor buried in the ground At the house earth Copper-bonded or galvanised steel rod; length and diameter set by the CEWP earth rod, ground rod You may carry and hold it
Earth clamp A clamp joining the earthing conductor to the rod At the rod Matches rod diameter ground clamp, rod clamp CEWP only
Earth inspection chamber A small covered pit with the rod head inside Lets the CEWP test and inspect the earth Plastic or concrete box earth pit, inspection pit You may help dig, as told
Earthing conductor The wire from the rod to the main earthing terminal Between rod and board Green-and-yellow (international colour); size set by the CEWP earth wire, ground wire CEWP only
Main earthing terminal The terminal where all earth and bonding wires meet At the consumer unit Brass bar MET, earth block Never touch
Bonding conductor and clamp A wire and clamp that join metal pipes and parts to the main earth Water pipes, gas pipes, structural metal Size set by the CEWP bonding wire, equipotential wire CEWP only
Earth electrode resistance tester An instrument that reads how well the rod connects to the soil After installing or when a fault is suspected 3-pole spike type or clamp type earth resistance tester, ground tester CEWP uses; you read aloud
RCD tester An instrument that checks the trip time and current of an RCD During testing Plug-in or lead type RCD test unit, trip tester CEWP uses

RCD

Photograph of an RCD and a row of miniature circuit breakersA real distribution board front: on the left an RCD with a TEST button and a blue switch handle, then a row of miniature circuit breakers with black toggles and printed ratings, under a strip of circuit labels. 1 2 3 4 5
A real distribution board front: an RCD on the left and a row of MCBs. Numbers match the table below. (Photo: Balurbala, CC BY-SA 3.0)
No. Part What it does Safety rule
1 TEST button Makes a small test leakage to prove the RCD trips Press it as the electrician shows; if the RCD does not trip, call the CEWP
2 RCD switch handle (blue) Switches the RCD on and off and shows that it has tripped Do not hold it on
3 MCB toggle (black) Switches that circuit on and off and shows a trip Never hold or tape it on
4 Rating mark (here C 10) Shows the trip curve (C) and the current in amps (10) Replace only with the same rating, by the CEWP
5 Circuit label strip Names each circuit (1Y1, 1Y2 and so on) Keep it up to date

(The label on this RCD reads 100 mA. The 30 mA setting is the usual one for protecting people, as written below.)

Labelled parts of an MCB and an RCD Left, a miniature circuit breaker with a toggle, a rating mark and breaking capacity and terminals; right, a residual current device with a toggle, a TEST button, a rating label and four terminals. C16 6000 TEST 30 mA 40 A Type A 1 2 3 4 5 6 7 8 9
Parts of an MCB (left) and an RCD (right)
No. Part What it does Safety rule
1 MCB toggle Switches the breaker on or off and shows a trip Never hold or tape it on
2 Rating and curve mark (for example C16) Says the trip curve (C) and the current (16 A) Replace only with the same rating, by the CEWP
3 Breaking capacity mark The biggest fault current it can break Must be above the available fault current
4 MCB terminals Where the cables are clamped Tight; CEWP only
5 RCD terminals (lower) Load connections CEWP only
6 TEST button Makes a small test leakage to prove the RCD trips Press as the electrician shows; if it does not trip, call the CEWP
7 Rating label (30 mA, 40 A, Type A) Leakage setting, current rating and type Check the type suits the load
8 RCD toggle Resets the RCD Do not hold on
9 RCD terminals (upper) Supply connections CEWP only

A residual current device (RCD) compares the current going out with the current coming back. If some is leaking, perhaps through a person, it switches off very quickly. A UK presentation says a high-sensitivity RCD of 30 mA or below is designed to cut the supply within 40 ms at five times its rated residual current. UK rules (BS 7671) require 30 mA RCD protection for sockets up to 32 A, and for luminaires in domestic premises on AC final circuits. These are foreign rules. Ghana's own earthing and RCD rules in L.I. 2008 and GS 1009 were not found: ask the certified electrician and the Energy Commission.

No earth, no safety. A socket with no earth connection, or an installation that has never been tested, is a warning sign. A three-pin plug with the earth pin snapped off must be replaced. If your Level 1 survey found missing earths, report them to the CEWP.

Earth path on the dead board

  1. With the board dead and locked, identify the earth conductor from a socket back to the main earthing terminal.
  2. Name every part in the path.
  3. On the training board, look at the RCD and name what its test button does (the CEWP shows it only with the board in a safe state).
  4. Inspect three sample plugs for the earth pin and for the plug's fuse and marks.
  5. Draw the earth path in your logbook.

Earth or not?

Eight situations: (1) Metal-cased fridge plugged into a two-pin adaptor with the earth pin cut off. (2) A new socket with the green and yellow wire connected. (3) A water heater with a loose earth clamp. (4) A rod driven into dry sand with no earth test. (5) A plastic lamp with no earth wire. (6) A breaker that trips when a person touches a faulty appliance. (7) An RCD taped in the on position. (8) A house with a tested earth. For each, say safe or unsafe and why.

Earth hunt

Look at three metal-cased appliances at home. Does the plug have three pins and is it in good condition? Tell an adult if not.

Check yourself

  1. What is the earth for?
  2. What does an RCD sense?
  3. Who may fix a bad earth?
05

Unit 4 · Lighting, switching and socket circuits

A lamp that works only when the switch near the bed and the switch near the door both agree is a nice piece of design. Learn how it is done.

Competency standard

Learning outcome Performance criteria — the trainee…
4.1 Explain a lighting circuit draws one lamp and one switch, and several lamps on one circuit
4.2 Explain two-way switching draws the idea and says where it is used
4.3 Prepare circuits for the CEWP fixes boxes, conduit and sample cable runs on dead circuits
4.4 Handle extension leads safely picks and uses a lead for the load

Range. House lighting, switching, sockets, outdoor lights; dead circuits only. Evidence. Drawings; board preparation; oral questions.

Ask a qualified expert. Connecting lights, switches and sockets, and outdoor and wet-area work, is for an Energy Commission-certified electrician. You prepare boxes and conduit under supervision, and you never connect them. For electrical injuries, see a doctor or nurse.

One lamp, one switch

The switch goes in the live conductor so the lamp is dead when the switch is off. A switch in the neutral leaves the lamp holder live even when the lamp looks off. This is why testing, not trusting, matters. (The CEWP does the connection.)

Many lamps on one circuit

Lamps are joined in parallel so that each gets the full voltage and one broken lamp does not put the rest out.

Two-way switching

Two switches control one lamp from two places, for example the top and bottom of a staircase. Two cables (the "strapping wires") join the two switches. The CEWP connects them; you must label ends so connections are not mixed up.

Sockets

A socket circuit feeds many sockets from one breaker. Each socket must have its earth. Keep the number of heavy appliances on one circuit low. An outdoor socket or a socket in a wet area needs extra protection chosen by the CEWP.

From the field: pipes in the concrete

The moment. Electrical conduits were cast into walls and concrete.

The problem. They clashed with the civil work. [[FLAG: author to confirm: one real case]]

The cause. The conduit routes were not planned with the builders.

What was done. [[FLAG: author to confirm: what was done on that job]]

The lesson. Plan the conduit before the concrete is poured.

Next time. 1. Agree conduit routes with the builder before casting. 2. Never cut a structural member for a conduit. 3. Ask the engineer.

Told by De-Graft Afful, from his own site experience.

Technical note (civil angle). Plan every conduit route on the drawings before casting, together with the structural and plumbing drawings, so conduit does not cross steel bars, columns or beams or other conduits at the same point. Cover to the bars and the engineer's details must not be reduced. Ask a qualified expert: a GhIE-registered engineer, a licensed architect or the District Assembly, and the CEWP for the electrical side.

Tools and items for this unit

Item What it is and what it does When you use it Size or type Also called Helper status
One-way switch A switch with one on-off position for one lamp A single room light 10 A or 16 A rating (typical) 1-way switch CEWP connects
Two-way switch A switch with a changeover contact; two together control one lamp from two places Stairs, bedrooms Same rating 2-way switch, staircase switch CEWP connects
Intermediate switch A third switch type used between two two-way switches for three or more places Long corridors Matches the others cross switch CEWP connects
Dimmer A switch that varies lamp brightness Living rooms; must suit the lamp type Rated in watts; LED-compatible only dimmer switch CEWP connects
Pull-cord switch A ceiling switch operated by a cord Bathrooms (cord is insulating) 6 A or 10 A ceiling pull switch CEWP connects
Fan regulator A control that changes fan speed Ceiling fans Matches fan fan speed controller CEWP connects
Switched socket (13 A, Type G) A wall outlet with its own switch General use 13 A, GS IEC 60884 wall socket, 13 A outlet CEWP connects
Double socket Two outlets in one plate General use 13 A each, but limited by the circuit twin socket CEWP connects
Fused connection unit (spur) A box with a fuse that supplies a fixed appliance Fixed appliances such as a water heater or a fan 13 A with a 3 A, 5 A or 13 A fuse spur unit, FCU CEWP connects
Cooker control unit A switch for the cooker circuit, often with a socket Cookers 45 A (typical) cooker switch CEWP connects
Ceiling rose, batten holder, lamp holder Parts that hold and connect a lamp Ceiling lights Bayonet or screw cap pendant rose CEWP connects
LED lamp, bulb and tube Light sources of different type; LED uses far less energy Lights Watts and base type on the lamp LED bulb, LED tube You may fit with the circuit off

SAFETY PROTOCOL: preparing circuits on a dead wall or in a ceiling.

Before: circuits isolated, locked and tested dead by the CEWP; ladder checked; glasses and dust mask; the plan agreed with the structural drawings.

While: Do keep cable ends capped and unconnected; do work with a partner; do not leave tools above you or walk on ceiling boards.

After: nothing switched on; ends taped; tools counted; the CEWP checks.

Emergency: stop at any smell of burning or shock; call the CEWP; 112 for injury.

Extension leads

  • Use a lead with a plug, a socket and a cable that suit the appliance's watts. Heavy appliances (kettle, iron, heater) plug into the wall, not into a long thin reel.
  • Unroll a cable reel fully; a coiled reel under load can overheat.
  • Do not run leads under mats or doors, or across wet floors.
  • Replace any lead with a damaged cable or plug.
  • Ghana uses 13 A type G plugs with GSA standards. A 13 A plug can carry about 2,990 W (13 × 230).

Lead check

A kettle (2,000 W), an iron (1,500 W) and a 1,000 W heater are all plugged into one four-way lead. (1) What is the total watts? (2) Total amps at 230 V? (3) What is the problem? (4) What would you advise?

Prepare two circuits on a dead training wall

  1. Read the instructor's plan: one lighting circuit with two-way switching and one socket circuit.
  2. Mark and fix the back boxes level.
  3. Fix conduit between boxes; file the ends.
  4. Draw unconnected cable through; leave 150 mm spare at each box (or as the CEWP says).
  5. Label every cable end with a tag: circuit, point and "live", "neutral", "earth" or "strapper" as the CEWP tells you.
  6. The CEWP inspects the work and signs your logbook.

Sketch the switching

Draw how two switches could control one lamp in a corridor of your home. Mark where the cable runs would go.

Check yourself

  1. In which conductor should a switch be?
  2. Why plug a kettle into the wall rather than a thin lead?
  3. What is the maximum watts a 13 A plug carries on 230 V?
06

Unit 5 · Inspect and test as an assistant

A job is not finished when the last socket is screwed on. It is finished when the installation has been inspected, tested and certified.

Competency standard

Learning outcome Performance criteria — the trainee…
5.1 Do a visual inspection checks parts, marks, fixings and neatness with a checklist
5.2 Explain the main tests names continuity, insulation, polarity, earth and RCD tests and what each shows
5.3 Record results writes readings and defects clearly beside the CEWP
5.4 Explain the certificate and periodic inspection says what the Installation Completion Certificate is for

Range. A small house; visual inspection with the CEWP; the CEWP does tests. Evidence. Checklist; recorded readings; oral questions.

Ask a qualified expert. Testing and certifying are done by an Energy Commission-certified electrician and an inspector. You do not test live circuits. Several tests need a dead circuit; others (such as RCD and earth loop tests) are done by the certified person with correct instruments. Ask the CEWP before touching any instrument.

The visual inspection checklist

  • Materials. Cables, accessories and breakers carry standard marks; nothing is cracked or burnt.
  • Fixings. Boxes are fixed level; conduit is saddled; cables are not hanging.
  • Terminations. Conductors are fully inside the terminals; no bare copper outside; no strands cut.
  • Colours and labels. Circuits are labelled in the consumer unit; every circuit is identified.
  • Earth. Every socket and metal fitting has its earth; main earth and bonding are in place.
  • Neatness. Cable runs are straight; no scorch; no paint on terminals.
  • Protection. Breakers match the circuits; RCD is present where the CEWP says it is needed.

The main tests (ideas)

Test What it shows Needs
Continuity of protective conductors The earth path is complete Circuit dead
Insulation resistance The insulation between conductors is good Circuit dead and isolated
Polarity Switches are in the live and sockets are wired correctly Circuit dead
Earth fault loop impedance Fault current will be large enough to trip the breaker Done by the CEWP
RCD test The RCD trips within its design time Done by the CEWP

The numbers that each test must reach are in the regulations. They were not found for this book, so none is given. The certified electrician compares each reading with the limit and decides whether the installation passes.

Labelled parts of an insulation resistance tester A hand-held tester with a display in megohms, a test-voltage selector, a TEST button and three terminals for the leads. >200 MΩ 250 500 1000 V TEST 1 2 3 4 5 6 7
Parts of an insulation resistance tester
No. Part What it does Safety rule
1 Display Shows megohms A reading means nothing if the leads are wrong
2 Test-voltage selector Chooses 250, 500 or 1,000 V Use 500 V for ordinary circuits as the CEWP decides
3 TEST button Applies the test voltage while held Never touch the leads while pressed
4 Line terminal (red lead) Positive lead to the conductor Dead circuit only
5 Earth terminal (black lead) Return lead Dead circuit only
6 Case Protects the instrument Keep dry
7 Voltage markings Show the test voltages Check before testing
Labelled parts of a clamp meter A clamp meter with jaws open at the top around a single conductor, a trigger lever on the side, a display and a function dial. 12.4 A 1 2 3 4 5 6
Parts of a clamp meter
No. Part What it does Safety rule
1 Jaws Open around one conductor and sense its current Never clamp a whole cable of two conductors
2 Conductor under test The single wire being measured Use the CEWP's method; keep fingers behind the guard
3 Jaw trigger Opens the jaws Close fully
4 Display Shows amps Check the range
5 Function dial Chooses current, voltage or resistance Set before clamping
6 Body and hand guard Holds the electronics and keeps fingers away Check for cracks

SAFETY PROTOCOL: insulation, continuity and earth tests (CEWP-led, dead circuits).

Before: circuit isolated, locked and proved dead; sensitive electronics unplugged; instrument and leads checked; PPE; a barrier at the far end of the circuit.

While: Do tell everyone before the test voltage is applied; do discharge the circuit after the insulation test as the CEWP directs. Do not touch the conductors during the test; do not test a live circuit; do not alter a reading.

After: disconnect leads; restore every disconnected device only with the CEWP; record results; store the instrument dry; report faults.

Emergency: for a shock call 112; switch off the supply; first aid as in Level 1; report any instrument that fails.

Pass limits (international values, labelled; Ghana limits by the Energy Commission)

The Ghana limits are in the regulations and the Energy Commission's inspection form; the text was not found free online. The international values below come from the British IET and are the same as IEC practice in general. Check against the Ghana text when it is read; the Energy Commission and the CEWP decide.

Test International value Note
Insulation resistance, circuits up to 500 V (not SELV or PELV) Test at 500 V DC; at least 1 MΩ BS 7671 Table 64
Insulation resistance, SELV and PELV Test at 250 V DC; at least 0.5 MΩ ; sources disagree on the voltage ceiling: check the standard
Earth fault loop impedance (Zs), TN systems Not more than the value for the breaker type and rating, in ohms; Appendix F gives a recalculated table 32 A type B limit 1.37 ohm
Earth electrode, TT systems Resistance × RCD trip current ≤ 50 V See Appendix E
RCD (30 mA) Trips within 40 ms at five times its rating; also within the general limit at its rating (300 ms commonly; not verified) See Appendix F
Protective conductor continuity Low and similar for like circuits; recalculate R1 + R2 from size and length See Appendix F

A reading outside the limit means the installation fails the test: the CEWP finds and repairs the cause and tests again. You never "adjust" a reading.

The test sequence is: dead tests first (continuity of protective conductors, ring final continuity where the UK pattern is used, insulation resistance, polarity), then the live tests (earth fault loop impedance, RCD, earth electrode) by the certified person only. Appendix F has the sequence as a quick card and a blank schedule of test results.

What has changed: the ICC app. The Energy Commission launched a mobile app (ICCAPP): the electrician enters the wiring details, an inspector approves, and a digital token is the certificate. It was piloted from November 2024; about 21,000 practitioners adopted it; paper certificates were reported no longer accepted for grid connection after June 2025. The lines in this unit that mention stamped forms describe the older route. Ask the Energy Commission which route is in force today. Rules reported to be mandatory (RCDs and earth inspection chambers) were not confirmed in a source I could read: check with the CEWP.

The certificate and the inspector

  • You need an Installation Completion Certificate (ICC) to be connected to the grid or to obtain a personal meter.
  • ECG cannot process a meter application without the stamped forms from the certified electrician and the inspector.
  • The Energy Commission is building a system linking certification with the utilities; a pilot ran in 10 ECG districts, and consumers get a text message confirming certification.
  • Old installations must be inspected too: the first inspection comes 10 years after the installation is first used, then every 3 to 5 years until it has been in service for 30 years, then every 2 years. The utility completes and signs the Electrical Installation Certificate and the schedule of test results.

What the helper does

Hold the end of the test lead only when the CEWP says; read the instrument aloud if asked; write the readings in the schedule; label every circuit; collect all tools; clear the site. Do not turn the supply on. Do not remove a lock the CEWP fitted.

Periodic inspection dates

A house is first used on 1 March 2018. (1) When is the first periodic inspection due? (2) If the next ones come every 5 years, when is the second? (3) After how many years in service does the interval drop to every 2 years? (Use the rule stated above.)

Visual inspection of a finished dead training board

  1. With the board dead and locked, take the checklist.
  2. Inspect every item. Tick it or write the defect.
  3. Photograph two defects (with permission).
  4. Fill in the CEWP's schedule layout as a practice form with the readings the instructor gives you.
  5. Explain to the instructor why each test is done.
  6. Return the board to its locked state.

A certificate story

Ask a certified electrician or a landlord what happened when they connected a house: what forms were needed, who inspected, how long it took. Write it up.

Check yourself

  1. Name two tests done on a dead circuit.
  2. What is the ICC for?
  3. When is the first periodic inspection due?
07

Unit 6 · Appliances, air conditioners, surges and backup power

Appliances are where wiring meets daily life. Most calls to an electrician start with an appliance that trips something.

Competency standard

Learning outcome Performance criteria — the trainee…
6.1 Match appliance to circuit says which appliances need their own circuit
6.2 Advise on energy use explains the yellow label and simple ways to cut use
6.3 Explain surge protection says what a surge is and why it matters
6.4 Explain safe backup power says why a generator needs a changeover switch fitted by a CEWP

Range. House appliances; basic ideas; refer repairs. Evidence. Oral questions; written advice sheet.

Ask a qualified expert. Connecting air conditioners, water heaters, cookers, surge devices and generators or inverters to the house wiring is the work of an Energy Commission-certified electrician. Refrigerant work belongs to a trained refrigeration technician (see the hub's Refrigeration and Air Conditioning Basics course). Generator and appliance repair has its own hub course.

Which appliances need their own circuit

Large loads: air conditioners, water heaters, cookers, washing machines and pumps. They draw a lot of current for a long time. The CEWP gives each its own circuit and breaker, as in the load list in Unit 2.

Energy and the yellow label

The Energy Commission advises buyers to check for its yellow energy label, and says air conditioners and refrigerators without it tend to use a lot of electricity. Simple savings: switch off lights and fans when you leave; use LED lamps; service air conditioner filters; keep fridge doors shut.

Energy sum

Example tariff GH¢2 per kWh. (1) An old 100 W bulb for 6 hours a day for 30 days: kWh and cost? (2) A 10 W LED for the same time: kWh and cost? (3) What is the monthly saving?

From the field: the fridge and the low voltage

The moment. In many houses the fridge is left on to keep food.

The problem. When the supply drops, the fridge keeps trying to start and in the end it is damaged.

The cause. Low supply voltage strains the fridge motor.

What was done. Many people now use a power stabiliser.

The lesson. A cheap protector costs less than a new fridge.

Next time. 1. Fit a stabiliser or a fridge guard. 2. Ask a qualified electrician which one suits the appliance. 3. [[FLAG: author to confirm: the type most used]]

Told by De-Graft Afful, from his own site experience.

Technical note (international, labelled). The harm comes from low voltage, not low current: a compressor motor draws more current and runs hot when voltage is low, and a compressor that restarts straight after a cut can be damaged, so it needs a delay of a few minutes. A voltage stabiliser steadies a drifting supply and often adds the delay; a fridge guard (time-delay protector) mainly cuts off outside a safe range and restores after a delay, and does not correct a weak supply. A fridge needs low-voltage cut-off and a time delay. Vendor pages are not independent tests: follow the fridge maker's advice. Ask a qualified expert: an Energy Commission-certified electrician for the installation; a trained refrigeration technician for the fridge.

Ghana field problems and what an installer can do (to be checked with ECG)

Problem What it does What an installer can and cannot do
Low or unstable supply voltage Damages fridges, air conditioners and TVs. A Ghana survey was reported to find that 26% of households had at least one appliance burned in a year (not verified by me). Low evening voltage was reported in one study (not verified). ECG has said low voltage in some towns is a grid problem. Cannot fix the grid. Can: right-sized cable (to limit extra drop), protect sensitive loads with a stabiliser or guard, tell the owner to report to ECG
Rain and humidity Moisture gets into outdoor fittings and boxes and trips RCDs Use outdoor-rated (IP) fittings, glands and sealed boxes; CEWP checks
Termites and rodents Eat insulation and conduit Use sealed conduit, close gaps, keep stores tidy; CEWP replaces damaged cable
Zinc roofs and block walls Metal roofing can become live if touched by faulty cable; chasing blockwork is dusty and can hit old cable Earth and bond roof metal if the CEWP says so; check the walls dead first
Dry laterite soil Earth rods read high in dry ground Longer or deeper rods, more rods in parallel, moist pit, tested by the CEWP
Generator and solar back-feed Current going back into the grid kills linesmen Changeover switch only, fitted by the CEWP
Illegal connections and tampering Overload and fire Report to ECG; never help with them

(Source for the voltage figures: Kleinman Center and Energy for Growth Hub items seen in search results only; no URL read, so these are not verified. Appliance protection advice is general; the CEWP advises.)

Tools and items for this unit

Item What it is and what it does When you use it Size or type Also called Helper status
Voltage stabiliser A device that holds the voltage steady when the supply drifts For a fridge, TV or other sensitive load Rated in VA; choose above the load; low-voltage cut-off and time delay for fridges AVR, voltage regulator, stabilizer CEWP advises
Fridge guard (time-delay protector) A plug-in cut-out with a delay Fridges and freezers 13 A (typical) refrigerator protector, time-delay protector You may fit it
Surge protective device (SPD) A device that diverts brief voltage spikes to earth At the board or at the socket Types 1, 2, 3 by location (IEC 61643; international) SPD, surge arrester, surge protector CEWP only
Changeover (transfer) switch A switch that feeds the house from the grid or a generator, never both Generators and inverters Rated above the load; manual or automatic transfer switch, ATS (automatic), manual changeover CEWP only
Water heater isolator A double-pole switch that isolates the heater Next to the heater 20 A or 32 A (typical) heater switch, double-pole switch CEWP only
Air conditioner isolator A switch beside the outdoor unit Servicing Matches the AC circuit AC isolator, AC switch CEWP only
Extension lead and multi-plug Short-term plug extensions Light loads only Rated in amps extension cord, trailing socket, extension board You may use within rating

Surges

A surge is a short, sudden rise in voltage that can damage electronics. Sensitive equipment can be protected with surge devices fitted by a CEWP, and by unplugging during storms. Which device to use, and where, is for the CEWP to decide; Ghana rules on surge devices were not found.

Backup power

Labelled parts of a generator changeover switch arrangement A changeover switch sits between the grid supply, a generator and the house board. The handle connects the house to either the grid or the generator, never both. GENERATOR HOUSE BOARD GRID (ECG) GRID | GEN never both together 1 2 3 4 5 6
Parts of a generator changeover arrangement
No. Part What it does Safety rule
1 Generator Makes the backup power Outdoors only, far from doors and windows
2 Changeover handle Selects grid or generator, never both CEWP fits it; never bypass it
3 House board Distributes the power to circuits Only through the changeover switch
4 Grid supply The electricity company's supply Never connect a generator to it directly
5 Position label Shows GRID or GEN Keep readable
6 Generator cable Brings the generator output to the switch Use proper cable and plug; never a plug into a wall socket

SAFETY PROTOCOL: running a generator with a changeover switch (hazardous task).

Before: the changeover switch was fitted by the CEWP; the generator is outdoors on level ground away from openings; fuel is stored safely and the engine is cool; the CEWP checks the earth arrangement; switch the house loads off.

While: Do start the generator first, let it settle, then switch the changeover to GEN, then switch loads on. Do not fill fuel while it runs; do not plug it into a socket; do not use it indoors, in a garage or near windows (carbon monoxide).

After: switch loads off, change back to GRID, stop the generator, let it cool, then store the fuel; report faults.

Emergency: for fumes or collapse move to fresh air and call 112; for fire use the correct extinguisher if trained, otherwise leave and call 112; isolate the supply at the main switch if safe.

  • A generator or inverter must feed a house only through a changeover (transfer) switch fitted by a certified electrician. Plugging a generator into a wall socket can send current back into the supply and kill linesmen and neighbours. This is general good practice taught in generator safety guides.
  • Run a generator outdoors, far from doors and windows, because carbon monoxide can build up.
  • For solar and battery systems, see the hub's Solar Energy course; solar installers need an Energy Commission licence and a CEWP certificate.

Is back-feeding covered by OSHA 4105? The leaflet was seen only in summary. The point about changeover switches is standard good practice; ask a CEWP and the electricity company about Ghana's rule.

Appliance advice sheet

  1. Choose five appliances at the centre or at home; read each label.
  2. For each, write watts, amps and whether it needs its own circuit.
  3. Write one energy-saving tip for each.
  4. Write two lines on why a generator needs a changeover switch.
  5. Present your advice sheet to a classmate and then to the instructor.

Energy audit

Ask a family to list their five most-used appliances and hours per day. Calculate the monthly kWh and cost with the example tariff. Suggest one saving.

Check yourself

  1. Name two appliances that need their own circuit.
  2. Why does a generator need a changeover switch?
  3. What does the yellow label tell you?
08

Unit 7 · Find paid work and grow

Skilled helpers are in demand. A good name travels faster than any advertisement.

Competency standard

Learning outcome Performance criteria — the trainee…
7.1 Follow the route to certification writes a dated plan with the Energy Commission steps
7.2 Choose a work location lists three locations or sectors and why
7.3 Choose a small business idea within the law names two ideas that do not require wiring
7.4 Market yourself builds a profile, portfolio and referral plan

Range. Helper and apprentice level. Evidence. Plan; profile; money exercise.

Ask a qualified expert. This is general information, not legal advice. Ask a qualified lawyer, the Energy Commission or the District Assembly before you act on any licence or registration matter. For tax, check with GRA or a qualified accountant. For loans or insurance, ask your bank or a licensed financial adviser. All wiring is for a certified electrician.

The route in numbers

The Energy Commission says over 18,600 electricians and inspectors have been certified since L.I. 2008 took effect, and over 600 apprentices registered from March 2026. Pass rates vary: May 2025 had 964 of 1,163 pass (about 81%) with an Inspector pass rate of 44.9%. Certification fees were not found: ask the Commission.

Tools and items for this unit

Item What it is and what it does When you use it Size or type Also called Helper status
Quotation form A page that lists points and prices for the client Before a job A4 quote sheet, estimate You may fill
Materials take-off form A page that lists quantities from the plan Before buying Appendix J material list, take-off sheet You may fill
Digital multimeter, borrowed An instrument you learn to read Practice only with the CEWP CAT-rated DMM, avometer Watch and read

Locations that give good returns

  • New estates and building plots where several houses are wired at once.
  • Hardware and electrical shops that refer electricians.
  • Hotels, schools, clinics and farms that need maintenance helpers and energy advice.
  • The Hub's own farm and training centre buildings, for supervised practice.

Business ideas within the law

Idea Notes
Certified electrician's team member Stay with one electrician; build trust
Materials buying and delivery Check marks and prices; keep receipts
Site preparation crew Chasing, conduit and boxes under supervision
Energy audit and advice Count appliances, suggest savings, no wiring
Retail of approved accessories Importers need Energy Commission conformance certificates; sellers must not sell non-compliant goods. Ask about any retailer registration; not verified
Maintenance records for a small business Keep logs, remind owners of inspection dates

Market yourself

  • WhatsApp Business. Profile photo, "Electrician's apprentice, working under a certified electrician". Catalogue of what you do (helping, preparation, energy advice).
  • Google Business Profile. Your name, area and services; ask satisfied customers for a review.
  • Signage. A simple board or sticker on your motorbike or toolbox with your name and area; never claim "certified" until you are.
  • Portfolio. Photographs of neat preparation work, with permission.
  • Referrals. Ask your electrician and hardware shop to give your name.

Money maths

Helper income and savings

Example figures. A helper works 22 days in a month at GH¢90 a day (example). Transport and food cost GH¢30 a day. (1) What is the income? (2) Costs? (3) What is left? (4) If you save 30% of what is left towards your Energy Commission exam, how much per month? (5) How many months to save GH¢1,200 (example exam and training cost)?

Accessibility

Ghana's Disability Act requires accessible public places and bans job discrimination. The Assemblies' disability fund rose to 5% in 2026, aimed at skills, devices and capital. Many tasks in this trade are workable from a seat or at ground level: drawings, load lists, estimating, materials control, records and customer advice. Ladder and roof work is not suitable for everyone. Helpful adjustments include clear task cards, seated benches, good light and a work buddy.

Your two-year plan

  1. Write the steps to certification: finish training, find a CEWP who will register you, practise, and ask the Energy Commission about the exam.
  2. Add dates and costs; mark what is example and what is verified.
  3. Write a WhatsApp profile and three photos you could use (with permission).
  4. Choose one business idea from the table and list what you need.
  5. Present your plan to a panel of two classmates.

Interview an electrical shop

Ask a hardware shop which cables and accessories they sell, how they check the standard marks, and which electricians they recommend. Write it up (do not buy).

Check yourself

  1. Name two business ideas that do not involve wiring.
  2. What must you never claim until you have it?
  3. Who registers apprentices?
09

Glossary

Items, instruments and protective devices are in Appendix N. This glossary holds the ideas and the law words.

Term Meaning
Bonding Joining metal parts so they stay at the same electrical level
Breaking capacity The biggest fault current a breaker can switch off safely, for example 6 kA
CEWP Certified Electrical Wiring Professional
CEWI Certified Electrical Wiring Inspector
Changeover switch A switch that feeds the house from the grid or a generator but never both
Continuity test A test that shows a conductor is unbroken
Current-carrying capacity (Iz) The current a cable can carry for long periods in its real installation without overheating
Derating factor A multiplier below 1 that reduces a cable's rating for heat, grouping or insulation
Design current (Ib) The current the circuit is intended to carry
Diversity An allowance for the fact that not all loads run at once; the CEWP applies it under the rules
Earth electrode A rod, plate or mesh in the ground
Earth fault loop impedance (Zs) The resistance of the whole path fault current takes; low enough to trip the breaker quickly
EICR Electrical installation condition report (a periodic inspection report, UK term, foreign)
ICC Installation Completion Certificate
IP rating A code such as IP44 for protection against solids and water
Insulation resistance How well insulation keeps conductors apart, in megohms
Load list A list of appliances with watts and amps
MCB Miniature circuit breaker
Nominal current (In) The rating of the breaker, for example 16 A
PME, TN and TT International codes for how the supply and house earth are arranged; Ghana's to be checked
Polarity Whether live and neutral are on the right terminals
Power factor The ratio of real power to the volt-amps the appliance draws
Protective conductor The earth wire in a cable
Prove, test, prove The test method that checks the tester before and after
RCBO A breaker and an RCD in one device
RCD Residual current device; switches off when current leaks
SELV Safety extra-low voltage, a very low-voltage system separated from the mains
SPD Surge protective device
Surge A short, sudden rise in voltage
Thermal insulation factor (Ci) The factor that cuts a cable's rating when it is covered by insulation
Voltage drop The volts lost along a cable because of its resistance
10

Logbook

Copy these pages into an exercise book. Your logbook is part of your assessment evidence.

  • Unit 1: isolation drills; flow chart
  • Unit 2: load lists; circuit sketches; materials lists
  • Unit 3: earth path drawing; earth hunt
  • Unit 4: prepared circuits; labelled cable ends; lead check
  • Unit 5: inspection checklists; practice schedule; certificate story
  • Unit 6: appliance advice sheet; energy audit
  • Unit 7: two-year plan; profile; interview notes
  • Appendices A to N: used for at least one sizing, one test record and one fault chart
  • Every homework, dated
11

Self-check quiz

  1. Put the steps of safe isolation in order.
  2. Why must the tester be proved before and after?
  3. A 3,000 W water heater on 230 V draws about how many amps?
  4. Why is a thin cable on a large breaker dangerous?
  5. What does the earth path do when a fault occurs?
  6. What does an RCD sense?
  7. In which conductor should a switch be fitted?
  8. What is the most a 13 A plug can carry on 230 V, in watts?
  9. Name two tests done on a dead circuit.
  10. When is the first periodic inspection due?
  11. Why must a generator feed a house through a changeover switch?
  12. Who registers apprentices with the Energy Commission?
12

Appendix A · Cable and breaker pairing tables

The cable is chosen for the current it must carry in the place where it runs. The breaker is chosen to protect that cable. These tables are international, labelled, and must be checked against GS 1009 by the CEWP.

Ask a qualified expert. The cable and breaker for a real circuit are chosen by an Energy Commission-certified electrician under L.I. 2008 and GS 1009. The tables below are international values, not Ghana law, and not verified against the standard text in this book's research: check them against the Ghana Standards Authority and Energy Commission text when it is read. Never size a real circuit from this page.

The rule that links everything

Design current Ib is not more than breaker rating In, and In is not more than the cable's current-carrying capacity Iz in its real installation. Iz = It × Ca × Cg × Ci × Cc, where It is the tabulated rating and the factors are in Appendix C.

Tabulated current-carrying capacity It, single-phase, two loaded copper conductors, PVC insulation, 30 °C ambient

International extract in the style of IEC 60364-5-52 as widely reproduced. Not verified against the standard text. The IET article shows that the British table for flat twin-and-earth cable gives slightly different values from the IEC single-core table (for example, 32 A for 6 mm² in an insulated wall, Method A, where IEC single-core shows 34 A). Use the value for the exact cable type from the standard.

Cable size (mm²) Method A: in conduit in an insulated wall Method B1: in conduit on a wall Method C: clipped direct to a wall Typical use and typical breaker (example)
1.5 14.5 A 17.5 A 19.5 A Lights; 6 A or 10 A
2.5 19.5 A 24 A 27 A Sockets, one air conditioner, water heater; 16 A or 20 A
4 26 A 32 A 36 A A large air conditioner, a small cooker; 25 A or 32 A
6 34 A 41 A 46 A Cooker, shower; 32 A or 40 A
10 46 A 57 A 63 A A large shower or a sub-main; 40 A or 50 A
16 61 A 76 A 85 A A sub-main; 63 A

Standard breaker sizes (international preferred values, IEC 60898 style)

6, 10, 16, 20, 25, 32, 40, 50, 63 A. RCD residual ratings: 10, 30, 100, 300 mA. Standard conductor sizes (IEC 60228): 1.5, 2.5, 4, 6, 10, 16, 25 mm² and larger. (International practice, not verified in a source read for this book.)

Worked pairing: a 6 kW shower (from the IET article, recalculated)

Ib = 6,000 ÷ 230 = 26.1 A. Choose In = 32 A. Cable: Iz must be at least 32 A. In an insulated wall (Method A), 6 mm² has 32 A or 34 A, so 6 mm² is enough, while 4 mm² (26 A) is not. Then check voltage drop (Appendix B).


13

Appendix B · Voltage drop method and three worked examples

A cable has resistance. The longer and thinner it is, the more volts it eats before the load.

Ask a qualified expert. Voltage drop limits and cable choices for a real job are the CEWP's. The limits below are international (IEC 60364-5-52 Table G.52.1 as described in the Electrical Installation Guide, summary only); check against GS 1009.

The limits (international)

For an installation supplied directly from a public low-voltage network: 3% for lighting and 5% for other uses. These apply to normal running, not to motor starting.

The method

Voltage drop in volts = mV per amp per metre × current in amps × length in metres ÷ 1,000. Percentage = volts lost ÷ 230 × 100.

mV/A/m values recalculated for a two-wire single-phase run from copper resistivity at working temperature (0.0225 ohm mm²/m, a textbook value): 2 × 0.0225 ÷ size × 1,000. Published tables for larger sizes are slightly lower, so these are conservative.

Size (mm²) 1.5 2.5 4 6 10 16
mV/A/m (recalculated) 30.0 18.0 11.2 7.5 4.5 2.8

Worked examples (example circuits, script-checked)

# Circuit Working Result Within limit?
1 Lights: 1.5 mm², 25 m run, 5 A 30 × 5 × 25 ÷ 1,000 = 3.75 V; ÷ 230 3.75 V = 1.63% Yes (3%)
2 Air conditioner: 2.5 mm², 25 m, 7.83 A 18 × 7.83 × 25 ÷ 1,000 3.52 V = 1.53% Yes (5%)
3 Shower: 6 mm², 28 m, 26.1 A 7.5 × 26.1 × 28 ÷ 1,000 5.48 V = 2.38% Yes (5%)

If a result is over the limit, use the next size up (a bigger cable has less resistance) and calculate again.


14

Appendix C · Derating and grouping factors

A cable in a hot roof, or bundled with others, cannot shed its heat. The tables must be reduced.

Ask a qualified expert. Derating factors for a real job are chosen by the CEWP from the standard. The values below are international, from memory of the British tables, not verified in this book's research: check against the standard text.

Factor Meaning Typical values (PVC, copper; international, not verified)
Ca: ambient temperature Surrounding air hotter than 30 °C 25 °C: 1.03; 30 °C: 1.00; 35 °C: 0.94; 40 °C: 0.87; 45 °C: 0.79; 50 °C: 0.71
Cg: grouping Several circuits together in one conduit, trunking or clip run 1 circuit: 1.00; 2: 0.80; 3: 0.70; 4: 0.65; 5: 0.60; 6: 0.57
Ci: thermal insulation Cable touching or covered by thermal insulation Use the tables for the specific method; fully surrounded is much worse (not verified)
Cc: protective device A rewirable fuse needs 0.725; MCBs use 1

Worked example (recalculated)

A 16 A breaker, cables in a hot roof space at 40 °C (Ca 0.87), three circuits grouped (Cg 0.70). Required tabulated rating It ≥ 16 ÷ (0.87 × 0.70) = 26.3 A. With Appendix A (Method C), 2.5 mm² gives 27 A, which only just works; 4 mm² (36 A) gives a safe margin. The lesson: heat and bundling push you up a size.


15

Appendix D · Circuit schedules for 1, 2 and 3 bedroom houses

A circuit schedule lists every circuit, what it feeds, its load and its proposed cable and breaker. These are examples for the CEWP to correct.

Ask a qualified expert. Every number below is an example. The CEWP designs the real schedule under L.I. 2008 and GS 1009, applies diversity, and decides the supply size with the electricity company.

Loads are example label watts; Ib = watts ÷ 230. Cable and breaker are example pairs from Appendix A; all sockets and lights are on 30 mA RCD protection as the CEWP decides.

One bedroom

Circuit Feeds Load (W) Ib (A) Cable / breaker (example)
C1 Lights: 8 LED lamps at 10 W 80 0.35 1.5 mm² / 6 A
C2 Sockets: kettle 2,000, iron 1,500, TV 100, fridge 150 3,750 16.3 2.5 mm² / 20 A
C3 One air conditioner 1,100 4.78 2.5 mm² / 16 A
C4 Water heater 3,000 13.0 2.5 mm² / 16 A

Two bedrooms

Circuit Feeds Load (W) Ib (A) Cable / breaker (example)
C1 Lights, 16 lamps at 10 W 160 0.70 1.5 mm² / 6 A
C2, C3 Sockets, two circuits about 4,000 each up to 17.4 2.5 mm² / 20 A each
C4, C5 One air conditioner each, 1,800 W 1,800 7.83 2.5 mm² / 16 A each
C6 Water heater 3,000 13.0 2.5 mm² / 16 A
C7 Cooker 6,000 26.1 6 mm² / 32 A

Three bedrooms

Circuit Feeds Load (W) Ib (A) Cable / breaker (example)
C1, C2 Lights, two circuits (24 lamps) 240 1.04 1.5 mm² / 6 A each
C3, C4, C5 Sockets, three circuits about 4,000 each up to 17.4 2.5 mm² / 20 A each
C6, C7, C8 One air conditioner each, 1,800 W 1,800 7.83 2.5 mm² / 16 A each
C9 Water heater 3,000 13.0 2.5 mm² / 16 A
C10 Cooker 6,000 26.1 6 mm² / 32 A
C11 Shower 7,500 32.6 10 mm² / 40 A or 50 A (the CEWP decides)

If every load ran at once the three-bedroom house would draw about 114 A (26,190 W ÷ 230). That never happens; the CEWP applies diversity, and Ghana's diversity rule was not found: not verified.


16

Appendix E · Earthing, bonding and RCD one-pager

Earth, bond and cut off fast.

Ask a qualified expert. Earthing and RCD design and testing are the CEWP's. This page is international ideas and not Ghana law: check against the Energy Commission, ECG and GS 1009.

Topic Rule (international, labelled)
What earthing does Gives fault current a low-resistance path so the breaker or RCD trips and metal parts do not stay live
Earthing system TN (earth return through the supply) or TT (earth return through the ground). Ghana's domestic system: to be checked.
TT touch-voltage rule Electrode resistance (ohms) × RCD trip current (amps) is not more than 50 V
Examples With 30 mA: at most 1,667 ohms on paper; with 100 mA: 500 ohms; with 300 mA: 167 ohms. Good practice aims much lower because soil dries
Main bonding Join incoming metal water and gas pipes and structural metal to the main earthing terminal
Earth inspection chamber A covered pit over the rod head so the CEWP can test; reported to be mandatory in Ghana, not verified
Electrodes Rod, plate or mesh; copper-bonded or galvanised steel; deeper and wetter is better

Resistance of one vertical rod (textbook formula, recalculated)

R = ρ ÷ (2πL) × (ln(4L ÷ r) − 1), where ρ is soil resistivity in ohm metres, L the rod length and r its radius. For a rod 2.4 m long and 16 mm across:

Soil Resistivity (example) Rod resistance
Wet clay 30 ohm metres 12.1 ohms
Typical soil 100 ohm metres 40.4 ohms
Dry laterite or sand 1,000 ohm metres 403.9 ohms

Two identical rods set well apart in parallel give about half (20.2 ohms for the middle row), in the ideal case. Real values are always measured with an earth tester.

Reading an earth test

Drive the test spikes in a straight line away from the rod at the spacing the instrument says. Read the resistance. If it is above what the CEWP needs, add a rod, drive deeper, or improve the soil with moisture; then test again. Do not guess.


17

Appendix F · Inspection and testing pack

The tests, in order, with the limits and a blank record.

Ask a qualified expert. Testing and certifying are done by an Energy Commission-certified electrician and inspector. You never test live circuits. The limits are international values; the Ghana limits are in the regulations and the Energy Commission's form.

The sequence

  1. Visual inspection (checklist, Unit 5). 2. Dead tests: continuity of protective conductors; ring final circuit continuity where used; insulation resistance; polarity. 3. Live tests (by the certified person): earth fault loop impedance; earth electrode resistance; RCD trip time. 4. Record, certify, label. All dead tests come before any live test.

Limits (international, labelled)

Test Limit Source
Insulation resistance, up to 500 V circuits Test at 500 V DC; at least 1 MΩ
SELV and PELV Test at 250 V DC; at least 0.5 MΩ
RCD, 30 mA Trips within 40 ms at five times its rated current
Earth electrode (TT) Resistance × RCD trip current ≤ 50 V International rule
32 A type B breaker, maximum Zs 1.37 ohm
On-site Zs (hot-conductor allowance) Measured Zs is compared with 0.8 of the tabulated value

Maximum earth fault loop impedance, recalculated (TN, 0.4 to 5 s style; check the table)

Zs maximum = 0.95 × 230 ÷ (k × In), with k = 5 for type B, 10 for type C, 20 for type D. The 32 A type B result of 1.37 ohm matches the IET figure. Other rows are recalculated by script, not copied.

In (A) Type B max Zs (ohm) Type C max Zs (ohm)
6 7.28 3.64
10 4.37 2.19
16 2.73 1.37
20 2.19 1.09
25 1.75 0.87
32 1.37 0.68

Continuity example (recalculated)

Copper resistance at 20 °C, 1.5 mm²: 12.1 milliohm per metre; 2.5 mm²: 7.41 milliohm per metre (international table values, not verified here). A 20 m run of 2.5 mm² live with a 1.5 mm² earth wire: R1 + R2 = (12.1 + 7.41) × 20 ÷ 1,000 = 0.39 ohm. A measured value close to this shows the earth path is sound.

Blank schedule of test results (copy and use)

Circuit Description Breaker type and rating Cable size (mm²) R1+R2 (ohm) Insulation (MΩ) live-neutral Insulation (MΩ) live-earth Polarity OK Zs (ohm) RCD time (ms) Result

ICC data sheet to prepare (typical fields; the official form and the ICCAPP fields were not found)

Owner's name; address and GPS or plot number; category (domestic, commercial, industrial); electrician's name and certificate number; inspector; date; supply type and meter number; consumer unit make and number of ways; circuit list; test results; earthing arrangement; RCD present; remarks. Ask the Energy Commission for the real form.


18

Appendix G · Special locations

Wet and special places need extra care. These sheets give the international rule and leave the Ghana rule to the CEWP.

Ask a qualified expert. Wiring in bathrooms, outdoors, kitchens, pools and with pumps and generators is for an Energy Commission-certified electrician. International rules here are not Ghana law: check against GS 1009.

Location or item International rule (labelled) Helper note
Bathroom and shower IEC 60364-7-701 defines zones 0 (inside the bath or shower tray), 1 (above it) and 2 (beside it); the old zone 3 was dropped in the 2019 edition. Equipment in zone 0 needs IPX7; zones 1 and 2 need IPX4, but sources disagree on the figures. 30 mA RCD protection for the circuits serving the location. A UK rule allows a socket only 3 m horizontally from zone 1: UK national rule, not verified No sockets or switches in the wrong zone; use a pull-cord; keep water away from the CEWP's work
Outdoor and garden Use IP-rated fittings, glands and sealed boxes; protect with a 30 mA RCD; use armoured or sheathed cable; keep clear of digging Never use indoor fittings outside
Kitchen Separate circuits for the cooker and big appliances; sockets away from sinks; a 30 mA RCD Report overloaded leads
Air conditioner Its own circuit and isolator beside the unit; refrigerant work belongs to the refrigeration technician You do not touch refrigerant
Water heater Its own circuit, a double-pole isolator, earth bonding of pipes as the CEWP decides Never work on a heater with water in it live
Borehole pump Starter, overload protection and RCD; cable sized for the long run and the pump's starting current; earth with the well casing as the CEWP decides See the hub's Boreholes and Water Pumps course
Gates and CCTV Low-voltage supplies from a safe isolating transformer; fused at the mains Keep low-voltage cables apart from mains
Standby generator Changeover switch only; the earth arrangement as the CEWP decides Never plug a generator into a wall socket
Rooftop solar Referred to the hub's Solar Energy course; licensed installers and a CEWP Not covered here
Electric vehicle charge point New; needs a dedicated circuit, an RCD of suitable type and a CEWP; not covered here Not covered here
Swimming pools and farms Special rules for wet and animal areas; 30 mA RCDs; IP-rated fittings and equipotential bonding Ask the CEWP
Temporary building-site supply Protect with RCDs; use IP-rated sockets and tough cable; keep above water and clear of vehicles Report damaged leads

19

Appendix H · Protective devices guide

Which device protects against which fault.

Ask a qualified expert. The CEWP chooses and fits protective devices. The international ratings and types below are not Ghana law; check against GS 1009 and whether the GSA has adopted the IEC standards.

Device What it protects against Notes
MCB (IEC 60898 style) Overload and short circuit Curve B trips at 3 to 5 times its rating, C at 5 to 10 times, D at 10 to 20 times (international, not verified here). Use B for lights and sockets, C for motors and air conditioners with starting surges as the CEWP decides. Breaking capacity such as 6 kA must exceed the fault current
RCD (IEC 61008 style) Leakage to earth, shock 30 mA for people. Type AC detects smooth AC leakage; Type A also detects pulsating DC leakage from electronics (international). Does not protect against overload
RCBO (IEC 61009 style) Overload, short circuit and leakage for one circuit A breaker and an RCD in one body; good for stopping one fault from tripping many circuits
SPD (IEC 61643 style) Surges Types 1, 2 and 3 by location; need a good earth and the right fuse or breaker upstream
Isolator None (it only disconnects) Used to switch off for work
Fuse in a plug Overload of the flexible lead 3 A or 13 A by appliance

20

Appendix I · Instrument guide

The right instrument for the right question, and what it cannot tell you.

Ask a qualified expert. Instruments are used by the certified person under safe-isolation rules. A wrong instrument or a wrong lead can kill. Buy and use only approved instruments.

Instrument What it proves What it does not prove Buying and care
Two-pole voltage tester with proving unit Dead or live, when prove-test-prove is followed Insulation quality Choose one marked to IEC 61243-3; short probe tips (HSE GS 38, UK, foreign, not verified here)
Non-contact detector Voltage is near It cannot prove dead A warning tool only
Multimeter Voltage, resistance, continuity It is not for proving dead Choose the right CAT rating for the place of use (CAT II for sockets, CAT III for distribution boards, CAT IV at the origin; IEC 61010 idea, international)
Clamp meter Load current and leakage current by clamping one conductor Does not give voltage Clamp one conductor, never the whole cable
Insulation tester Insulation resistance on a dead circuit Not safe on live circuits Test voltage 500 V or 250 V; disconnect sensitive equipment first
Continuity tester Low-resistance paths of earth and bonding Insulation Zero the leads before use
Earth electrode tester Resistance of the earth rod Wiring faults Spikes in line, away from other electrodes
Loop impedance tester The path fault current takes (live test) Insulation CEWP only
RCD tester Trip time and current Other faults Follow the instrument's guide
Socket tester Quick wiring check Not a substitute for tests Cheap; for fault spotting only
Cable locator and stud detector Hidden cable and metal That a cable is dead Always confirm dead

Do not use: a neon screwdriver as a tester; a test lamp; a multimeter to prove dead; leads with damaged insulation. Calibration: instruments are checked at the maker's interval; keep a calibration log (Level 3). What to buy first on a budget: a two-pole tester with a proving unit, then a multimeter, then a clamp meter.


21

Appendix J · Materials take-off sheet and conduit fill

Count first, then buy. A take-off list prevents a second trip to the shop.

Ask a qualified expert. Quantities and sizes are confirmed by the CEWP; do not buy from this page alone.

Blank take-off form

Item Size or type Quantity Unit Notes
Cable m
Conduit length
Back boxes each
Junction boxes each
Switches each
Sockets each
Lamp holders each
Breakers each
Consumer unit each
Saddles and clips each
Earth rod and clamp set

Conduit fill (international rule of thumb, recalculated example)

A common design limit is that cables fill not more than 40% of the conduit's inside cross-section, to allow pulling and heat. Fill = total cable area ÷ conduit inside area. Number of equal cables = 0.4 × (inside diameter ÷ cable diameter)².

Example (not real products): conduit inside diameter 16.9 mm, cable overall diameter 3.5 mm. Number = 0.4 × (16.9 ÷ 3.5)² = 9.3, so at most 9 cables on paper. Real jobs allow fewer because of bends. Use the cable's real overall diameter from the packaging, and the conduit's real inside diameter.


22

Appendix K · Standards crosswalk and "which book next"

What each standard is for, and the next book to buy.

Ask a qualified expert. Whether an IEC standard has been adopted as a Ghana Standard must be checked at the GSA catalogue, and legal wording by a lawyer.

Standard What it covers Where it sits
Act 541 and L.I. 2008 Energy Commission and Ghana's wiring regulations Ghana law
L.I. 2478 Cables and accessories Ghana law
GS 1009 Ghana wiring code Ghana standard; contents not read
GS IEC 60227 PVC cable example Ghana standard, per GSA
GS IEC 60884 Plugs and sockets, 13 A Type G Ghana standard, per GSA notice
IEC 60364 series International wiring rules (part 5-52 cable ratings; part 7-701 bathrooms) International; basis of BS 7671
BS 7671 and IET guidance British Standard wiring regulations; follows IEC 60364 with national differences Foreign; used as the best-documented international version
IEC 60898, 61008, 61009 MCBs, RCDs, RCBOs International; adoption by GSA to be checked
IEC 61243-3 Two-pole voltage detectors International
IEC 60529 IP codes International

Which book to buy next: the current edition of BS 7671 (the IET Wiring Regulations), the IET On-Site Guide, and IET Guidance Note 3 on inspection and testing. Ask the GSA for the Ghana texts (GS 1009).


23

Appendix L · Worked calculations bank

Fifteen solved problems. Every number is an example, and every answer was checked by script.

Ask a qualified expert. These sums teach method. The CEWP does the real design.

# Problem Working Answer
1 A 2,500 W air conditioner with power factor 0.85 on 230 V: current? 2,500 ÷ (230 × 0.85) 12.8 A
2 A 6 kW cooker: Ib? Which breaker size from the standard list? 6,000 ÷ 230 = 26.1 A; next size up 26.1 A; 32 A
3 A 7.5 kW shower: Ib? 7,500 ÷ 230 32.6 A (breaker 40 A)
4 Voltage drop for a 6 mm², 28 m cable carrying 26.1 A 7.5 × 26.1 × 28 ÷ 1,000 5.48 V = 2.38%
5 Voltage drop for a 1.5 mm², 25 m lighting run at 5 A 30 × 5 × 25 ÷ 1,000 3.75 V = 1.63%
6 Required It for 16 A, Ca 0.87, Cg 0.70 16 ÷ (0.87 × 0.70) 26.3 A
7 Heat per metre in 2.5 mm² at 23.5 A 23.5² × (2 × 0.0225 ÷ 2.5) 9.9 W per metre
8 Cost of a 1,800 W air conditioner for 8 h a day, 30 days, at the example GH¢2 per kWh 1.8 × 8 × 30 × 2 GH¢864
9 An insulation reading of 0.8 MΩ at 500 V DC on a circuit: pass? Limit 1 MΩ Fail; investigate
10 Max Zs for a 16 A type B breaker, and 80% of it 0.95 × 230 ÷ (5 × 16) = 2.73; × 0.8 2.73 ohm; 2.19 ohm
11 TT system with a 30 mA RCD: maximum electrode resistance by the 50 V rule 50 ÷ 0.03 1,667 ohm
12 One rod 2.4 m, 16 mm, soil 100 ohm metres Formula in Appendix E 40.4 ohm
13 Two such rods in parallel, widely spaced (ideal) 40.4 ÷ 2 20.2 ohm
14 Conduit inside 16.9 mm, cable 3.5 mm at 40% fill: how many cables? 0.4 × (16.9 ÷ 3.5)² 9
15 A balanced three-phase load of 10 kW at 400 V and power factor 0.8: line current? 10,000 ÷ (1.732 × 400 × 0.8) 18.0 A

(A generator sizing example: running load 5,000 W plus the extra starting load of two more air conditioner starts of 1,100 W each gives 7,200 W; at power factor 0.8 that is 9 kVA. Example numbers.)


24

Appendix M · Test-and-tell charts

Charts for the helper to understand what the CEWP is doing and to report clearly. The CEWP does the tests.

Ask a qualified expert. Every chart ends with "call the CEWP". Never test live, and never "fix" a reading.

Chart 1: An RCD trips

  1. Does it trip with every appliance unplugged? Yes: the fault is in the fixed wiring or the RCD: call the CEWP. No: go to 2.
  2. Plug in one appliance at a time. Which one makes it trip? That appliance has a leakage fault: leave it unplugged and report.
  3. Does it trip only in rain? Moisture in an outdoor fitting: call the CEWP.
  4. Does it trip at the same time every day? A heater or pump is leaking: report the time and the load.

Chart 2: An insulation reading is low

  1. Was the circuit dead and isolated, with sensitive equipment unplugged? No: repeat correctly.
  2. Is the reading below the limit (1 MΩ at 500 V)? Yes: the insulation is damaged or wet.
  3. Disconnect sections one by one with the CEWP to find the faulty section. Record each reading. The CEWP repairs and tests again.

Chart 3: Earth fault loop impedance is high

  1. Is the measured Zs above the limit for the breaker (Appendix F)? Yes: go to 2.
  2. Check for a loose terminal, a damaged earth wire, a long or thin cable or a poor earth electrode. Report all.
  3. The CEWP repairs and re-tests; you never adjust the number.

25

Appendix N · Tools, instruments and items glossary

This builds on Level 1 Appendix H. Each item is named and defined with a typical size or rating and a safety note. "Also called" gives other common English or trade names. Local names for tools differ from town to town. Use the standard name given here when you order or ask for help, and show the picture.

Ask a qualified expert. Sizes and ratings are typical international values and guides. The CEWP chooses the real items under L.I. 2008. Items marked CEWP are not for helpers to fit or use.

Name Type What it is and does Size, type or rating Status Also called
Air conditioner isolator Part A switch beside the AC unit Matches the circuit CEWP AC isolator, AC switch
Bonding clamp Part Joins a bonding wire to a pipe By pipe size CEWP earth bonding clamp
Bonding conductor Material Wire joining metal parts to main earth Size by CEWP CEWP bonding wire, equipotential wire
Breaking capacity (6 kA) Rating The fault current a breaker can switch off 6 kA typical for houses CEWP kA rating, fault rating
Calibration log Form A record of instrument checks A4 You may fill instrument log
Changeover switch Part Selects grid or generator Above the load CEWP transfer switch, ATS (automatic), manual changeover
Circuit chart Form A list of circuits at the board A4 You may write circuit schedule, board label
Clamp meter Instrument Reads current in one conductor CAT-rated CEWP tong tester, clamp ammeter
Continuity tester Instrument Checks the earth path Low-ohm CEWP low-ohm tester, buzzer tester
Earth electrode resistance tester Instrument Measures rod resistance Spike or clamp CEWP earth resistance tester, ground tester
Earth fault loop tester Instrument Measures fault path resistance Live test CEWP loop tester, Zs tester
Earthing conductor Material Rod to main earthing terminal Size by CEWP CEWP earth wire, ground wire
Earth inspection chamber Part A pit over the rod head Plastic or concrete Look only earth pit, inspection pit
Earth rod Part A buried metal rod Copper-bonded or galvanised; length by CEWP Carry ground rod, earth electrode
Fused connection unit Part A box with a fuse for a fixed appliance 13 A, fuse 3, 5, 13 A CEWP spur unit, FCU
Generator Equipment Makes electricity from an engine By kVA Refer gen set, standby generator
Insulation resistance tester Instrument Reads megohms on a dead circuit 250 / 500 / 1000 V CEWP megger, IR tester
Intermediate switch Part Third switch for 3+ place control Matches CEWP cross switch
Isolator Part A disconnect switch By load CEWP disconnector, main switch, isolating switch
MCB curve B, C, D Rating The trip speed shape of a breaker B, C, D CEWP trip curve
Megohm Unit A million ohms MΩ Learn M-ohm
Meter Part Utility kWh instrument Single-phase Never touch kWh meter, energy meter
Non-contact detector Instrument Warns of nearby voltage Pen Warning only volt stick, voltage pen, NCV detector
Permit-to-work Form A written permission for risky work A5 You fill your part work permit, PTW
Proving unit Instrument A known voltage source Pocket CEWP proving stick, proving device
Pump starter Part A switch with overload protection for a pump By motor CEWP motor starter, DOL starter
RCBO Part Breaker plus RCD 6 to 40 A, 30 mA CEWP combined breaker and RCD
RCD type A and AC Part Leakage trip types 30 mA CEWP leakage trip type
RCD tester Instrument Tests trip time Plug or lead CEWP RCD test unit, trip tester
Schedule of test results Form The record of test readings Appendix F You may fill test schedule, test record
Socket tester Instrument Quick wiring check Plug-in You may read plug-in tester, outlet tester
Surge protective device Part Diverts spikes Types 1, 2, 3 CEWP SPD, surge arrester, surge protector
Test leads Item Insulated wires with probes CAT-rated CEWP probes, test probes
Two-pole voltage tester Instrument Proves dead IEC 61243-3 CEWP voltage indicator, two-pole tester, voltage detector
Voltage drop Idea Volts lost along a cable % of 230 V Learn volt drop
Water heater isolator Part A double-pole switch for the heater 20 or 32 A CEWP heater switch, double-pole switch
13 A Type G socket and plug Part Standard outlet and plug 13 A, GS IEC 60884 Check 13 A plug, top
Cable, 1.5 mm² twin-and-earth Material Lights 1.5 mm² Carry flat cable, TWE cable, T&E
Cable, 2.5 mm² twin-and-earth Material Sockets and ACs 2.5 mm² Carry flat cable, TWE cable, T&E
Cable, 4 mm² twin-and-earth Material Big ACs, small cookers 4 mm² Carry flat cable, TWE cable, T&E
Cable, 6 mm² twin-and-earth Material Cooker, shower 6 mm² Carry flat cable, TWE cable, T&E
Cable, 10 mm² Material Large shower or sub-main 10 mm² Carry twin-and-earth, flat cable
Conduit 20 mm and 25 mm Material Common sizes for house runs 20, 25 mm (typical) Fix pipe 20 mm, PVC pipe
Conduit saddle and coupler Material Fix and join conduit By size Fix pipe clip, conduit clip
Cable tray and trunking Material Larger cable routes By size Fix tray, raceway
Cable lug and ferrule Part Ends for stranded wire By cable size CEWP terminal lug, ferrule
Torque screwdriver Tool Tightens terminals to a set torque Maker's range CEWP torque driver
Cable cutter Tool Cuts large cable Hand CEWP heavy cutters
Crimp tool Tool Fixes lugs By size CEWP lug crimper, crimping pliers
Heat-shrink sleeve Material Insulates a joint By size CEWP heatshrink, shrink sleeve
Terminal block (screw and push-in) Part Joins wires By amps CEWP connector block, choc block
Warning labels Material "Danger" and circuit labels Standard You may fit danger labels, stickers
26

Further reading and sources

Best next reads: the Energy Commission's electrical wiring pages; the GSA's notices on cables and plugs; the maker's instructions for any consumer unit, RCD or tester you meet; the HSE's guidance GS38 on test equipment (UK, foreign).

What this module does not cover: the Ghana text of L.I. 2008 and GS 1009 (not freely online: every table in the appendices is international and labelled, and the CEWP confirms), diversity in load calculations (Ghana's rule not found), the Energy Commission examination fees and syllabus, the official ICC form fields and fees, three-phase supplies (see Level 3 Appendix G), and solar and battery systems (see the hub's Solar Energy course).

Every source used in this manual is listed, with links, in the Teacher Copy.

One application of the Cold-Start Learning Kit, which stays general-purpose and can build a guide on any topic in any field. Written in CTVET format; not a CTVET or Energy Commission curriculum.