About this module
Every house, shop, clinic and farm needs safe wiring. Bad wiring starts fires and kills people, and good electricians are always in demand. This module teaches you the basics, the law and the safe way to begin. You will learn by watching, helping and asking questions, never by taking risks.
Who it is for. People with no formal certificate, aged 18 or over. National Proficiency I is a bridging level for people with little or no formal education; holders do routine tasks under supervision. In Ghana, nobody under 18 may do hazardous work.
What you may and may not do
The law first. The Electrical Wiring Regulations, 2011 (L.I. 2008) say that wiring must be done by certified electricians. Hiring an uncertified electrician can lead to a fine of up to 250 penalty units, up to two years in prison, or both, and the electricity supply can be disconnected. So at this level you assist a certified electrician. You never wire a house, a socket, a light or a consumer unit on your own. You never touch a circuit that is live. Ask a qualified expert: an Energy Commission-certified electrician.
How to read the labels in this book
Three kinds of number. (1) Ghana, verified: read on an official or press page and cited. (2) International standard, labelled: where no Ghana text could be read, the book uses the internationally accepted rule (IEC 60364 and the British BS 7671 that follows it) and says so. These are not Ghana law: check them against the Ghana Standards Authority and Energy Commission texts (L.I. 2008, GS 1009) when you read them. (3) Example: a number made up to teach a sum; always marked "example". Where a number could not be settled, the book writes "not verified". Ask a qualified expert: an Energy Commission-certified electrician (CEWP) confirms every number before you rely on it.
Why electrical work
- The Energy Commission says untrained, uncertified electricians cause poor installations, which can lead to electrical fires, electrocution and losses.
- The Commission has certified over 18,600 electricians and inspectors since L.I. 2008 took effect.
- In the November and December 2025 certification examinations, 1,179 of 1,386 candidates passed, about 85%.
- In Takoradi, 151 electricians in the Western Region were certified at one ceremony in 2026.
The road to certification
The Energy Commission says a beginner's path is structured training, then registration as an apprentice, then supervision by a certified professional, then certification. Over 600 apprentices were registered nationwide from March 2026, 36 of them women. Certified master electricians must register all their apprentices. This module is a good first step on that road.
This is not the certification syllabus. The Commission examines practitioners in Domestic, Commercial and Industrial categories, and there is an Inspector category too. The exam fees, entry rules and official syllabus were not found in full online: ask the Energy Commission for the current rules before you plan your path. National occupational standards for entry-level electrical installation at NP I and II have been developed; ask CTVET or the Ghana TVET Service for the official standard.
How the module works
Each unit has learning outcomes, performance criteria, the range and the evidence your assessor needs. You are judged Competent or Not Yet Competent by being watched at work, by answering questions, and by your logbook. About 60% of the time is practical.
Unit 1 · Electricity, the law and staying alive
You cannot see electricity, smell it or hear it, but it can stop your heart in a second. Respect it, learn the rules, and you will have a long career.
Competency standard
| Learning outcome | Performance criteria — the trainee… |
|---|---|
| 1.1 Explain the hazards | names shock, burns, fire and falls as the four main dangers |
| 1.2 Explain the law | says who may wire in Ghana, and what the Energy Commission does |
| 1.3 Isolate, lock, test | follows the isolate, lock out, test dead rule on a training board with the instructor |
| 1.4 Respond to a shock | gives the first steps and calls for help |
| 1.5 Refuse unsafe work | says no to live work and to unapproved materials |
Range. All workshop and site work. Evidence. Observation every session; oral questions.
Ask a qualified expert. For all electrical work, hire an Energy Commission-certified electrician (CEWP). Do not attempt any work you are not trained and authorised to do. For any injury, shock or burn, see a doctor or nurse; in an emergency, call 112. This unit teaches awareness and good practice, not medical treatment. This is general information about the law, not legal advice: ask a qualified lawyer or the Energy Commission before you act.
The four dangers
- Shock. Current passing through your body can stop the heart or breathing. In Ghana the supply to a house is 230 volts, 50 hertz.
- Burns. Arcs and hot cables burn skin and eyes.
- Fire. Faulty wiring, overloaded circuits and illegal connections are named causes of fires. Ghana's fire service recorded 3,595 fire cases in the first half of 2025.
- Falls. Ladders and roofs are part of the job. Never work from a broken ladder.
The law in plain words
- The Electrical Wiring Regulations, 2011 (L.I. 2008) require certified electricians for all wiring installations.
- The utility must not supply premises that do not meet the rules, and must disconnect supply where the rules are not met.
- You need an Installation Completion Certificate to be connected to the grid or to get a personal meter, and only certified electricians can give it.
- Anyone can check an electrician through the Certified Electrician mobile app, the Energy Commission website or CEWPAG, the electricians' association.
- Only materials approved by the Ghana Standards Authority may be used for wiring.
Which year is L.I. 2008? News reports call it the Electrical Wiring Regulations, 2011 and some say 2012. The number L.I. 2008 is the same in all of them. Use "L.I. 2008" when you speak to people.
From the field: too small, so it keeps tripping
The moment. A breaker kept going off.
The problem. Repeated tripping, mostly in rural areas and slums where people avoid qualified persons.
The cause. Undersized cable overheats and trips the breaker many times. Tripping on one section also shows that section is overloaded.
What was done. The ECG only connects a house when a certified contractor has validated and approved the wiring before a meter is given. [[FLAG: check the current Energy Commission certificate process]]
The lesson. A breaker that keeps tripping is a warning, not a nuisance.
Next time. 1. Find which section is overloaded. 2. Lighten it or re-wire that circuit with the correct cable. 3. Call a certified electrician.
Told by De-Graft Afful, from his own site experience.
Technical note (international method, labelled). A breaker that trips is doing its job: the cable cannot carry the load. The cure is a larger cable chosen by the CEWP, never a bigger breaker on the same cable. Appendix C explains the current Ghana certificate route. Ask a qualified expert: an Energy Commission-certified electrician.
Tools and items for this unit
Each item is named and defined at first use. "Also called" gives other common English or trade names. Local names for tools differ from town to town. Use the standard name given here when you order or ask for help, and show the picture. Helper status says what you may do.
| Item | What it is and what it does | When you use it | Size or type | Also called | Helper status |
|---|---|---|---|---|---|
| Lock-out padlock | A small padlock with its own key that locks a breaker or isolator in the OFF position | Every time a circuit is isolated | One lock, one key, one person; coloured body helps | safety lock, lockout lock | You may use it |
| Lock-out tag | A card tied to the lock with the name, date and "Do not switch on" | With every padlock | Plastic or card, about palm size | danger tag, lockout tag | You may use it |
| Breaker lock-off device (hasp) | A clip that fits over the breaker toggle so a padlock can be fitted | When a breaker has no hole for a lock | Fits 1-pole and 2-pole MCBs | MCB lock, lockout clip | You may use it |
| Voltage tester (approved voltage indicator, two-pole) | A tester with two probes that lights or shows when voltage is present; used to prove dead | By the CEWP only, with the prove-test-prove steps | Probe tips short and shrouded; marked to IEC 61243-3 (international, not verified here) | voltage indicator, two-pole tester, voltage detector | Watch only |
| Proving unit | A small box that gives a known voltage so the tester can be checked before and after use | Every test | Pocket size | proving stick, proving device | Watch only |
| Non-contact voltage detector ("volt stick") | A pen-shaped sensor that beeps near live conductors. It shows live; it can never prove dead | For a quick warning only | Pen size, batteries | volt stick, voltage pen, NCV detector | You may use it as a warning only |
| Safety glasses, gloves, boots, hard hat, high-visibility vest | The personal protective equipment (PPE) set | Hard hat and vest on building sites; glasses when drilling or cutting | Boots with non-metal toe cap and insulating sole are best (check the maker's rating) | goggles, safety spectacles | You must wear it |
| First-aid kit | A box with dressings, gloves and a breathing mask | Kept on site and in the workshop | Contents checked monthly | first aid box | You may use it |
| Emergency poster | A page that says: switch off, do not touch, call 112 | Fixed on the workshop wall | A4 or larger | safety poster | Read it |
The golden rule: isolate, lock out, test dead
Before anyone works on a circuit, three things must happen, in this order:
- Isolate. Switch the circuit off at its breaker or main switch.
- Lock out. Put a padlock and a tag on the switch, so nobody switches it back on. Keep the key in your pocket.
- Test dead. A qualified person uses an approved voltage tester, checks the tester on a known live source, tests the circuit, then checks the tester again. This is called prove, test, prove.
A switch in the "off" position or a tripped breaker is not proof that a circuit is dead. A non-contact "volt stick" shows that something is live, but it does not prove that something is dead. At this level the CEWP does the test; you watch and learn.
You are not allowed to do live work. Not "just to see if it works". Not "it is only a small wire". Not "the electrician said it is fine". If you are not sure it is dead and locked, it is live.
Parts of the lock-out kit and the voltage tester
| No. | Part | What it does | Safety rule |
|---|---|---|---|
| 1 | Personal safety padlock | Locks the breaker or isolator OFF | One lock, one key, one person; the key stays in your pocket |
| 2 | Danger tag | Tells everyone "Do not switch on" | Written clearly; never removed by anyone else |
| 3 | Name and date tag | Shows who locked it and when | Fill in before fitting |
| 4 | Breaker lock-off clip | Holds an MCB toggle OFF so a lock can be fitted | Check it fits snugly; do not force |
| 5 | Hasp | A hinged bar that takes several locks | One lock per worker on the hasp |
| 6 | Cable tie | Fixes the tag to the lock or switch | Use a new tie each time |
| 7 | Lock-out register | A book where each lock is recorded | Sign in and out |
| No. | Part | What it does | Safety rule |
|---|---|---|---|
| 1 | Probe tip | The short exposed metal that touches the conductor | Keep the exposed length short; never bend or file it |
| 2 | Finger guard | Stops your fingers sliding onto the tip | Never hold in front of the guard |
| 3 | Second probe handle | The second contact point | Check the insulation for cracks |
| 4 | Connecting lead | Joins the two probe bodies | Replace if the insulation is cut |
| 5 | Display | Shows the voltage | If it is blank, the tester is not proven |
| 6 | Indicator lamps | Light up when voltage is present | Prove on the proving unit first |
| 7 | Test button | Self-checks the tester | Press before use |
| 8 | Main body | Holds the electronics and battery | Keep it dry; do not drop it |
SAFETY PROTOCOL: isolation and lock-out (hazardous task, CEWP-led).
Before: the CEWP is named and present; PPE on (boots, glasses, gloves, hard hat on site); lock-out kit checked; the circuit identified; the CEWP isolates at the breaker.
While: Do fit your own padlock and tag and keep the key. Do watch the CEWP prove the tester, test, and prove again. Do not touch any conductor, even if "it is off". Do not use a non-contact detector as proof. Do not remove anyone else's lock.
After: tools out and counted; the lock is removed only by its owner; tell the CEWP; sign the lock-out register; store the kit.
Emergency: if anyone is shocked, do not touch them, switch off the supply, call 112, give first aid if trained (see below); report faults in the tester or lock to the CEWP at once.
First aid for electric shock
- Do not touch the person while they may still be in contact with the supply.
- Switch the power off at the breaker or main switch. If you cannot, push them away with a dry non-conducting thing such as a dry wooden stick.
- Call 112 and ask for an ambulance.
- Check if the person is awake and breathing; if trained, give first aid while waiting for help.
- Even if the person seems fine afterwards, they must see a doctor or nurse.
Safe or unsafe?
Your trainer describes eight scenes. For each, say safe or unsafe and why.
Lock-out drill on the training board
- Dress in boots, gloves and glasses; your partner checks you.
- Find the board's isolator. Switch it off (the board is not connected to the mains, but treat it as if it were).
- Fit a padlock and a tag with your name and date. Keep the key.
- Watch your instructor prove the tester on the proving source, test the board, and prove again.
- Say aloud the three words: isolate, lock out, test dead.
- Record the drill in your logbook.
Look around at home
Walk round your home with a family member. Write down three safe things and three worrying things about the wiring you can see (for example cracked sockets, bare wire, an overloaded extension). Do not touch anything. Tell an adult.
Check yourself
- Name the four main dangers of electrical work.
- What are the three steps of the golden rule?
- Who may legally do wiring in Ghana?
Unit 2 · How electricity works in a house
If you understand a torch, you understand a house. Both have a source, a path and a load, and both stop working when the path is broken.
Competency standard
| Learning outcome | Performance criteria — the trainee… |
|---|---|
| 2.1 Explain a circuit | draws a simple circuit and names source, path and load |
| 2.2 Use the units | explains volts, amps, watts and kilowatt-hours |
| 2.3 Calculate load and cost | finds amps from watts and the cost of using an appliance |
| 2.4 Explain the earth | says why every house needs an earth |
Range. Single-phase house supply; simple calculations. Evidence. Drawings; calculations; oral questions.
Ask a qualified expert. This unit teaches ideas, not wiring. For any electrical installation or test, hire an Energy Commission-certified electrician. Do not attempt any electrical work you are not trained and authorised to do.
The circuit
Electricity flows only round a closed loop: from the source, along a conductor to the load (a lamp, a fan), and back. If the loop is broken, nothing flows. A switch simply breaks and closes the loop. In a house, the live conductor carries the current to the load and the neutral brings it back. The earth is a separate safety path (see below).
The words
| Word | Meaning | Unit | Simple picture |
|---|---|---|---|
| Voltage | The push | volt (V) | Water pressure |
| Current | The flow | ampere, amp (A) | How much water flows |
| Power | How hard the appliance works | watt (W) | The size of the job |
| Energy | Power used over time | kilowatt-hour (kWh) | What the meter counts |
A kilowatt (kW) is 1,000 watts. The units on your meter are kilowatt-hours: a 1,000 W appliance used for one hour uses 1 kWh. The house supply in Ghana is 230 V at 50 Hz.
To find the current, divide the watts by the volts: amps = watts ÷ volts. A 2,000 W kettle on 230 V draws about 8.7 A.
Why cable size matters
A cable carries only so much current before it gets hot. Too much current heats the cable and can melt the insulation and start a fire. This is why each circuit has a breaker, and why the electrician chooses cable and breaker together. You do not choose them at this level; the certified electrician does, under L.I. 2008.
From the field: the house that burnt
The moment. A house was burnt down within two years of use. The whole house and all its wiring were lost.
The problem. Three air conditioners were running on one cable. That cable was the same size as the one bringing the mains in from the electricity company.
The cause. The cable was too small for the load, so it overheated, the wires touched, and the spark started the fire.
What was done. Nothing could be saved. [[FLAG: author to confirm: any action taken afterwards, who inspected]]
The lesson. One small cable cannot carry three air conditioners.
Next time. 1. Add up the load before choosing the cable. 2. Give each big load its own correctly sized circuit and breaker. 3. Use good-quality cable and ask a qualified, certified electrician to check the design.
Told by De-Graft Afful, from his own site experience.
Technical note (international method, labelled). Each circuit is sized for its own load, and the breaker is chosen for the cable: the load current must not exceed the breaker rating, and the breaker rating must not exceed the cable's safe current. The service cable only brings the supply to the house; it does not size your circuits. An inspection before connection should have caught this. Ask a qualified expert: an Energy Commission-certified electrician (CEWP) sizes cables under L.I. 2008.
Why heat grows so fast (worked example, example numbers)
A cable heats in proportion to the square of the current: heat in watts = current² × resistance. Copper's resistance is about 0.0225 ohm for 1 mm² and 1 metre at working temperature (a textbook value, recalculated by script), and the current goes down one conductor and back along the other, so the resistance per metre of a two-wire run is 2 × 0.0225 ÷ size.
| Case (example: each air conditioner 1,800 W on 230 V) | Current | Heat in 2.5 mm² cable | Heat in 6 mm² cable |
|---|---|---|---|
| One air conditioner | 7.8 A | 1.1 W per metre | 0.5 W per metre |
| Three air conditioners on one cable | 23.5 A | 9.9 W per metre | 4.1 W per metre |
Three times the current gives nine times the heat. Nine watts in every metre, for hours, inside a ceiling, is how insulation softens, wires touch and a fire starts. (Heat figures recalculated by script. They teach the idea; the CEWP chooses the real cable. Appendix A of Level 2 gives the sizing method.)
The earth
Every appliance with a metal case has an earth wire. If a fault lets live current touch the case, the earth gives that current a safe path so the breaker can trip, instead of you becoming the path. The earth wire is the most important wire you will never see working.
Colours. Wire colours in Ghana have changed over time and old houses may have red, black or other colours. Some sources say new wiring uses brown for live, blue for neutral and green and yellow for earth, as in Britain, but the exact rule in L.I. 2008 was not found. Never trust a colour. Always test, and ask the certified electrician.
Tools and items for this unit
| Item | What it is and what it does | When you use it | Size or type | Also called | Helper status |
|---|---|---|---|---|---|
| Electricity meter (prepaid or postpaid) | The electricity company's instrument that counts kWh | Read it for the bill; never open it or break the seal | Single-phase house meter | kWh meter, energy meter | Never touch the inside |
| Appliance rating label | A sticker on the appliance with volts, watts or amps | Before you add the appliance to a load list | Look at the back or base | nameplate, rating plate | You may read it |
| Torch battery, small bulb, switch and wire (low-voltage kit) | A safe model circuit for learning | Unit practical only | 3 V to 6 V, never mains | model circuit kit | You may use it |
| Calculator | To work out amps, kWh and cost | Every sum in this book | Any basic one | - | You may use it |
The bill
A house is billed for the units it uses. The tariff changes from time to time. For non-residential users from April 2026 the first 300 units a month cost about GH¢1.78 per unit, and tariffs rose 3.49% from July 2026. The home tariff was not verified; the sums below use an example price of GH¢2 per kWh. Ask your electricity company for the real one.
Watts, amps and cost
Example tariff GH¢2 per kWh. (1) A 60 W fan runs 10 hours. How many kWh and what cost? (2) A 1,500 W iron runs 2 hours. kWh and cost? (3) How many amps does the 1,500 W iron draw on 230 V? (4) Which costs more, the fan for 10 hours or the iron for 2 hours?
Draw and measure the circuit
- On paper, draw a battery, a switch and a lamp, and mark source, path and load.
- With the instructor, build the same circuit from a torch battery, a small bulb, wire and a switch (this is low voltage, not mains).
- Open and close the switch; say what happens to the loop.
- Copy your appliance table: list 5 appliances from home with their watts from the label.
- Work out amps and cost for each, using the example tariff.
Read the labels
At home, read the label on five appliances and write down the watts and volts. Work out the amps for each.
Check yourself
- What does a switch do to a circuit?
- A 1,000 W heater runs for 3 hours. How many kWh?
- Why does a metal-cased appliance have an earth wire?
Unit 3 · The parts of a house installation
Walk through a house and you will see only the switches, sockets and lights. Behind the wall is a whole system. Know its parts and you will know where to look.
Competency standard
| Learning outcome | Performance criteria — the trainee… |
|---|---|
| 3.1 Name the parts | names the meter, consumer unit, breakers, circuits, cables, switches, sockets and lights |
| 3.2 Read a simple layout | follows a drawing of one room circuit |
| 3.3 Tell good from bad parts | checks standard marks and spots damaged parts |
Range. Single-phase house. Evidence. Labelled drawings; board tour; oral questions.
Ask a qualified expert. This unit names parts; it does not teach you to connect them. Only an Energy Commission-certified electrician may connect, change or open them. Never open a consumer unit or meter.
From the pole to the plug
| Part | What it does |
|---|---|
| Service cable and meter | Brings the supply in and counts the units; belongs to the electricity company |
| Main switch | Switches the whole house off |
| Consumer unit (the "fuse box") | Holds the breakers and often an RCD (Level 2 explains it) |
| Circuit breaker (MCB) | Trips automatically when a circuit carries too much current |
| Circuits | Separate loops, for example lights, sockets, air conditioner, cooker |
| Cables | Carry the current to switches, sockets and lights |
| Switches, sockets and light fittings | Where you use the supply |
| Earth conductor and earth electrode | Safety path to the ground |
A house is divided into circuits so that one fault does not put the whole house in the dark, and so that each circuit has the right cable and breaker for its load.
Sockets and plugs
Ghana uses plug types D and G. The Ghana Standards Authority says household plugs and sockets must meet its standards, and notes the 13 A, three-pin type G plug. Buy only plugs and sockets marked with a standard number.
Cables
- Cables and accessories sold in Ghana must meet GSA standards under the Electrical Wiring Cables and Accessories Regulations, 2023 (L.I. 2478); importers and manufacturers must register with the Energy Commission and get a Certificate of Conformance.
- Storing or selling cables that do not comply is illegal, and the Energy Commission, the GSA, Customs and the Police can inspect and seize them.
- Look for a standard number on the packaging or the cable. The GSA gives GS-1009 as the wiring code and GS IEC 60227 as an example cable standard.
Cable types, sizes and colours
| Cable type | What it is | Where it is used | Note |
|---|---|---|---|
| Single-core cable | One copper conductor in coloured PVC | Inside conduit, to the lights and sockets | Needs conduit or trunking for protection |
| Twin-and-earth (flat) cable | Two insulated conductors (live and neutral) and one bare earth in a grey or white PVC sheath | Fixed wiring behind plaster or in ceilings | The bare earth must be sleeved green-and-yellow at every connection |
| Flexible cord (flex) | Many fine copper strands in rubber or PVC, for items that move | From plug to appliance | Never use as fixed wiring |
| Armoured cable | Cable with a steel wire layer | Outdoors or underground, where it can be hit | Fitted only by the CEWP |
What does "mm²" mean? It is the cross-section area of the copper, the thickness of the metal path for current. Standard international sizes are 1.5, 2.5, 4, 6, 10 and 16 mm² and bigger (IEC 60228 sizes; international, not verified in a source read for this book). A bigger number carries more current and heats less. Solid or stranded: a solid conductor is one wire (stiff, for fixed wiring); a stranded conductor is many thin wires (flexible). Old gauge numbers (AWG, SWG) are not the same as mm²; do not mix them.
Colours: the international rule (labelled), Ghana to be checked. The internationally harmonised single-phase colours are brown for live, blue for neutral and green-and-yellow for earth; for three-phase, brown, black and grey for the three lives. Older installations used red for live, black for neutral and green or bare for earth. This is not verified in a source read for this book. Ghana's colour rule and the date it changed are to be checked in GS 1009 or with the Energy Commission. A house may have mixed colours. Never trust a colour: test, and ask the CEWP.
| No. | Part | What it does | Safety rule |
|---|---|---|---|
| 1 | Outer sheath (black here) | Holds the cores together and protects them | Never strip it far back or leave it cracked |
| 2 | Brown core insulation | Covers the live conductor under the international colour rule | Treat as live until proven dead |
| 3 | Blue core insulation | Covers the neutral conductor under the international colour rule | Also dangerous when live |
| 4 | Bare copper earth conductor | The safety path; it has no insulation of its own | Must be sleeved green-and-yellow at every connection |
| 5 | Stranded copper conductor | Many thin copper wires that carry the current | Never cut strands off to fit a terminal |
| 6 | White filler between sheath and cores | Fills the space inside the sheath | Cut it back with the sheath, as the electrician shows |
(Sheath colours vary: this cable is black, others are grey or white. Brown and blue are the international colours; Ghana's rule is to be checked, as written above.)
| No. | Part | What it does | Safety rule |
|---|---|---|---|
| 1 | Outer sheath | Holds the cable together and protects it | Never strip it far back or leave it cracked |
| 2 | Live conductor (brown insulation) | Carries current to the load | Treat as live until proven dead |
| 3 | Neutral conductor (blue insulation) | Carries current back | Also dangerous when live |
| 4 | Bare earth conductor | The safety path | Must always be sleeved green-and-yellow at connections |
| 5 | Copper core | The metal path; its area in mm² sets the current limit | Copper must be pure; do the magnet test on samples |
| 6 | Insulation | Keeps conductors apart | Even thickness; replace cable if cut or cracked |
(Colours drawn as in the international rule; Ghana's colour rule is to be checked.)
Spotting bad cable
| Check | Good sign | Bad sign |
|---|---|---|
| Brand and marking | Known brand; standard number printed | No name, no number |
| Length | A standard coil is about 100 yards (91.4 m) | Short coil sold at a long-coil price |
| Copper | Pure copper is not attracted by a magnet | Magnet sticks: impurities that can overheat |
| Price | About the same as other dealers | Far below others |
Tools and items for this unit
| Item | What it is and what it does | When you use it | Size or type | Also called | Helper status |
|---|---|---|---|---|---|
| Consumer unit (distribution board, "fuse box") | A box with the main switch, the breakers and the neutral and earth bars | Where the house is divided into circuits | Often 4 to 12 ways in a house | fuse box, distribution board, DB | Never open it |
| Busbar, neutral bar, earth bar | Metal strips inside the box that carry the supply to the breakers (busbar) or collect the neutral and earth wires | Inside the consumer unit | Brass or copper strips | ground bar, earth terminal bar | Never touch |
| Circuit breaker (miniature circuit breaker, MCB) | A switch that trips when the current is too high | One for each circuit | Common ratings 6, 10, 16, 20, 25, 32, 40 A (international preferred values; the CEWP chooses) | breaker, MCB, trip switch | Never touch |
| Residual current device (RCD) | A switch that trips when current leaks to earth, for example through a person | Protects people on sockets and other circuits | 30 mA is the usual personal-protection setting | RCD, earth leakage breaker, ELCB | Press TEST only as the electrician shows |
| Isolator (main switch) | A switch that disconnects the supply, no automatic tripping | At the start of the installation or for one big appliance | Same current rating as the circuit | disconnector, main switch, isolating switch | Never touch |
| Junction box | A small box where cables are joined | Ceilings and walls | Plastic, with screw terminals | JB, joint box | Fix empty boxes only |
| Back box | A box set in the wall behind a socket or switch | At every switch and socket | Depths of about 25, 35 and 47 mm are common (typical) | pattress, wall box, flush box | You fix it, dead only |
| Conduit and trunking | Plastic or steel tube (conduit) or channel (trunking) that holds cable | Walls, ceilings and surfaces | Conduit 16, 20, 25 and 32 mm are common sizes (typical) | pipe and raceway | You may fix it |
| No. | Part | What it does | Safety rule |
|---|---|---|---|
| 1 | Enclosure and cover | Keeps hands away from live parts | Never open or remove the cover |
| 2 | Incoming supply cable | Brings the supply from the meter | Never touch |
| 3 | Main switch | Switches the whole house off | The CEWP uses it for isolation |
| 4 | RCD with TEST button | Trips when current leaks to earth | Press TEST only as the electrician shows |
| 5 | Circuit breaker (MCB) | Trips on overload or short circuit | Never tape or wedge it on |
| 6 | Busbar | A metal strip that feeds the breakers | Live: never touch |
| 7 | Neutral bar | Collects the neutral wires | Live when the supply is on |
| 8 | Earth bar | Collects the earth wires | Never disconnect |
| 9 | Circuit label strip | Names each circuit | Keep it up to date |
| 10 | DIN rail | The metal rail that holds the devices | Part of the board; do not touch |
| 11 | Outgoing circuit cables | Take power to lights, sockets, AC | Never pull or move them |
| No. | Part | What it does | Safety rule |
|---|---|---|---|
| 1 | Earth pin | The longest pin; connects the earth first; opens the shutters on the socket | Never snap it off or use an adaptor that bypasses it |
| 2 | Neutral pin | Return path | Part of a matched set |
| 3 | Live pin | Carries current in | Never poke with metal |
| 4 | Fuse | A cartridge that blows to protect the lead, 3 A or 13 A | Choose by appliance label; never use foil or wire |
| 5 | Cord grip | Holds the cable so the wires are not pulled | Must grip the outer sheath |
| 6 | Flex entry | Where the cable enters the plug | No bare wire outside |
| 7 | Cover screw | Holds the plug together | Replace a cracked plug at once |
(The real plug has the earth pin at the top, above the live and neutral pins; the sketch is simplified. A plug may be changed only by a competent person, not by a helper on a live circuit.)
Light, socket and the ring of life
Lights and sockets are on separate circuits. Why? A fault in a heater plug should not leave you in the dark. Also the cable and breaker for lights are smaller than for sockets and heavy appliances. Your certified electrician decides the sizes (Level 2 explains the ideas).
Name the parts
Your trainer shows a labelled drawing of a house with eight numbers pointing at parts. Name each part and say what it does.
Board tour
- With the board dead and locked, name every part on the training board.
- Trace one circuit with your finger from the consumer unit to the socket.
- Read the label on three cables: size, standard number, voltage rating.
- Inspect three plugs or sockets for a standard mark and for damage; list the faulty ones.
- Draw the board in your logbook with labels.
Spot the parts at home
Find the meter, main switch and consumer unit in your home or a relative's. Draw where they are. Do not open them.
Check yourself
- What does a circuit breaker do?
- Why are lights and sockets on different circuits?
- Name two signs of a bad cable.
Unit 4 · Tools, instruments and materials
A good helper brings the right tool and keeps it in good condition. Cheap tools break, and broken tools hurt.
Competency standard
| Learning outcome | Performance criteria — the trainee… |
|---|---|
| 4.1 Name and use hand tools | names and uses insulated hand tools safely |
| 4.2 Care for instruments | knows what a voltage tester and a multimeter do, without using them live |
| 4.3 Choose materials | reads labels and buys approved materials |
| 4.4 Work tidy | keeps the site clean and tools counted |
Range. Hand tools, drill, ladder, voltage tester, multimeter, cable, conduit, boxes, plugs, sockets. Evidence. Tool tour; oral questions; observation.
Ask a qualified expert. For any electrical work, hire an Energy Commission-certified electrician. At this level you do not use a tester on a live circuit. You watch the CEWP use it.
Hand tools
| Tool | Use | Care |
|---|---|---|
| Insulated screwdrivers | Fix screws in switches and sockets | Check the handle is not cracked |
| Pliers and side cutters | Hold and cut cable | Keep the cutting edge sharp |
| Wire stripper | Take off the insulation without cutting the copper | Choose the right size |
| Knife and tape | Trim and wrap | Cut away from your body |
| Tape measure and spirit level | Mark positions | Keep clean |
| Hacksaw and file | Cut conduit | Deburr cut ends |
| Hammer, drill and bits | Fix boxes and saddles | Use glasses and a dust mask |
| Ladder | Reach ceilings | Check feet and rungs; someone holds it |
Insulated handles do not make live work safe. They protect only if the circuit is dead and locked.
The test instruments
- Voltage tester (approved voltage indicator). Used by the certified person to prove a circuit dead. The tester must be checked before and after each test ("prove, test, prove"), and a non-contact detector cannot prove dead.
- Multimeter. Measures voltage, resistance and continuity. Its probes must be in good condition. A multimeter is not the tool to prove dead.
- Continuity. With the circuit dead, a continuity test checks that the conductor is unbroken. This is a job for the certified electrician and a competent helper at Level 2.
Tools and items, defined
These are the tools a helper meets. A "tool tour" photograph page is a good classroom aid (use your own centre's tools).
| Tool or instrument | What it is and does | When to use it | Size or type | Helper status |
|---|---|---|---|---|
| Insulated screwdriver set | Screwdrivers with plastic-covered shafts and handles | Terminals, screws in boxes | Slotted (flat) blades 3 to 6 mm; cross-head sizes PH1 and PH2 (typical) | You may use it |
| Combination pliers | Pliers that grip, twist and cut | Holding and bending wire | About 180 mm | You may use it |
| Long-nose pliers | Thin-tipped pliers | Reaching into boxes, forming loops | About 160 mm | You may use it |
| Diagonal (side) cutters | Cutters whose blades meet at an angle | Cutting wire flush, cable ties | About 160 mm | You may use it |
| Wire stripper | A tool that removes insulation without cutting the copper | Preparing cable ends | Automatic type grips and strips in one squeeze; set to the wire size | You may use it |
| Electrician's knife | A short, strong knife | Trimming sheath on dead, unconnected cable | Folding blade | You may use it, cut away from you |
| Insulating tape (PVC tape) | Plastic tape that insulates and marks | Marking colours, wrapping ends | 19 mm wide, in colours | You may use it |
| Tape measure | A rolled steel ruler | Marking positions and lengths | 5 m | You may use it |
| Spirit level | A bar with a bubble that shows level | Fixing boxes straight | 600 mm | You may use it |
| Hacksaw and half-round file | A saw for cutting conduit and a file for smoothing the cut | Cutting plastic or metal conduit | 24 teeth per inch blade (typical) | You may use it |
| Claw hammer | A hammer with a claw for pulling nails | Fixing clips and saddles | About 450 g | You may use it |
| Club hammer and cold chisel (bolster) | A heavy hammer and a wide steel chisel | Chasing (cutting channels) in blockwork | 1.5 kg hammer, 100 mm bolster (typical) | Watch first, then with permission |
| Hammer drill and masonry bits | A drill that hammers as it turns, for block and concrete | Holes for plugs and boxes | Bits of 6, 8 and 10 mm (typical) | With permission, with glasses and mask |
| Wall plugs | Plastic sleeves that hold a screw in a drilled hole | Fixing saddles and boxes | Colour-coded to the bit size | You may use them |
| Ladder (step or extension) | A frame for reaching high work | Ceiling work | Check feet, rungs and locks; someone holds it | Use with a holder |
| Fish tape (draw wire) | A flexible steel or plastic strip used to pull cable through conduit | Pulling unconnected cable | 10 m to 30 m | You may use it |
| Conduit bending spring | A coiled spring that goes inside plastic conduit to stop it kinking | Gentle bends in small conduit | Fits 20 mm conduit (typical) | You may use it |
| Cable cutters | Heavy cutters for large cable | Cutting big cable | Hand type | CEWP or with permission |
| Crimping tool and lugs | A tool that squeezes a metal sleeve (lug) onto a conductor | Big cable ends | By cable size | CEWP only |
| Torch or headlamp | A hands-free light | Dark ceilings and boards | LED | You may use it |
| Cable ties and marker pen | Plastic straps and a pen | Tidying and labelling | 100 to 200 mm ties | You may use them |
Instruments (the certified person uses them; you must know what each one does and does not do):
| Instrument | What it measures or proves | What it does NOT prove |
|---|---|---|
| Two-pole voltage tester with proving unit | Proves a circuit is dead (when prove, test, prove is followed) | Nothing about insulation quality |
| Non-contact detector | That live voltage is near | It cannot prove dead |
| Multimeter | Voltage, resistance and continuity | It is not the proving tool; use only as the CEWP allows |
| Clamp meter | Current in a wire without touching the metal, by clamping around one conductor | Voltage |
| Insulation resistance tester ("megger") | Resistance of insulation, in megohms, on a dead circuit | Does not prove earth quality |
| Continuity (low-ohm) tester | Whether a wire or earth path is unbroken | Does not test insulation |
| Earth electrode resistance tester | The resistance of the earth electrode to the ground | Does not prove wiring is correct |
| Earth fault loop impedance tester | The path resistance that a fault current must follow | It is a live test for the certified person |
| RCD tester | The time and current at which an RCD trips | Does not test the rest of the circuit |
| Plug-in socket tester | A quick check of socket wiring for wrong connections | It does not replace the full tests |
| Cable locator and stud detector | Finds cables and metal behind walls | Does not prove a cable is dead |
(Instrument ideas are international practice; Ghana's required tests are with the CEWP and the Energy Commission.)
From the field: his bench warning (told by De-Graft Afful). "Use a qualified and certified electrician and use quality wires and materials." Everything else in this book supports that one line.
Parts and safety protocols for the main tools
| No. | Part | What it does | Safety rule |
|---|---|---|---|
| 1 | Insulated grip (red plastic cover) | Your grip on one arm | Check for cracks; insulated grips do not make live work safe |
| 2 | Jaws with a notch | The notched tips at the top that close on the wire | Use the notch for the wire size, never a smaller one |
| 3 | Slot in the arm | A long slot in one arm; with the nut it makes the tool adjustable | Set it before use |
| 4 | Nut | Locks the setting in the slot | Keep it tight |
| 5 | Steel arm | Carries your squeeze from the grip to the jaws | Do not use it as a hammer or lever |
| 6 | Second insulated grip | Your grip on the other arm | Check for cracks |
(This is a different design from the sketch below, which shows a pivot, spring and cutting edge. Both are wire strippers; use the tool as the electrician shows.)
| No. | Part | What it does | Safety rule |
|---|---|---|---|
| 1 | Upper handle | Your grip; insulated | Check for cracks |
| 2 | Lower handle | Your grip; insulated | Insulated handles do not make live work safe |
| 3 | Pivot | Joint on which the jaws swing | Keep tight and oiled |
| 4 | Jaws | Hold the wire while stripping | Keep clean; do not grip live wire |
| 5 | Stripping notches | Sized openings that cut only the insulation | Use the notch for the wire size, not a smaller one |
| 6 | Return spring | Opens the handles after use | Replace if weak |
| 7 | Adjusting stop | Sets the strip length | Set before use |
| 8 | Cutting edge | Cuts wire to length | Keep sharp; cut away from your face |
| No. | Part | What it does | Safety rule |
|---|---|---|---|
| 1 | Side rail (stile) | Carries the load | Reject a bent, cracked or repaired rail |
| 2 | Rung (step) | The tread you stand on | Clean and dry; no cracked rungs |
| 3 | Top platform | The top step | Never stand on the top platform |
| 4 | Hinge | Lets the ladder open | Check it is not loose |
| 5 | Spreader brace | Locks the ladder open | Fully locked before climbing |
| 6 | Right foot | A rubber foot that grips | Replace if worn |
| 7 | Left foot | A rubber foot that grips | Place on firm, level ground |
SAFETY PROTOCOL: step ladder (working at height).
Before: check rails, rungs, feet and the brace; open fully and lock; place on firm, level ground away from doors and bare wires; wear boots with grip; a second person holds the ladder.
While: Do face the ladder and keep three points of contact. Do not overreach, stand on the top platform, carry heavy loads while climbing or use a metal ladder near live parts. Do not use a ladder in rain or wind.
After: close and store it dry and flat or upright on a rack; report damage and tag a damaged ladder "Do not use".
Emergency: if someone falls, do not move them if they are hurt; call 112; keep the area clear; if the ladder touched a live part, do not touch it: switch off the supply first.
| No. | Part | What it does | Safety rule |
|---|---|---|---|
| 1 | Body (housing) | Holds the motor and gears | Check the case is not cracked |
| 2 | Pistol handle | Main grip | Hold with both hands |
| 3 | Trigger | Starts and speeds the drill | Release to stop; never lock on |
| 4 | Chuck | Holds the bit | Tighten fully; remove the key |
| 5 | Masonry bit | The cutting tool for block and concrete | Use a sharp bit of the right size |
| 6 | Hammer mode selector | Switches hammering on and off | Use hammer mode only for masonry |
| 7 | Direction switch | Forward or reverse | Change only when stopped |
| 8 | Side handle | The second grip that controls the twist | Always fitted |
| 9 | Power cable | Brings mains power | Keep away from the bit; use a protected supply; check for cuts |
SAFETY PROTOCOL: hammer drill and chasing (dust, noise, hidden cables).
Before: the CEWP isolates, locks and tests dead the circuits in the wall area; check for old cables and pipes; wear glasses, dust mask, ear protection and gloves; check the drill cable and the supply protection; mark the hole depth.
While: Do hold firmly with both hands and keep the bit straight. Do not drill into a column, beam or reinforcement; do not force the drill; do not carry it by the cable.
After: switch off and unplug; let the bit cool; clean dust (wet wipe, not blowing); coil the cable; store dry; report damage.
Emergency: if you hit a cable or pipe, stop and unplug; keep away from the wall; call the CEWP; for a shock or serious injury call 112.
| No. | Part | What it does | Safety rule |
|---|---|---|---|
| 1 | Display | Shows the reading | Blank or odd? Stop and tell the CEWP |
| 2 | Rotary range dial | Chooses what is measured, such as volts or ohms | Set the dial before touching anything |
| 3 | HOLD button (yellow) | Freezes the reading on the display | Does not make a live test safe |
| 4 | Push buttons (RANGE, MAX/MIN, REL, Hz%) | Choose extra functions named on each key | Learn each key with the CEWP before using it |
| 5 | Input jacks (including COM) | The sockets where the test leads plug in; the black lead goes in COM | A wrong jack can blow the fuse or hurt you |
| 6 | Tilt stand | Props the meter up on a bench | Use it on a dry, steady surface |
| 7 | Rubber case | Protects the meter against knocks | A cracked case or lead: do not use the meter |
| No. | Part | What it does | Safety rule |
|---|---|---|---|
| 1 | Display | Shows the reading | Blank or odd? Stop and tell the CEWP |
| 2 | Range dial | Chooses volts, ohms or continuity | Set the dial before touching anything |
| 3 | COM jack | Black lead goes here | Always in COM |
| 4 | V and ohm jack | Red lead for voltage and resistance | Wrong jack can blow the fuse or hurt you |
| 5 | 10 A jack | Red lead for high current | Never use for voltage |
| 6 | Red lead | Test probe | Check insulation; keep fingers behind the guard |
| 7 | Black lead | Test probe | As above |
| 8 | HOLD button | Freezes the reading | Does not make a live test safe |
| 9 | CAT rating mark | The category the meter is safe in | Use only where the rating allows |
(A multimeter is not the tool that proves a circuit dead. The CEWP decides when it may be used.)
Materials
- Cables, conduit and trunking, boxes, plugs and sockets, switches, lamp holders, breakers, screws and saddles, tape, glands.
- Only buy materials with a standard number. If you are not sure, ask the GSA.
- Cable prices change often. As an example, a 100-yard coil of 2.5 mm single-core cable was advertised at about GH¢470 to GH¢480 on a classifieds site. That is an advertised example price, not a market survey.
Cheap cable is not cheap. Ghana's Standards Authority warns about substandard cables. The Energy Commission also says substandard material vendors still operate. Buy from known shops and check the marks.
Tool tour and spot test
- Name each hand tool on the table and say its use and its care.
- Check three screwdrivers and two pliers for cracked or worn insulation; set aside the bad ones.
- Strip 100 mm of insulation from new, unconnected sample cable without nicking the copper; measure the copper with a ruler.
- Read the labels on three cables and say which are approved.
- Do the magnet test on a stripped, unconnected sample, with your instructor.
- Tidy and count the tools back into the box.
Price check
Visit a hardware shop. Write the price of a 100-yard coil of 1.5 mm cable, a socket, a switch and a breaker, and whether they carry a standard number. Do not buy.
Check yourself
- Does an insulated handle make live work safe?
- Can a non-contact volt stick prove a circuit is dead?
- What should be printed on good cable?
Unit 5 · Assist on an installation
The helper who arrives on time, carries well, listens, keeps the site tidy and never touches live parts is the helper the electrician asks for again.
Competency standard
| Learning outcome | Performance criteria — the trainee… |
|---|---|
| 5.1 Read a plan | counts points and routes from a simple plan |
| 5.2 Prepare the site | marks positions, protects floors and fixes boxes as told |
| 5.3 Install conduit and pull cable on dead circuits | cuts and fixes conduit; draws unconnected cable as directed |
| 5.4 Work with the CEWP | follows instructions; hands tools; keeps the site safe |
Range. A small house or one room; dead circuits; the CEWP present. Evidence. Observation; the CEWP's comment; logbook.
Ask a qualified expert. An Energy Commission-certified electrician must connect, test and certify every installation. Trainees do preparation only and never connect to a supply. Ask the electrician before you do any task that you are unsure about. In the end, the CEWP signs the work, not you.
Why the helper matters
On a real job the CEWP does the connecting and testing. The helper marks, drills, fixes, carries, cleans, passes tools and watches. That is how you learn.
The sequence of a small job
| Step | Who | Note |
|---|---|---|
| 1 Plan and agree the points | CEWP and client | Number of lights, sockets, switches, AC points |
| 2 Mark positions on the wall | Helper under the CEWP | Heights from the CEWP |
| 3 Chase or fix conduit; fix boxes | Helper | Dust mask; check no old live cable in the wall |
| 4 Draw cable through | Helper, CEWP present | Supply off and locked, cable not connected to anything |
| 5 Connect | CEWP only | |
| 6 Test and inspect | CEWP and the inspector | |
| 7 Certificate and meter | CEWP, inspector, then ECG | ECG needs the stamped forms from the certified electrician and inspector; the customer pays the electrician but not the inspector |
Existing cables in old walls. If you cut a wall in an old house you may hit an old live cable. Before any cutting, the CEWP isolates, locks and tests the circuits in that area. Look for signs of cable runs and ask.
Tools and items for this unit
| Item | What it is and what it does | When you use it | Size or type | Also called | Helper status |
|---|---|---|---|---|---|
| Saddle | A plastic or metal clip that holds conduit or cable to the wall | Every 0.5 m to 1 m on runs (the CEWP sets spacing) | Matches conduit size | pipe clip, conduit clip | You may fix it |
| Conduit coupler and bend | A joint to join two lengths; a curve for a corner | At joins and corners | Same size as the conduit | conduit joiner | You may use it |
| Grommet | A rubber or plastic ring that protects cable where it passes through a hole | In metal boxes | Fits the knockout | rubber bush | You may fit it |
| Knockout | A thin circle in a box that you press out to let cable in | When entering a box | Plastic or metal boxes | blank, punch-out | You may open it |
| Cable clip | A small nail-fixed clip that holds flat cable | Surface runs of twin-and-earth | 6 to 10 mm | nail clip, flat cable clip | You may fix it |
| Cable gland | A fitting that grips cable entering a box or an outdoor fitting | Outdoor and armoured cable | By cable size | cord grip, gland | CEWP only |
| Dust sheet | A cloth cover for floors and furniture | Before any chasing | Large | drop cloth | You may use it |
| Dust mask | A mask that stops dust entering the lungs | Chasing, drilling, cutting | FFP2 type is a good choice (international rating, check the pack) | respirator, face mask | You must wear it |
Never cut into the structure. Chasing is for plaster and blockwork only. Do not cut a column, a beam, a slab or the steel bars inside. A cut in a structural member can weaken the building. The plan for chases and conduit routes must be agreed with the structural drawings before concrete is cast. Ask a qualified expert: a GhIE-registered engineer, a licensed architect or the District Assembly.
SAFETY PROTOCOL: pulling cable and preparing walls and ceilings (hazardous task, dead circuits only).
Before: CEWP present; area isolated, locked and tested dead; PPE; ladder checked; chase lines agreed with the structural drawings; dust sheets down.
While: Do keep cable unconnected; do work in pairs in ceilings; do not walk on ceiling boards, use a bare lamp in a ceiling void or cut anything structural.
After: switch nothing on; remove tools and offcuts; tape ends; tell the CEWP what you did.
Emergency: if you feel a shock or smell burning, stop, move away, tell the CEWP, call 112 for an injury, and let the CEWP isolate.
Plan reading
On the plan, each light is a circle with a cross, each socket a small half-circle, each switch a small square or arrow. The key on the plan tells you. Count them: the number of points tells the CEWP how many circuits and how much cable to buy.
Conduit and boxes
- Conduit protects the cable in the wall and ceiling. Cut square with a hacksaw and file the burrs so the cable skin is not cut.
- Fix with saddles at even spaces, and keep bends gentle.
- Fix boxes level and true; use the spirit level.
Count the points
A two-room plan shows: Room A, 2 lights, 3 sockets, 1 switch; Room B, 1 light, 2 sockets, 1 switch. (1) How many light points, socket points and switch points? (2) If the CEWP says one lighting circuit and one socket circuit, what goes on each? (3) If you must buy 15 m of cable for each light point, how much for all lights? (Example figures.)
Prepare a room on the dead board or a training wall
- With the board dead and locked, read the plan together and count the points.
- Mark the positions of two lights, two sockets and one switch, using the heights the instructor gives you.
- Fix three back boxes level with the spirit level.
- Cut and fix two lengths of conduit between boxes; file the ends.
- Draw an unconnected sample cable through one length, with the instructor present.
- Tidy up and count the tools.
- The instructor checks and signs your logbook.
Draw your room
Draw a plan of one room at home with the places you would want lights, sockets and a switch. Count the points.
Check yourself
- Who connects the cables to the supply?
- What must be done to a wall area before cutting it in an old house?
- What does ECG need before it will fit a meter?
Unit 6 · Checks, simple faults and when to call the electrician
Most electrical fires give warnings first. A helper who notices a warm plug or a burning smell may save a house.
Competency standard
| Learning outcome | Performance criteria — the trainee… |
|---|---|
| 6.1 Spot warning signs | names at least six signs of a wiring problem |
| 6.2 React safely | switches off at the breaker if safe, keeps others away and calls the electrician |
| 6.3 Give simple advice | tells a household how to avoid overloading |
| 6.4 Report | records and reports a fault clearly |
Range. Visual signs only; no testing of live circuits. Evidence. Oral scenarios; a short fault report.
Ask a qualified expert. Every wiring fault must be investigated by an Energy Commission-certified electrician. If there is smoke, fire or a shock, call 112. If someone is hurt, see a doctor or nurse. Do not try to repair live wiring.
Warning signs
- A plug, socket or cable that feels hot or smells of burning.
- A socket that is cracked, loose, scorched or has a brown mark.
- Flickering lights that you did not cause.
- A breaker that trips again and again.
- A buzzing or crackling sound.
- Bare wire or cable with damaged insulation.
- An extension lead with many appliances plugged in.
- Water near sockets, switches or the consumer unit.
Faulty wiring, overloaded circuits and illegal connections are named among causes of fires in Ghana.
What to do
- Stay calm. Keep children and others away.
- If it is safe and your hands and floor are dry, switch off the breaker for that area. If you cannot reach it safely, do not.
- If there is smoke or flame, leave the building and call 112. Do not use water on an electrical fire while the supply may be on.
- Do not touch the damaged part.
- Call a certified electrician. Write what you saw, when, and what was running.
How to avoid overload
- Do not plug several heavy appliances (iron, kettle, heater) into one extension lead.
- Use leads that carry the appliance's watts; check the label (Unit 2).
- Keep cables out of water and away from heat.
- Unplug appliances you are not using.
- Buy appliances with the Energy Commission's yellow label, because those that lack it tend to use a lot of electricity.
From the field: the fridge and the low voltage
The moment. In many houses the fridge is left on to keep food.
The problem. When the supply drops, the fridge keeps trying to start and in the end it is damaged.
The cause. Low supply voltage strains the fridge motor.
What was done. Many people now use a power stabiliser.
The lesson. A cheap protector costs less than a new fridge.
Next time. 1. Fit a stabiliser or a fridge guard. 2. Ask a qualified electrician which one suits the appliance. 3. [[FLAG: author to confirm: the type most used]]
Told by De-Graft Afful, from his own site experience.
Technical note (international, labelled). The harm comes from low voltage, not low current: a compressor motor draws more current and runs hot when voltage is low, and a compressor that restarts straight after a cut can be damaged, so it needs a delay of a few minutes. A voltage stabiliser steadies a drifting supply and often adds the delay; a fridge guard (time-delay protector) mainly cuts off outside a safe range and restores after a delay, and does not correct a weak supply. A fridge needs low-voltage cut-off and a time delay. Vendor pages are not independent tests: follow the fridge maker's advice. Ask a qualified expert: an Energy Commission-certified electrician for the installation; a trained refrigeration technician for the fridge.
Three simple charts for a household
Start at the top and follow the answer. Stop and call the CEWP at any "call" box. These are for the household's first actions, not for repair.
Chart 1: A socket or plug is hot or smells of burning
- Is there smoke or flame? Yes: leave, call 112. No: go to 2.
- Can you reach the breaker for that area safely with dry hands and a dry floor? Yes: switch it off. No: stay away, call the CEWP.
- Unplug nothing until the supply is off. Then unplug the appliance.
- Do not use the socket again. Call the CEWP.
Chart 2: A breaker trips
- Did it trip when you switched on one appliance? Yes: unplug that appliance; switch the breaker on once. If it trips again with nothing plugged in, call the CEWP.
- Does it trip again with the appliance plugged in? The appliance may be faulty or the circuit is overloaded: leave it unplugged, call the CEWP.
- Does it trip again and again, with different appliances? Call the CEWP: do not hold it on.
Chart 3: A tingle or shock from a metal part
- Do not touch it again. Switch off at the breaker if it is safe.
- Keep everyone away. Call the CEWP.
- If anyone was shocked, they must see a doctor or nurse; call 112 if they are unwell.
Tools and items for this unit
| Item | What it is and what it does | When you use it | Size or type | Also called | Helper status |
|---|---|---|---|---|---|
| Smoke alarm | A small device that sounds when it detects smoke | In halls and near bedrooms | Battery type; test weekly | smoke detector | You may fit and test |
| Fire extinguisher | A cylinder for putting out small fires; the type for electrical fires is set by the fire service | Near the exit | The Ghana National Fire Service advises which type | fire fighter, extinguisher | Know where it is; train first |
| Extension lead | A flexible cable with a plug and sockets | Short-term use only | Rated in amps; check the label | extension cord, trailing socket, extension board | You may use it within its rating |
| Multi-plug adaptor | A block that puts several plugs into one socket | Avoid with heavy loads | Total load must not exceed the plug fuse | multiway adaptor, power strip | Do not overload |
| Plug fuse | A small fuse inside a 13 A plug that protects the lead; usually 3 A for small appliances and 13 A for heavy ones (international rule of thumb, not verified for Ghana) | In the plug | 3 A or 13 A | cartridge fuse | CEWP or electrician chooses |
| Voltage stabiliser | A device that raises or lowers a changing supply voltage to a steady level | For sensitive loads, as the CEWP advises | Rated in VA or watts | AVR, voltage regulator, stabilizer | Do not open |
SAFETY PROTOCOL: a hot socket, a burning smell or an electrical fire (household emergency).
Before (prevention): no overloaded leads; smoke alarm tested; escape route clear; extinguisher location known; electrician's name displayed.
While: Do switch off at the breaker only if you can reach it safely with dry hands; do leave the building if there is smoke; do keep children away. Do not use water; do not touch a damaged plug or cable.
After: keep the socket out of use; call the CEWP; write a short report (Unit 6 practical).
Emergency: call 112 for fire or injury; give shock first aid as in Unit 1; the fire service says which extinguisher type is correct for electrical fires.
The test button
Some consumer units have a protective device with a TEST button. The maker's leaflet says how often to press it. Ask the certified electrician what your device does and how to use the test button. Do not open the cover.
Spot the problem
A trainer shows 8 photographs or describes 8 scenes of a house. For each, say the warning sign and the first action.
Fault report
- Your trainer sets up a dead training board with three faults visible (a cracked socket, a burnt label, a loose cable clip). The board is not connected to anything.
- Walk round it and write each fault.
- For each, write the action: stay away, switch off at the breaker, call the certified electrician.
- Write a short report: place, time, what you saw, the action, who was told.
- Read your report aloud to the class.
Household safety talk
Give a two-minute talk to your family on avoiding overload and the signs of danger. Ask them to write one thing they will change.
Check yourself
- Give three warning signs of a wiring fault.
- What should you do first if there is smoke?
- Why not use water on an electrical fire while the supply may be on?
Unit 7 · Find work and start your road
The best way to learn electrical work is beside a good electrician. The best way to find that electrician is to be useful, reliable and honest.
Competency standard
| Learning outcome | Performance criteria — the trainee… |
|---|---|
| 7.1 Plan your route | names the steps from helper to certified electrician |
| 7.2 Find work | lists three places to find helper or sales work |
| 7.3 Market yourself | makes a simple profile and gets a first referral |
| 7.4 Plan costs | records pay and costs for a small job |
Range. Helper, apprentice and small-seller work. Evidence. Route plan; profile; records.
Ask a qualified expert. This is general information, not legal advice. Ask a qualified lawyer, the Energy Commission or the Assembly before you act on any licence or registration matter. For tax, check with GRA or a qualified accountant. For any wiring job, work with an Energy Commission-certified electrician.
Your route
- Finish this module and Level 2.
- Get a master electrician (a CEWP) to take you as an apprentice and ask them to register you with the Energy Commission.
- Learn on real jobs under supervision.
- Prepare for the Energy Commission examination (Domestic is the common first category; ask the Commission for the current syllabus and fees; not verified here).
- Become a CEWP, and later a registered contractor if you wish (the Commission registers electrical contractors; the steps were not found online, so ask).
Work you can do now
| Work | Notes |
|---|---|
| Helper to a certified electrician | Carry, mark, drill, fix, clean, count materials |
| Site cleaner and material runner | Collect from shops; check marks and prices |
| Selling approved accessories | Sellers must not store or sell non-compliant cable or accessories; ask the Energy Commission or the GSA about any registration |
| Energy advice | Tell households about yellow-label appliances and safe use |
| Records and customer care | Quotes, receipts, appointments, follow-up |
Do not do "small wiring" on the side. It feels harmless to change a socket for a neighbour, but it is illegal work, and if there is a fire, you are responsible. Only the certified electrician does wiring.
Tools and items for this unit
| Item | What it is and what it does | When you use it | Size or type | Also called | Helper status |
|---|---|---|---|---|---|
| Phone with WhatsApp Business | A free business profile on a phone | Greeting message, catalogue, referrals | Any smartphone | - | You may use it |
| Job record book | An exercise book for date, customer, work, pay and cost | After every job | A4 or A5, hard cover | job book | You may use it |
| Receipt book | Numbered carbon-copy receipts | When you sell or are paid | 50 sets | receipt pad | You may use it |
| Portfolio photos | Pictures of tidy work done under your electrician | When asking for work | On the phone; permission needed | work gallery | You may use them |
Where to work
- Areas with new buildings and renovations, near hardware shops and building supply, and around estates under construction.
- Ask the Ghana Enterprises Agency about the nearest Business Advisory Centre (Takoradi, Shama, Effia-Kwesimintsim, Mpohor and Ahanta West have them).
- Ask hardware shops which electricians they trust; shops often give referrals.
Market yourself
- WhatsApp Business: a clear photo, your name, "electrician's helper in training", the services you do, and a polite greeting message.
- Google Business Profile: list your name and area when you work for yourself in future.
- A portfolio: photographs of tidy work done under your electrician (with permission from the customer and the electrician), cables labelled, boxes level.
- Referrals: ask each happy customer to tell two people.
- Honesty: never say you are a certified electrician until you are one. Show the certificate when you have it.
Money: a small job record
Record every job: date, customer, what you did, hours, the pay, money spent and money left. This habit is the start of bookkeeping (see the hub's Money Skills Level 2).
Helper's week
Example figures. You work as a helper 5 days at GH¢80 a day (example). You spend GH¢20 on transport and GH¢15 on lunch each day. (1) What do you earn in the week? (2) What do you spend? (3) What is left? (4) If you save a quarter of what is left, how much is that?
Accessibility
Ghana's Disability Act requires accessible public places and bans job discrimination. The Assemblies' disability fund rose to 5% in 2026, aimed at skills, devices and capital. Work at heights and in tight ceilings is not suitable for everyone. Planning drawings, point counts, estimating, customer care, stores, records and telephone sales are workable for many people with disabilities. Adjustments that help include seated work benches, clear written task cards, good lighting, a work buddy and agreed hand signals for deaf trainees.
Your route plan and profile
- Write your route in five steps from today to certified electrician, with a target date for each.
- Name the master electrician or shop you will ask for a helper place, and what you will say.
- Write a four-line WhatsApp profile (no claim to be certified).
- Start a job record book from today.
- Present your plan to the class.
Talk to a certified electrician
With the electrician's permission, ask how they started, how they found customers and what they wish they had known. Ask to see their certificate. Write it down.
Check yourself
- What is the first official step to becoming a certified electrician, according to the Energy Commission?
- Can you say you are a certified electrician after this course?
- Name two ways to market yourself honestly.
Glossary
Terms about tools, parts and materials are in Appendix H. This glossary holds the ideas and the law words.
| Term | Meaning |
|---|---|
| Amp (A) | The unit of electric current |
| Arcing | A spark jumping across a gap, which is very hot and starts fires |
| Breaker (MCB) | A switch that trips when a circuit carries too much current |
| Busbar | A metal strip in the consumer unit that carries the supply to the breakers |
| CAT rating | A safety rating on an instrument that says where it may be used safely; higher is safer for bigger supplies |
| CEWP | Certified Electrical Wiring Professional, certified by the Energy Commission |
| CEWI | Certified Electrical Wiring Inspector |
| Circuit | A closed loop from the supply to a load and back |
| Competent / Not Yet Competent | The two possible results of a CBT assessment |
| Conductor | A material, usually copper, that lets current flow |
| Consumer unit | The box with the breakers, often called the fuse box |
| Core | One insulated conductor inside a cable |
| Dead | Switched off, locked out and tested, so that it carries no voltage |
| Diversity | The fact that not every appliance runs at once; the CEWP allows for it under the rules |
| Double insulation (Class II) | An appliance built with two layers of insulation so it needs no earth wire; marked with a square-in-square symbol |
| Earth | The safety path for fault current |
| ECG | Electricity Company of Ghana, the main distribution company in the south |
| Fault current | The very large current that flows when live touches earth or neutral |
| Flex | Flexible cord for appliances |
| GhIE | Ghana Institution of Engineers |
| GSA | Ghana Standards Authority |
| ICC | Installation Completion Certificate |
| IP rating | A code that says how well equipment keeps out dust and water, for example IP44 |
| Isolate | To switch a circuit off at its breaker or main switch |
| kVA | Kilovolt-ampere, a way of rating a supply or generator; close to kilowatts for many house loads |
| kWh | Kilowatt-hour, the unit on the electricity meter |
| L.I. 2008 | The Electrical Wiring Regulations (2011) |
| Live | Carrying voltage |
| Neutral | The return conductor of a circuit |
| Nuisance tripping | A breaker or RCD that trips when nothing is really wrong |
| Overload | More current than the cable or breaker is meant to carry |
| Power factor | A number between 0 and 1 that says how well an appliance uses the current it draws; motors are below 1 |
| Short circuit | A fault where live meets neutral directly, giving a huge current |
| Single phase and three phase | One live supply wire (houses) or three live supply wires (bigger loads) |
| Starting (inrush) current | The big surge when a motor or compressor starts, several times its running current |
| Tracking | A thin carbon line burnt across a dirty or damp surface by leaking current |
| Volt (V) | The unit of electrical push |
| Voltage drop | The voltage lost along a cable because of its resistance |
| Watt (W) | The unit of power |
Logbook
Copy these pages into an exercise book. Your logbook is part of your assessment evidence.
- Unit 1: lock-out drills; safety checks
- Unit 2: appliance table; calculations
- Unit 3: board drawings; cable label readings; faulty parts list
- Unit 4: tool tour; stripped sample; price check
- Unit 5: room preparation; point counts; helper log
- Unit 6: fault report; household talk
- Unit 7: route plan; profile; job records
- Appendices A to H: used at least once (units sum, label reading, bad-cable spot test, checklists)
- Every homework, dated
Self-check quiz
- Who may legally wire a house in Ghana?
- What are the three steps of the golden rule before work on a circuit?
- Why is a switched-off breaker not proof that a circuit is dead?
- What voltage and frequency does a Ghanaian house use?
- A 2,000 W heater runs for 2 hours. How many kWh?
- Why does a metal-cased appliance have an earth wire?
- Name two signs of a substandard cable.
- What document do you need to get a personal meter?
- What is the first thing to do for a person stuck to a live wire?
- Name three warning signs of a wiring fault.
- Can a helper connect a cable to the supply?
- Why must you never say you are certified until you are?
Appendix A · Units, formulas and bill maths
One page to keep in your tool bag. Every number below is either a standard physics formula or an example, and every worked answer was checked by script.
Ask a qualified expert. These formulas teach ideas and bill sums. The sizes of cables, breakers and circuits are decided by an Energy Commission-certified electrician (CEWP) under L.I. 2008. This is general information, not legal advice.
Formulas
| What you want | Formula | Units |
|---|---|---|
| Current from power | amps = watts ÷ volts | A = W ÷ V |
| Power from voltage and current | watts = volts × amps | W = V × A |
| Ohm's law | volts = amps × ohms | V = I × R |
| Energy | kWh = kilowatts × hours | kWh = (W ÷ 1,000) × h |
| Cost | cost = kWh × tariff per kWh | GH¢ |
| Current for motors and air conditioners | amps = watts ÷ (volts × power factor) | the label may give amps directly |
| Heat in a cable | watts = current² × resistance | W = I² × R |
(Standard physics formulas. The power factor of motors is below 1, so their amps are higher than watts ÷ volts.)
Conversions
| From | To |
|---|---|
| 1 kW | 1,000 W |
| 1 A | 1,000 mA |
| 1 MΩ (megohm) | 1,000,000 Ω (ohms) |
| 1 hp (horsepower, mechanical) | about 746 W of shaft power; the electrical input is higher |
| 100 yards of cable | 91.4 m |
| 1 yard | 0.9144 m |
Worked examples (example tariff GH¢2 per kWh; ask ECG for the real tariff)
| # | Question | Working | Answer |
|---|---|---|---|
| 1 | A 60 W fan runs 10 hours a day for 30 days. Monthly kWh and cost? | 0.06 × 10 × 30 = 18 kWh; 18 × 2 | 18 kWh, GH¢36.00 |
| 2 | A fridge labelled 150 W runs about 40% of the time (example). Monthly cost? | 0.15 × 24 × 0.4 × 30 = 43.2 kWh; × 2 | 43.2 kWh, GH¢86.40 |
| 3 | A 1,800 W air conditioner runs 8 hours a day for 30 days. | 1.8 × 8 × 30 = 432 kWh; × 2 | 432 kWh, GH¢864.00 |
| 4 | A 3,000 W water heater on 230 V draws how many amps? | 3,000 ÷ 230 | 13.0 A |
| 5 | A heater element of 50 ohms on 230 V: amps and watts? | 230 ÷ 50 = 4.6 A; 230 × 4.6 | 4.6 A, 1,058 W |
| 6 | The most a 13 A plug carries at 230 V? | 13 × 230 | 2,990 W |
| 7 | A 2,000 W kettle for 15 minutes in one day. Energy and cost? | 2 × 0.25 = 0.5 kWh; × 2 | 0.5 kWh, GH¢1.00 |
| 8 | A prepaid purchase of GH¢100 at the example tariff buys how many kWh (ignoring fees)? | 100 ÷ 2 | 50 kWh |
The air conditioner in row 3 costs ten times the fan in row 1 for the same month. That is why Appendix H of Level 2 treats air conditioners as their own circuits.
Appendix B · Symbols and colours card
Plans are read with a key. Learn the common symbols, then always read the key on the actual plan.
Ask a qualified expert. Symbols and colours help you read a plan. They do not authorise you to wire. Colours in Ghana must be confirmed with an Energy Commission-certified electrician and GS 1009.
Common wiring-plan symbols (as usually drawn; the key on your plan rules)
| Symbol, described | Meaning |
|---|---|
| Circle with a cross | A ceiling light point |
| Circle with a cross and a short bar | A wall light |
| Small square, or a short line with a hook | A switch (one-way); a figure "2" beside it means two-way |
| Half circle on a line | A socket outlet |
| Half circle with a cross or a second half circle | A double socket |
| Square with a diagonal | A distribution board (consumer unit) |
| Small circle with a line to earth bars | An earth point |
| Rectangle with the letters AC | An air conditioner point |
| Rectangle with the letters WH | A water heater point |
(Described from common international practice for plans, IEC 60617 style; not copied from the standard. Your plan's key rules.)
Cable colours: international rule, Ghana to be checked
| Conductor | International harmonised colour (single-phase) | Older colour found in old houses |
|---|---|---|
| Live (line) | Brown | Red |
| Neutral | Blue | Black |
| Earth (protective) | Green-and-yellow | Green, or bare with a sleeve |
| Three-phase lives | Brown, black, grey | Red, yellow, blue |
(International practice, not verified in a source read for this book. Ghana's colour rule and the date it changed: to be checked in GS 1009 or with the Energy Commission. An Energy Commission official was reported to say new colours differ from old red, blue, yellow and black; I could not read the report: not verified.)
Rules that never change. Green-and-yellow is for earth only, never for any other job. A house may have old and new colours together: tell the CEWP, and label the wires. Never trust a colour. Test the conductors with the CEWP.
Appendix C · The Ghana law card
Who may wire, what paper you need, what the penalty is, and how to check an electrician. Read on official and press pages; checked 20 November 2026.
Ask a qualified expert. This is general information about the law, not legal advice. Ask a qualified lawyer, the Energy Commission or the Ghana Standards Authority before you act on any legal, licence or registration matter. The law and the procedures change: re-check at the Energy Commission.
| Question | Answer (with source) |
|---|---|
| Who may do house wiring? | Only an Energy Commission-certified electrician (CEWP) under the Electrical Wiring Regulations, 2011 (L.I. 2008) |
| What happens if I hire an uncertified electrician? | A fine of up to 250 penalty units, up to two years in prison, or both; the supply may be disconnected |
| What paper connects my house? | The Installation Completion Certificate (ICC) |
| How is the ICC issued now? | The Energy Commission launched a mobile app: the electrician enters the wiring details, an inspector approves, and a digital token acts as the certificate; piloted from November 2024; paper certificates were reported no longer accepted for grid connection after June 2025. Ask the Energy Commission whether paper is still accepted today. |
| What did the electricity company say about meters? | ECG will not process a meter application without the stamped forms of the electrician and the inspector; the customer pays the electrician, not the inspector |
| How do I check an electrician? | The Certified Electrician mobile app, the Energy Commission website or CEWPAG |
| Which materials may be sold? | Only cables and accessories that meet GSA standards, under L.I. 2478 (2023); importers register with the Energy Commission and obtain a Certificate of Conformance |
| What are the L.I. 2478 penalties? | 125 to 500 penalty units or 6 to 24 months in prison |
| How often must an old installation be inspected? | First inspection 10 years after first use, then every 3 to 5 years until 30 years in service, then every 2 years. A later article called the regime "in limbo" in practice; ask the Energy Commission. |
| What if an electrician does shoddy work? | The Energy Commission samples inspected work, has withdrawn licences, some for over a year and some permanently, and certified electricians who do shoddy work must correct it |
| Are there approved rates? | The Energy Minister urged certified electricians and inspectors to charge approved rates, lower for rural customers; no figures were found |
| Are the rules changing? | The Energy Commission and the Ghana Standards Authority said in 2023 they planned to review the wiring standards for rooftop solar and smart homes. RCDs and earth inspection chambers were reported to be made mandatory at a certification ceremony; I could not read the full report: not verified. |
Standards in play (labelled)
| Standard | What it is | Status in this book |
|---|---|---|
| L.I. 2008 | Ghana Electrical Wiring Regulations | Law; text not read in full |
| L.I. 2478 | Ghana Electrical Wiring Cables and Accessories Regulations, 2023 | Law; summarised from press |
| GS 1009 | Ghana wiring code of the GSA | Named by the GSA; contents not read |
| GS IEC 60227 | Cable standard example named by the GSA | Named only |
| IEC 60364 and BS 7671 | International wiring rules; the British code follows IEC 60364 | International, used where Ghana text was not found |
Edition and date box
This book was checked on 20 November 2026. The Ghana text of L.I. 2008 and GS 1009 and the ICC procedure may have changed. When you read this book, check the Energy Commission website first.
Appendix D · Parts identification sheet
Walk through a house with this sheet. For every part: name it, say what it does, and know whether a helper may touch it.
Ask a qualified expert. A helper names and prepares; only an Energy Commission-certified electrician (CEWP) connects, changes or opens these parts.
| Part | What it looks like | What it does | Helper status |
|---|---|---|---|
| Service cable | Thick cable from the pole or a line to the house | Brings the supply in | Never touch |
| Meter | A box with a display or dials and a seal | Counts kWh | Never touch |
| Main switch / isolator | A big switch at the start of the board | Disconnects everything | Never touch |
| Consumer unit | A box with a row of switches | Splits the supply into circuits | Never touch |
| MCB | A narrow switch on a rail inside the box | Trips on overload and short circuit | Never touch |
| RCD | A switch with a TEST button, often with a different colour | Trips on leakage to earth | Press TEST only as shown |
| RCBO | A breaker and an RCD in one body | Protects one circuit from overload and leakage | Never touch |
| Switch | A rocker or toggle on the wall | Opens and closes the circuit | Look only |
| Socket | A wall outlet with three rectangular holes (Type G) | Plugs in appliances | Look; report damage |
| Plug | The part on the appliance lead, with a small fuse | Connects the appliance | You may check for cracks |
| Light fitting | A ceiling or wall lamp holder with a lamp | Gives light | Replace lamps only with the circuit off |
| Junction box | A small plastic box in a ceiling or wall | Joins cables | Never open |
| Conduit / trunking | Plastic tube or channel on or in the wall | Protects cable | You may fix on dead jobs |
| Earth rod and clamp | A metal rod in the ground by the wall, with a clamp | Passes fault current into the soil | Look; never remove |
| Earth inspection chamber | A small covered pit over the earth rod | Lets the electrician test the earth | Look only |
Appendix E · Safe isolation and first aid wall card
Print this page and fix it to the workshop wall.
Ask a qualified expert. For any shock, burn or injury see a doctor or nurse; call 112 in an emergency. This card is awareness, not medical treatment or a licence to do electrical work.
Safe isolation (CEWP-led)
- Identify the circuit. 2. Switch off at the breaker. 3. Lock out with your own padlock and tag; keep the key. 4. Prove the tester on a proving unit. 5. Test the circuit. 6. Prove the tester again. 7. Only then work. 8. When finished, tools out, remove the lock yourself, tell the CEWP.
"Off" is not proof. A tripped breaker is not proof. A non-contact detector never proves dead.
Electric shock first aid
- Do not touch the person while they may be in contact with the supply.
- Switch the power off at the breaker or main switch. If you cannot, push them away with a dry wooden stick.
- Call 112.
- Check they are awake and breathing; if you are trained, give first aid while help comes.
- Even if they seem fine, they must see a doctor or nurse.
If a power line is down: stay well back and keep everyone away. Call 112 and the electricity company. Do not go near, even to help. (Good practice from international safety guides; not verified here.)
Do not use water on an electrical fire while the supply may be on. Leave the building.
Appendix F · Spot the bad cable and starter tool kit
A fake cable is cheap on the shelf and expensive in the ceiling.
Ask a qualified expert. Cable sizes and materials are chosen by an Energy Commission-certified electrician; the Ghana Standards Authority tests and approves products. Do not buy or fit unmarked cable.
Spot the bad cable
| Check | Good | Bad |
|---|---|---|
| Printed marks | Brand, size in mm², voltage, a standard number such as GS IEC 60227 | Nothing printed, or only a vague word |
| Coil length | About 100 yards (91.4 m) | Short coil at a full-coil price |
| Copper colour | Bright copper-coloured conductor; not attracted by a magnet | A silvery or grey metal, or a magnet sticks |
| Strands | Neat, even strands of the stated size | Thin, uneven or hairy strands |
| Insulation | Even thickness, smooth, flexible | Thin, hard, cracked or sticky |
| Price | In line with other dealers | Far below others |
The standard number, coil length, magnet test and price checks come from the GSA; the other checks are good practice that a CEWP confirms. The GSA has reported that many sampled cables failed tests: 43 percent in 2024 was seen in a search summary only, and the older 2017 figure of 70 percent of brands is disputed by industry; both are not verified. Do not name brands: ask the GSA for its current list.
Starter tool kit for a helper (in suggested order of purchase)
- Safety glasses. 2. Insulated screwdriver set. 3. Combination pliers. 4. Diagonal cutters. 5. Wire stripper. 6. Tape measure. 7. Spirit level. 8. Knife and PVC tape. 9. Torch or headlamp. 10. Tool bag. (This is a suggested order; ask your CEWP for his own list. No prices are given because none were verified: do a price check at a Takoradi shop and mark it as an example.)
Appendix G · Daily checklists and common mistakes
Good habits are the cheapest safety equipment.
Ask a qualified expert. These checklists support, and never replace, the CEWP's instructions and the lock-out rule.
- Before work: CEWP named and present; supply isolated, locked and tested dead by the CEWP; tag on; PPE on; ladder checked; area clear; plan read; tools counted out.
- During work: keep to the plan; no live parts touched; cables unconnected until the CEWP says; tell the CEWP about anything odd; dust sheets down.
- After work: tools counted back in; offcuts and packing removed; no open boxes with bare ends; lock removed only by its owner; report written.
- Tool count: every tool in the box has a place; broken tools are tagged and removed; insulation on handles checked.
- Site tidy: floors clear, cables not across walkways, waste in a bag, nothing left on ladders.
Twelve common mistakes (international good-practice view, from the notes of this book; the CEWP and De-Graft Afful can add Ghana examples)
| # | Mistake | Why it is dangerous | Fix |
|---|---|---|---|
| 1 | Trusting "the current is off" | It may be live | Prove dead with the CEWP |
| 2 | Cheap or unmarked cable | May overheat | Buy marked cable (Appendix F) |
| 3 | One thin cable for many loads | Heat grows with the square of the current | Separate circuits (Unit 2) |
| 4 | A bigger breaker to stop tripping | Cable cooks before it trips | Report; the CEWP fixes the cause |
| 5 | Snapped-off earth pin | No safety path | Replace the plug |
| 6 | Taping over an RCD or breaker | Removes protection | Never |
| 7 | Cutting walls with no check for old cable | Live cable hit | CEWP isolates and tests the area |
| 8 | Cutting a column or beam for conduit | Weakens the building | Plan with the engineer first |
| 9 | Water near sockets | Shock and short circuit | Keep dry; call the CEWP |
| 10 | Extension lead with heaters and irons | Overload | One heavy load per socket |
| 11 | Loose terminal screws | Heat and arcing | The CEWP tightens and tests |
| 12 | Saying "I am certified" before you are | Illegal and untrue | Say "helper in training" |
Appendix H · Tools, parts and materials glossary
Every tool, part and material in this book, named and defined. Sizes are typical; the maker's data sheet, the Ghana Standards Authority or the CEWP rules. "Also called" gives other common English or trade names. Local names for tools differ from town to town. Use the standard name given here when you order or ask for help, and show the picture.
Ask a qualified expert. Ratings and sizes here are guides for a helper. An Energy Commission-certified electrician chooses and fits the real items under L.I. 2008. Never fit, open or change the parts marked "never touch".
| Name | Type | What it is and does | Size, type or rating | Helper status | Also called |
|---|---|---|---|---|---|
| Armoured cable | Material | Cable with a steel wire layer for outdoors and underground | By load | CEWP only | SWA cable, steel-wire armoured cable |
| Back box | Part | A box in the wall behind a switch or socket | 25, 35, 47 mm deep (typical) | You fix it dead | pattress, wall box, flush box |
| Breaker lock-off | Tool | A clip so a padlock can lock a breaker off | Fits MCBs | You may use it | MCB lock, lockout clip |
| Busbar | Part | A metal strip carrying supply inside the board | Brass or copper | Never touch | bus bar |
| Cable clip | Material | A small clip holding flat cable on a surface | 6 to 10 mm | You may fix | nail clip, flat cable clip |
| Cable gland | Part | A fitting that grips cable at a box | By cable size | CEWP only | cord grip, gland |
| Cable locator | Instrument | Finds hidden cable or metal | Hand-held | CEWP | cable detector, wire tracer |
| Cable ties | Material | Plastic straps | 100 to 200 mm | You may use | zip ties, cable straps |
| Ceiling rose | Part | A round ceiling box that connects a pendant light | 1 per light | CEWP only | pendant rose |
| Circuit breaker (MCB) | Part | A switch that trips on overload and short circuit | 6, 10, 16, 20, 25, 32, 40 A (international preferred values) | Never touch | breaker, MCB, trip switch |
| Claw hammer | Tool | Hammer with nail claw | 450 g | You may use | carpenter hammer |
| Clamp meter | Instrument | Measures current by clamping one conductor | CAT-rated | CEWP | tong tester, clamp ammeter |
| Club hammer | Tool | Heavy hammer for chisel work | 1.5 kg | With permission | lump hammer, sledge |
| Cold chisel (bolster) | Tool | Wide steel chisel for chasing | 100 mm | With permission | bolster, masonry chisel |
| Combination pliers | Tool | Grip, bend and cut | 180 mm | You may use | lineman pliers, side-cutting pliers |
| Conduit (plastic or steel) | Material | A tube holding cable | 16, 20, 25, 32 mm (typical) | You may fix | - |
| Conduit bending spring | Tool | A spring inside conduit to bend without kinking | By conduit size | You may use | bending spring |
| Consumer unit | Part | A box with the breakers | 4 to 12 ways | Never open | fuse box, distribution board, DB |
| Continuity tester | Instrument | Checks a wire is unbroken | Low-ohm | CEWP | low-ohm tester, buzzer tester |
| Crimping tool and lugs | Tool | Squeezes a metal sleeve on a conductor | By cable size | CEWP | lug crimper, crimping pliers |
| Diagonal cutters | Tool | Cut wire flush | 160 mm | You may use | side cutters, flush cutters |
| Dust mask | PPE | Stops dust entering lungs | FFP2 (check pack) | You must wear | respirator, face mask |
| Earth bar | Part | A strip in the board where earth wires meet | Brass | Never touch | ground bar, earth terminal bar |
| Earth clamp | Part | A clamp joining the earth wire to the rod | By rod size | CEWP | ground clamp, rod clamp |
| Earth electrode (rod) | Part | A rod in the ground that passes fault current to soil | Copper-bonded or galvanised steel rod; length and size set by the CEWP | Look only | earth rod, ground rod |
| Earth inspection chamber | Part | A covered pit over the rod for testing | Plastic or concrete | Look only | earth pit, inspection pit |
| Earth tester | Instrument | Measures the resistance of the earth electrode | 3-pole or clamp type | CEWP | earth resistance tester, ground tester |
| Extension lead | Item | Flexible cable with plug and sockets | Rated in amps | Use within rating | extension cord, trailing socket, extension board |
| Fire extinguisher | Safety item | For small fires; type advised by the fire service | Ask GNFS | Know where it is | fire fighter, extinguisher |
| First-aid kit | Safety item | Dressings and gloves | Boxed | You may use | first aid box |
| Fish tape | Tool | Pulls cable through conduit | 10 to 30 m | You may use | draw wire, pull wire, cable puller |
| Flexible cord | Material | Fine-strand cable for appliances | 0.75 to 1.5 mm² (typical) | Do not use as fixed wiring | flex, cord |
| Gloves, boots, glasses, hard hat | PPE | Personal protection | Maker's rating | You must wear | PPE set, safety kit |
| Hacksaw | Tool | Saw for conduit | 24 teeth per inch | You may use | metal saw |
| Hammer drill | Tool | Drill that hammers, for block and concrete | 6, 8, 10 mm bits | With permission | percussion drill, rotary hammer |
| Insulated screwdrivers | Tool | Screwdrivers with plastic coverings | Flat 3 to 6 mm; PH1, PH2 | You may use | electrician screwdriver, VDE screwdriver |
| Insulating tape | Material | Plastic tape that insulates | 19 mm | You may use | PVC tape, electrical tape |
| Insulation tester (megger) | Instrument | Measures insulation resistance | Test voltage set by the CEWP | CEWP | megger, insulation resistance tester, IR tester |
| Isolator | Part | Switch that disconnects the supply | Same rating as the circuit | Never touch | disconnector, main switch, isolating switch |
| Junction box | Part | A small box where cables are joined | Plastic | Fix empty only | JB, joint box |
| Knife | Tool | Short folding knife | Folding | Cut away from you | cable knife |
| Ladder | Tool | Frame for reaching high | Check rungs and feet | Use with a holder | step ladder, steps |
| Lamp holder | Part | The fitting that holds a lamp | Screw or bayonet | Look | bulb holder, lamp socket |
| Lock-out padlock and tag | Safety item | Locks a breaker off and warns others | Own key | You may use | safety lock, lockout lock |
| Meter | Part | Utility instrument that counts kWh | Single-phase | Never touch | kWh meter, energy meter |
| Multimeter | Instrument | Measures volts, ohms and continuity | CAT-rated | CEWP | avometer, multitester, DMM |
| Non-contact detector | Instrument | Beeps near live conductors | Pen type | Warning use only | volt stick, voltage pen, NCV detector |
| Pliers, long-nose | Tool | Thin pliers for tight spots | 160 mm | You may use | - |
| Plug | Part | Connects an appliance to a socket | 13 A Type G, GS IEC 60884 | Check for cracks | 13 A plug, top |
| Plug fuse | Part | A small fuse inside the plug | 3 A or 13 A | CEWP chooses | cartridge fuse |
| Proving unit | Instrument | A known source to check the tester | Pocket size | CEWP | proving stick, proving device |
| RCD | Part | Trips on leakage | 30 mA is usual for people | Press TEST only as shown | earth leakage breaker, residual current breaker, ELCB |
| Saddle | Material | A clip fixing conduit to a wall | By conduit size | You may fix | pipe clip, conduit clip |
| Smoke alarm | Safety item | Sounds when smoke is detected | Battery type | You may fit | smoke detector |
| Socket outlet | Part | Wall outlet for plugs | 13 A Type G | Look; report damage | wall socket, power point, outlet |
| Spirit level | Tool | Shows level | 600 mm | You may use | bubble level |
| Surge protective device | Part | Protects against sudden voltage rises | By CEWP | Never touch | SPD, surge arrester, surge protector |
| Switch | Part | Opens or closes a circuit | 1-way or 2-way | Look | light switch |
| Tape measure | Tool | Rolled steel ruler | 5 m | You may use | measuring tape |
| Trunking | Material | A channel that holds cables | By size | You may fix | raceway, cable trunking |
| Twin-and-earth cable | Material | Flat cable with live, neutral and bare earth | 1.5, 2.5, 4, 6 mm² (typical) | You may carry and draw dead | flat cable, TWE cable, T&E |
| Voltage stabiliser | Item | Steadies a changing supply voltage | By load (VA) | Do not open | AVR, voltage regulator, stabilizer |
| Voltage tester | Instrument | Two-pole tester proving circuits dead | IEC 61243-3 type (international) | CEWP | voltage indicator, two-pole tester, voltage detector |
| Wall plug | Material | A sleeve that holds a screw in masonry | Matches drill size | You may use | rawl plug, anchor |
| Wire stripper | Tool | Removes insulation | Sized to the wire | You may use | cable stripper, stripping pliers |
Index by type
- Tools: breaker lock-off, claw hammer, club hammer, cold chisel, combination pliers, conduit bending spring, crimping tool, diagonal cutters, fish tape, hacksaw, hammer drill, insulated screwdrivers, knife, ladder, long-nose pliers, spirit level, tape measure, wire stripper.
- Instruments: cable locator, clamp meter, continuity tester, earth tester, insulation tester, multimeter, non-contact detector, proving unit, voltage tester.
- Parts: back box, busbar, cable gland, ceiling rose, circuit breaker, consumer unit, earth bar, earth clamp, earth electrode, earth inspection chamber, isolator, junction box, lamp holder, meter, plug, plug fuse, RCD, socket outlet, surge protective device, switch.
- Materials: armoured cable, cable clip, cable ties, conduit, flexible cord, insulating tape, saddle, trunking, twin-and-earth cable, wall plug.
- PPE and safety items: dust mask, extension lead (item), fire extinguisher, first-aid kit, gloves, boots, glasses, hard hat, lock-out padlock and tag, smoke alarm, voltage stabiliser (item).
Further reading and sources
Best next reads: the Energy Commission's electrical wiring pages (the certificate and apprentice rules); the GSA's notices on cables; your instructor's CEWP notes; the manufacturer's leaflet for any consumer unit you work beside.
What this module does not cover: how to wire (the job of a certified electrician), the Energy Commission's examination syllabus, fees and contractor registration steps (not found online), the text of L.I. 2008 and GS 1009 (not freely online; the colour rule and any Ghana limits are marked "to be checked"), cable sizing rules and test limits (Level 2 gives the international method, labelled), solar PV (see the hub's Solar Energy course), generators and appliance repair (see the hub's Appliance and Generator Repair course), and Ghana helper pay rates (not found).
Every source used in this manual is listed, with links, in the Teacher Copy.