About this module
Level 3 is where you stop being the person who paints the wall and become the person who answers for the whole finish.
Who it is for. People who have finished Painting, Decorating and POP Ceilings Level 2, or can show the same skills, and who want to lead a painting gang, act as a finishing foreman, or start a painting and decorating business. Ghana's TVET framework places National Proficiency II below National Certificate I. This module is written at an advanced level, comparable to National Certificate I; that comparison is the author's judgement, not a CTVET ruling.
CTVET status. No CTVET or NTC painting and decorating curriculum was found; a trade test for "interior decoration" exists inside a domestic module of NVTI. The Nigerian NBTE Painting, Decoration and Finishes certificate was used only as a design model. This module is not a CTVET curriculum and carries no accreditation. Ask CTVET and NVTI which standard applies.
Foreign data. Almost all product data in this book come from non-Ghana makers (India, UK, Greece, Tanzania). They are labelled and are typical figures only. The product data sheet (TDS) on the tin or from the dealer always overrides this book.
Prices. Paint prices are seller asking prices seen on Jiji Ghana on 9 October 2026, mostly in Greater Accra, not Takoradi. No published Ghana painting labour rate per square metre was found. Every price, wage and rate in the worked examples is an example unless it names a source. Ask three Takoradi dealers and three clients before you price a real job.
Law status. Ghana's workplace safety and health bill was still being prepared in August 2026 and is not yet law. The Labour Act 2003 still applies.
Bridge from Level 2: what you already know
- Surface preparation on cement, plaster, wood and metal; mist coats and primers
- Emulsion by brush and roller; gloss on wood and metal; reading a coverage figure
- Estimating: net area, coats, litres and waste; a first quote
- Tinting in small steps and keeping a record of the recipe
- Gypsum board ceilings, POP mixing, cornices, graffiato and wallpaper basics
- Faults and fixes: peeling, blistering, efflorescence, chalking, mould
- Ladder safety, lead-safe practice and the rule never to spray two-pack paints at this level
Level 2 gave you the craft. Level 3 turns it into a system you can lead, a quality you can prove, and a business you can run.
How the module works
Each unit has learning outcomes, performance criteria, the range and the evidence your assessor needs. You are judged Competent or Not Yet Competent. About 60% of the time is practical. Every unit ends with a Check yourself of three questions, and has a practical and homework.
Unit 1 · Specification reading, coating systems and surface-failure diagnosis
A paint job is not a colour. It is a system that was written down before the first brush touched the wall. Read the system, then find out why it broke.
Competency standard
| Learning outcome | Performance criteria — the trainee… |
|---|---|
| 1.1 Read a painting specification | finds the surfaces, systems, colours, coats and standards in a finishes schedule or bill of quantities and lists questions to ask |
| 1.2 Read a product data sheet | pulls out solids, coverage, drying, thinning, temperature limits and warnings from a TDS |
| 1.3 Choose a coating system | matches a surface to primer, undercoat and finish, and says why |
| 1.4 Diagnose a failure | works from symptom to cause with tests, and writes a short repair method and report |
Range. Interior and exterior masonry, plaster, board ceilings, wood and metal on a house, shop or small institution in Sekondi-Takoradi. Evidence. Specification query list; TDS summary sheet; system table; failure diagnosis report; oral questions.
Why a Level 3 painter reads the specification
At Level 2 you were told what to paint. At Level 3 you are the person who checks that the instruction can work. A specification (spec) is the written description of what the client or the architect wants: the surfaces, the paint products, the number of coats, the colours and the standard of finish. It often sits in a finishes schedule (a table room by room) or in the bill of quantities (a priced list of items). Many small jobs in Takoradi have no written spec at all. Then you write one and the client signs it. That one page can save you from a long argument later.
What nobody has told you. Most disputes in painting are not about skill. They are about what was promised. If the spec says "two coats of emulsion" and the client expected a "perfect smooth finish", you will lose, even if your work is good. A specification and a signed quote are your protection.
How to read a spec, step by step
Read a finishes schedule
- Take a drawing or schedule. Make a table with one row per room or elevation.
- For each surface write: what is it (block wall, plaster, plasterboard ceiling, timber door, steel gate), where (inside or outside), what finish is asked for (matt, silk, gloss, textured).
- Write the product or system named (brand and product code, or the words "supply by contractor").
- Write the number of coats and who does the primer and filler.
- Write the colour codes. If it says "as selected by client", note a date by which the client must decide.
- Circle anything missing, unclear or in conflict (for example "emulsion on steel", or "exterior finish" with no mention of fungicidal wash).
- Turn the circles into a list of questions and send it in writing (WhatsApp is fine) before you price.
Typical things to look for in a spec:
- Surfaces and condition: new plaster, old painted surface, bare timber, rusted steel, damp wall?
- Areas and exclusions: are ceilings, doors, window frames, gutters, fascia boards included?
- System: primer, undercoat, finish coats, and the product named for each
- Standard of finish: "smooth, even, no visible joints or brush marks in normal daylight" is better than "good quality"
- Access: who provides scaffolding or a tower for high work?
- Protection: floors, glass, fittings
- Programme and working hours: school or shop hours, noise, rain delays
- Warranty or defects period and what it covers
How to read a product data sheet (TDS)
A product data sheet (TDS) is the maker's instruction page for one product. Ask the dealer for it, or photograph the label. It overrides every number in this book. The sheets we read for this book came from India, the UK, Greece and Tanzania, so numbers differ from product to product.
Read these lines, in this order:
- Use: interior or exterior? For masonry, wood or metal? Using the wrong product is the commonest mistake.
- Surface preparation: what must the surface be like? The sheets we read all say the surface must be dry, clean and free of dust, grease and loose paint. One asked for a wall moisture below 4% measured with a meter.
- Primer or sealer to use first.
- Coverage in square metres per litre per coat, and the dry film thickness it is based on.
- Drying times: touch dry and recoat, at a stated temperature and humidity. Example: one UK sheet gives touch dry 1 to 2 hours and recoat 3 to 5 hours at 20 °C and 65% humidity.
- Thinning: how much and with what. Never thin more than the sheet allows.
- Application temperature and weather limits. Examples: not below 10 °C or above 35 °C on one sheet; not if humidity is above 80% during application or drying on another. Akwidaa and Takoradi are often above 80% humidity, so you must plan around this (see Unit 2).
- Safety and disposal: hazard symbols, flash point, solvent, isocyanate or lead warning.
One page is not enough. The label may be short. Always ask the dealer for the full TDS and the safety data sheet (SDS). If the dealer cannot give them, ask why. Write the product batch number on your job sheet.
Coverage, solids and film thickness
Coverage is not a fixed number. It depends on the volume solids (the part of the wet paint that stays on the wall) and the dry film thickness (DFT) you want. One TDS gives a pattern we can check: 8.0 m²/L at 40 microns, 6.4 at 50 and 5.33 at 60. Divide 320 by each thickness and you get the same numbers. So the maker's paint has volume solids of about 32% (320 ÷ 10).
Theoretical coverage (m²/L) = volume solids % × 10 ÷ DFT (microns)
Check with the sheet: 32 × 10 ÷ 40 = 8.0. This is the usual trade formula and it matches that sheet; confirm with the maker for your product. Real walls are rougher, wind and sun dry the paint, and some paint is lost on brushes and in tins. Site coverage is typically 80 to 90% of the theoretical figure. Practical coverage depends on the surface, the method and the weather.
Worked example (example numbers): TDS says volume solids 40% and you want 40 microns. Theoretical = 40 × 10 ÷ 40 = 10 m²/L. At 85% efficiency, practical = 8.5 m²/L. A 120 m² wall with 2 coats needs 120 × 2 ÷ 8.5 = 28.2 litres.
Coating systems: which layers go where
A coating system is the stack of layers: primer (grips the surface and seals it), undercoat or filler coat (builds an even base), and finish coat(s) (colour and protection). Typical trade practice is one primer plus two finish coats; no explicit Ghana standard was verified. New surfaces or dark colours may need more than one coat. Horizontal surfaces like sunshades, parapets and window tops need three or more coats outside because water sits on them.
| Surface | Prepare | Primer | Finish | Watch for |
|---|---|---|---|---|
| New cement plaster, inside | Cure fully; dry; dust off | Mist coat of diluted emulsion or the sealer on the TDS | 2 coats emulsion | Cure time; moisture |
| New plaster, outside | Same; moisture below the TDS limit | Alkali-resisting primer | Masonry paint, 2 coats; 3 on ledges | Efflorescence; rain; humidity |
| Old painted wall | Wash, scrape loose paint, fill, sand | Spot prime bare patches; bonding liquid if chalky | 2 coats | Lead in old paint (Unit 3) |
| Plasterboard ceiling | Joints taped and sanded; dust off | Water-based primer first | 2 coats ceiling emulsion | Joint show-through |
| Bare wood | Sand 120 grit along the grain; knotting | Primer, then undercoat | Gloss, thin coats; sand lightly between | Resin bleed; dark colours in sun |
| Rusted steel | Wire brush flaking rust; degrease | Rust-inhibiting metal primer; ask your dealer | Gloss in thin coats | Rust converter does not work on galvanised, aluminium, copper or stainless |
| Wall with efflorescence | Brush, wipe dry; find the water source | Alkali-resisting primer | Masonry paint | Salts return if water is not stopped |
Red oxide and zinc phosphate primers are used in the trade, but we did not find a source in this research, so the books say "ask the dealer for a rust-inhibiting primer for this metal".
Never mix products from different makers or types in one tin. Do not add white spirit to water-based paint; it is not compatible. Do not copy a varnish thinning schedule to a pigmented gloss. Do not add fungicide to paint or primer; it can void the warranty (forum report, weak source; ask the maker).
Surface-failure diagnosis
A failure is when the paint does not look or do what it should. A good decorator does not just repaint. First find out why. Otherwise the paint fails again, and you pay.
The diagnosis method (six steps).
- Look. Where is it? On one wall or all? South face only? Near a gutter, kitchen or bathroom? Take photos with a ruler or coin for size.
- Describe. Use these words: peeling or flaking (comes off in pieces), blistering (bubbles), chalking (white powder rubs off), efflorescence (white crystals on masonry), mould (black, green or grey growth), cracking, mud cracking, fading, staining.
- Ask history. When was it painted? By whom? What was used? Any leaks, rain, new plaster, fire or cleaning?
- Test. Use a moisture meter if you have one. Scrape and look at the back of a flake: is it clean (adhesion failure to the surface), powdery (dirty surface), or does it show old paint layers (failure between coats)? Rub chalk with a dark cloth. Hold a straight edge for cracks and mark crack ends with a date to see if they grow.
- Decide the cause (use the table).
- Write the fix and the report. Fix the cause first (water, movement, dirt), then repaint.
Common failures (cause, then fix). All from the sources named; they apply to any climate.
| Fault | Likely causes | Fix | Source |
|---|---|---|---|
| Peeling / flaking | Moisture trapped; powdery, dirty or greasy surface; movement; resin in knots | Scrape to a firm edge; spot prime; recoat; strip large areas | Dulux fixing problems |
| Blistering | Moisture; heat on fresh paint in strong sun; resin | Remove moisture source; scrape and sand blisters; treat knots; prime | Dulux search summary |
| Efflorescence | Salts rising through masonry | Stiff brush; dry wipe; alkali-resisting primer; stop the water; let the wall dry (can take weeks) | Dulux fixing problems |
| Chalking | Weathered film or salts | Stiff brush; stabilising primer; repaint | Dulux fixing problems |
| Mould / mildew | Damp; little sun or ventilation | Fungicidal wash with a nylon brush; rinse; dry; repaint with a suitable paint | Dulux fixing problems; Sandtex fungicidal wash |
| Mud cracking | Thick, unthinned coat on a textured surface; matt over silk | Thinned coats | Dulux fixing problems |
| Plaster cracks | Drying shrinkage or building movement | Cut out; remove dust; fill; paint | Dulux fixing problems |
Mould treatment methods vary by maker. One maker asks you to leave the anti-fungus solution on for at least 2 hours. One Indian sheet used diluted bleach, 2 kg to 50 litres of water, left 24 hours and rinsed. Use the method on your product's TDS. Wear rubber gloves and eye protection with any bleach or fungicide.
Damp. Find the source first: a leak, rising damp or a cracked gutter. Paint over damp will blister or peel. A damp-treatment product was advertised on Jiji at GH¢300 per piece in Okponglo; the unit is unclear, so ask the dealer.
What nobody has told you. On the Akwidaa and Takoradi coast, salt, humidity and sun act together. A wall that looks dry in the morning may not be dry. If you cannot prove it is dry, tell the client and note it on the quote. "Painted over damp at client's instruction" is a sentence that protects you.
Worked failure case (example)
A shop owner in Takoradi says: "My 8-month-old exterior paint is peeling on the sea-facing wall, and white powder is on the plaster under the flakes."
- Look: peeling in a band 1 m up from the ground and under the sill.
- Describe: peeling with white powder under: efflorescence.
- History: plaster was painted after 3 weeks. A blocked drain pipe leaks near the wall.
- Test: a meter reading would be high; the back of the flakes is powdery; a damp patch shows near the drain.
- Cause: moisture and salts coming through the wall pushed the paint off. The wall was painted too early. That Indian sheet says new plaster needs about 3 months to cure; Ghana practice was not verified.
- Fix: repair the drain; let the wall dry; brush off flakes and salts; apply alkali-resisting primer; repaint with masonry paint. Report: a one-page note with photos, the cause, the cure and a price. Say clearly that if the drain leaks again, the paint will fail again.
Exercise 1: coverage and a diagnosis
(All numbers are examples.)
- A TDS gives volume solids 36%. You want a dry film of 40 microns. What is the theoretical coverage in m²/L?
- Site efficiency is 85%. What is the practical coverage?
- An exterior wall is 150 m² and needs 2 coats. How many litres at the practical coverage?
- A client says the wood door gloss is blistering on the south face in the afternoon. Name two likely causes and your first test.
- A new plasterboard ceiling shows ghost lines along the joints after painting. What is the likely cause and which step did you probably skip or rush?
Read, choose and diagnose
- Collect two real TDS sheets from a dealer. Fill in a one-page summary for each: use, preparation, coverage, drying, thinning, temperature limits, safety.
- Take a finishes schedule for a four-room house. Mark five questions you would send to the client.
- Make a system table for five surfaces (plaster wall inside, new exterior wall, wooden door, steel gate, ceiling board). Name the primer and finish for each, and tick the TDS lines that support your choice.
- Examine three failure samples. For each follow the six steps and fill in a diagnosis sheet: symptom, cause, test, fix, who pays.
- Write a client report (half a page) for one failure, with photos, plain words and a clear price.
Spot failures at home
Walk round your home or church. Photograph three paint faults. For each, write the name, the likely cause, and what you would do first. Bring them to class.
Check yourself
- What does the formula volume solids × 10 ÷ DFT give you?
- Name two things the TDS says that override this book.
- What must you find and stop before repainting a wall with efflorescence?
Unit 2 · Managing a painting contract
The job is won or lost before the first tin is opened: in the survey, the programme and the paper.
Competency standard
| Learning outcome | Performance criteria — the trainee… |
|---|---|
| 2.1 Survey a site | measures, inspects, photographs and lists risks, access and client needs |
| 2.2 Build a programme | sets out tasks, gang size, days and weather allowances |
| 2.3 Lead a gang | gives tasks, safety briefings and quality checks daily |
| 2.4 Order and control materials | calculates, orders, stores and issues paint without waste |
| 2.5 Write the contract, handle variations and snag | puts the job, price, payments and changes in writing and closes the job |
Range. A house or small commercial job needing 3 to 5 people for 1 to 3 weeks. Evidence. Survey sheet; programme; materials order; contract; daily diary; snag list.
Step 1: The site survey
A site survey is your first and most important visit. Allow an hour or more. Take a tape (or laser measure), a notebook or phone, a torch, a moisture meter if you have one, and a camera.
Survey a job in 10 steps
- Greet the client. Ask what they want and by when. Ask what budget they have in mind.
- Walk the whole property with the client. Take photos of each room and wall before you touch anything.
- Measure each wall (length × height), ceilings, doors, windows, fascia and gutters. Write the sizes in a table by room.
- Decide your deduction rule and write it down: for example, deduct openings larger than 1 m², ignore smaller ones. The US painting trade association's rule is that small openings are not deducted but floor-to-ceiling wide openings are. In Ghana, there is no common rule that we verified, so state your own in the quote.
- Note the surface condition in each room: new, old, chalky, peeling, damp, cracked, greasy. Tap hollow plaster.
- Test moisture at 3 points on any wall that looks damp, and note readings.
- Note access: ladders, scaffold, tower, hoist, roof edges, power lines (stay at least 6 m from overhead lines unless they are dead or insulated; Source: HSE ladders).
- Note hazards: old paint (lead?), asbestos-looking sheets (do not disturb; call for advice), electrics, children, dogs, furniture, plants.
- Ask about water and power supply, where to store tins, hours allowed, parking, toilets, and who will be on site.
- Write the survey sheet the same day, with measurements, photos and questions for the client.
Area formulas you need: wall area = perimeter × height − openings. Rectangular opening = width × height. Gable = ½ × base × height. Circle = 3.14 × radius × radius. Ceiling = length × width. For a room 5 m × 4 m × 2.7 m, perimeter = 2 × (5 + 4) = 18 m; gross wall = 18 × 2.7 = 48.6 m².
Step 2: Estimating litres and tins
The method: net area = gross wall area minus openings; litres = net area × coats ÷ coverage; add waste. Typical site coverage for acrylic interior emulsion is 9 to 11 m²/L per coat, and 80 to 90% of the theoretical figure; add 5 to 8% for trim and brush losses. Always read your TDS first.
Worked example (example numbers, checked by script). House repaint: interior walls 210 m² (1 coat sealer or primer + 2 finish = 3 coats, 10 m²/L), ceilings 95 m² (2 coats, 10 m²/L), exterior walls 180 m² (3 coats at 9 m²/L), allow 10% waste.
| Part | Area m² | Coats | m²/L | Litres | + 10% waste |
|---|---|---|---|---|---|
| Interior walls | 210 | 3 | 10 | 63.0 | |
| Ceilings | 95 | 2 | 10 | 19.0 | |
| Interior total | 82.0 | 90.2 | |||
| Exterior walls | 180 | 3 | 9 | 60.0 | 66.0 |
Interior: 90.2 L = 5 tins of 20 L (100 L, 9.8 L spare, which you keep for touch-ups). Exterior: 66.0 L = 4 tins (80 L). Example tin prices: interior GH¢350, exterior GH¢480. Interior 5 × 350 = 1,750; exterior 4 × 480 = 1,920; paint total GH¢3,670. Buy whole tins in practice. Those listings gave 20 L asking prices from GH¢289 to GH¢750; use your own local quotes.
Step 3: Productivity, labour and the programme
Productivity is how much work one person finishes in a day. It is the key number in your price and your programme. There is no published Ghana figure we could verify, so you must measure your own gang: time a person painting 20 m² of wall and divide.
Worked example (example numbers). Productivity: 40 m² per painter per day per coat (roller work, prepared surfaces). Total coat-areas on the job above: interior walls 210 × 3 = 630; ceilings 95 × 2 = 190; exterior 180 × 3 = 540. Sum = 1,360 m² of coats. Painting time = 1,360 ÷ 40 = 34 painter-days. Add 10 painter-days for preparation, filling, masking and clean-up = 44 painter-days. With a gang of 4, that is 44 ÷ 4 = 11 working days.
A programme is a simple table of what happens on which day, with weather and drying time:
| Day | Task | Gang | Notes |
|---|---|---|---|
| 1 | Protect floors, move furniture, start prep inside | 4 | Check moisture; sand wet if old paint |
| 2 to 3 | Fill cracks; prime interior walls and ceilings | 4 | Let filler dry fully |
| 4 to 6 | Ceilings 2 coats; walls coat 2 | 4 | Recoat times from the TDS |
| 7 | Wall coat 3; touch-ups inside | 4 | Snag walk with client |
| 8 to 11 | Exterior: wash, fungicidal wash, prime, 2 finish coats | 4 | Weather days; early morning start; scaffold booked |
Weather and humidity. Do not paint outside if rain is likely or humidity is above 80%; in hot sun fresh paint can blister. Plan outside work for morning and late afternoon, and add 2 to 3 weather days to the exterior part of any programme (judgement). Seasonal demand in Takoradi (dry season before Christmas and Easter, rainy months slower) is a trade judgement; no Takoradi data was verified.
Step 4: Leading the gang
A gang is a small team led by you or a foreman. A good gang has these roles:
- Foreman: reads the spec, sets up each day, checks quality, talks to the client, keeps the diary
- Preparers: scrape, fill, sand, wash, mask (often the junior members)
- Painters: cut in and roll; the most skilled do trim and gloss
- Helper: mixes filler, carries tins, cleans tools, keeps the store tidy
- Safety and tools person: can be the foreman or a named painter; checks ladders and PPE each morning
Daily routine (15 minutes at 7 a.m.): 1. Say what we do today and who does what. 2. Safety talk: the one hazard of the day. 3. Check PPE, ladders and tools. 4. Show the standard (a finished patch). 5. At end of day: tools washed, tins closed, floors cleaned, diary written.
Quality check as you go. Do not wait for the end. After each room, the foreman looks at the wall in raking daylight (light across the wall), checks edges, corners and trim, and marks touch-ups with low-tack tape. Hold points: stop and get a check before the next layer: after preparation, after primer, after the first finish coat, and before removing masking.
Working in a client's home. Lay dust sheets and mask fittings. Do not take the client's water, toilet or electricity without asking. Keep the foreman's phone for the client. Be on time. Do not bring friends. Do not shout, sing loudly or smoke near paint. Greet the client at the start and end of each day.
Step 5: Ordering and controlling materials
Order paint without waste
- Use the estimate above. Add the sundries: filler, primer, masking tape, sandpaper, dust sheets, brushes, rollers, thinner (if the TDS asks), rags.
- Ask two or three Takoradi dealers for a written quote that names the product, tin size, batch availability, the TDS, delivery cost and return policy for unopened tins.
- For colour, ask for all tins of one colour from the same batch, or tint everything at once. Different batches can differ slightly (trade practice).
- Order a little early: delivery delays and rain days cost money. Do not over-order: unused tinted tins are hard to return.
- On delivery, check the label, product, batch, colour code and seal. Photograph the tins. Store them in the shade, cool and dry, off the ground, lids closed, away from fire and children.
- Issue tins to the gang with a materials issue book: date, product, tins out, tins back, signature. At the end, compare: tins used vs the estimate.
- Keep sealed leftover tins for the client's touch-ups. Write the colour code and date on the lid.
Mixing and tinting on site. Stir the tin well. Use the same batch for a wall. Add colorant in small steps, stir, and test a dry patch because emulsions dry a different shade. Keep a written record of amounts. One universal stainer maker allows up to 10% in emulsion, 6% in acrylics and 3% in silicate or silicone paint, using the minimum that gives colour. Too much colorant harms the paint film; one failure case involved about 14% by volume.
Step 6: The contract and variations
A contract is a written agreement. For a small job it can be one or two pages, signed by both sides, with a copy for each. It must say:
- Names, phone numbers and the site address
- Scope: which surfaces, how many coats, which products, what is not included
- Price (and whether VAT is included; see Unit 5)
- Payment stages (see below)
- Programme: start and end dates, working hours, weather delays
- Client's duties: access, water, power, clearing rooms, choosing colours by a date
- Variations: how extra work will be priced and agreed in writing
- Defects period: how long after handover you fix defects free, and what is not covered (for example damage by the client, new leaks)
- Insurance, safety and damage rules
- How either side can end it and what is paid
Payment stages (example). Contract price GH¢19,400 (the example house above: GH¢40 per m² on 485 m² of surface). Stages: 30% deposit on signing = GH¢5,820; 40% at the mid-point (interior done) = GH¢7,760; 25% at completion = GH¢4,850; 5% retention = GH¢970, paid after a defects period of 3 months (example). Check: 5,820 + 7,760 + 4,850 + 970 = 19,400.
A retention is a small part of the price held back by the client until the defects period ends. It is common in building contracts abroad; whether it is a rule in Ghana for small jobs was not verified, so it is only a term you may agree in your contract. Use the deposit to buy the paint so you do not pay it from your own pocket.
Variations are changes to the job after the contract. Rule: no extra work without a written (or WhatsApp) agreement on price and time. Example: the client adds 40 m² of wall. At the average rate of GH¢40 per m², variation = 40 × 40 = GH¢1,600 and 1 extra day. Keep a variations sheet and ask the client to sign or confirm in writing.
Sign before you start. A verbal "yes, just paint it" is not a contract. If the client will not sign anything, send the scope, the price and the payment dates on WhatsApp, and ask for a reply "I agree".
Step 7: Snagging and closing the job
A snag is a small defect or unfinished item found at the end. Snagging means walking the job with the client, listing every snag, fixing them, and having the client sign that the list is complete.
Snagging in 8 steps
- Choose a time of day with good natural light. Clear the room of tools.
- Walk each room with the client. Hold a torch or use daylight across the wall.
- Check: missed spots, brush or roller marks, drips, sags, paint on glass, floors or fittings, uneven sheen, cracks, gaps at edges, dust nibs, colour match.
- Write each snag on a list: room, wall, what, fix, who, by when. Number them. Photograph each one.
- Fix the items. After each repair take an "after" photo and re-inspect the repair. Do not tick until you have looked again.
- Clean the site: take out rubbish, wash drips, return furniture, sweep (wet-sweep if there was sanding).
- Hand over leftover tins labelled with colour and date, the TDS for each product, and care advice (for example, do not scrub emulsion for 3 to 4 weeks; check with the TDS).
- Get the client to sign the handover note. Issue the final invoice and ask for payment. Keep the file.
What nobody has told you. Most disputes about payment start at handover. A signed snag list and photos taken before and after are worth more than any argument. Keep them for at least six years with your business records.
Exercise 2: survey, litres, gang days and payments
(Example numbers.)
- A room is 5 m × 4 m × 2.7 m. It has 2 doors (0.9 m × 2.1 m each) and 2 windows (1.5 m × 1.2 m each). Find the net wall area.
- Walls get 2 coats at 10 m²/L with 10% waste. How many litres for the walls?
- The ceiling is 5 × 4 m, 2 coats at 10 m²/L, 10% waste. Litres? What is the total for walls and ceiling in litres, and what is the cost of the paint if bought by quantity at GH¢350 per 20 L tin (cost per litre method)? Why should you buy a whole tin in practice?
- A job has 640 m² of coats. A painter does 40 m² per day. Preparation takes 6 painter-days. With 3 painters, how many working days (round up)?
- A contract is GH¢24,000: 30% deposit, 40% mid-job, 25% at completion, 5% retention. Write the four amounts and check that they add up.
Run a mini-contract
- Survey a real room or a mock room. Fill in the survey sheet with measurements, photos and risks.
- Estimate litres, tins and cost; build a programme for a gang of three; write a one-page contract with payment stages and a variation rule.
- Order paint in writing from a dealer (role play), and fill in a materials issue book.
- Lead a 15-minute morning briefing for the gang.
- Hand over: do a snag walk with a partner as client, write the snag list, fix and re-inspect, and sign the handover note.
Quote a real room
Measure one room at home. Write the area, litres, tins and a price range. Ask a dealer for the real price of one 20 L tin and write the date. Compare your estimate with a local painter's quote if you can get one.
Check yourself
- Why must you state your own deduction rule in the quote?
- Name the four hold points in a painting job.
- What must a variation have before work starts?
Unit 3 · Health, safety, lead and solvent control, waste and compliance
Paint hurts slowly: through the lungs, the skin and the blood. The fall from a ladder hurts at once. A good decorator controls both.
Competency standard
| Learning outcome | Performance criteria — the trainee… |
|---|---|
| 3.1 Assess and control job risks | writes a job risk assessment for a painting job and briefs the gang |
| 3.2 Control work at height | uses ladders, towers and hired scaffolds correctly and stops unsafe work |
| 3.3 Control lead, solvent and dust hazards | follows lead-safe, solvent and dust rules and chooses and fits respirators |
| 3.4 Manage waste | stores, dries, collects and disposes of paint waste without harm |
| 3.5 Keep a compliance file | knows the Labour Act duties and the paint and EPA position, and keeps records |
Range. A painting job with a gang of 3 to 6 on a house, shop or small institution. Evidence. Job risk assessment; respirator fit check; lead-safe method statement; waste log; compliance file; oral questions.
The law you work under
Law status in October 2026. Ghana's workplace safety and health bill was still being prepared in August 2026, so it is not yet law. The Labour Act 2003 still applies. It makes the employer responsible for a safe workplace and for providing protective equipment free of charge. An employer must report occupational accidents and diseases as soon as practicable and not later than seven days. Injured workers, including casual workers, are compensated whoever was at fault. We did not verify a Ghana rule specific to painters, scaffolds or ladders, or a Ghana PPE standard for painters. Ask the Labour Department, and copy good foreign practice (labelled below).
A job risk assessment for painting
Before every job, write one page. It is the same idea as the job safety analysis you learned in workplace safety. Use the hierarchy: remove the hazard, replace it with a safer one, isolate it, change the way of working, and only last use PPE. Here is a model for a house repaint:
| Job step | Hazard | How bad? | Control | Who |
|---|---|---|---|---|
| Scrape and sand old paint | Lead dust; dust in eyes and lungs | High if old paint | Wet method; P2 or P3 respirator; sheets; no children in area | Foreman |
| Work on ladder | Fall | High | Correct angle, tie, three points of contact; use a platform for long jobs | Each person |
| Exterior high work | Fall; falling tools | High | Hired scaffold gang; keep people out below | Owner |
| Solvent paint indoors | Vapour; fire | Medium to high | Open windows, fan, A1P2 half-mask, no flames or sparks | Foreman |
| Mixing POP and filler | Dust | Medium | Gloves, dust mask; mix in a bucket outside | Preparer |
| Cleaning brushes, rags | Solvent on skin; fire from rags | Medium | Gloves; rags spread flat outside or in a sealed metal can with water | Helper |
| Hot day | Heat illness | Medium | Water, shade, early start | Foreman |
| Leaving site | Slips, tins left open | Low to medium | Clear, close tins | Everyone |
Work at height
You will meet this on exterior walls, stairwells, gables, ceilings and high walls. Always ask: can this job be done from the ground? Use an extension pole for rollers. If you must climb, follow this order: platform or tower first, ladder last. A ladder is the last choice, for low-risk, short jobs.
Leaning ladder rules (HSE, UK; the best source we read in full).
- Angle: 1 in 4 (about 75 degrees): one metre out for every four metres up
- The ladder extends at least 1 m, or 3 rungs, above the landing or work point
- Do not work off the top three rungs
- Secure it so it cannot slip (tie it at the top, or foot it)
- It rests on a strong place, not on glazing or plastic gutters
- Three points of contact when climbing and, where possible, at the work position
- Stay at least 6 m away from overhead power lines unless they are dead or insulated
- Stepladder: all four feet on firm level ground, locks engaged; do not work on the top three steps unless there is a handhold; tie it if the work pushes sideways
A summary of an older HSE leaflet says a stepladder suits only short, light work of up to about 30 minutes; treat this as a guide.
Scaffolds and towers (foreign, summary only). Guardrails at least 950 mm high; gaps under the guardrail less than 470 mm; toe boards 150 mm; platforms fully planked; firm level base; brakes on tower wheels; never ride a moving tower; towers built only by trained people; the ladder 900 mm above the platform; inspect before each shift. Ghana rules for scaffolds were not verified.
Do not build a scaffold unless you are trained. For exterior high work, hire a scaffold gang and write the cost in your quote. Never use a plank on two buckets. Never paint from a ladder placed on a wet or loose surface. If you cannot make the job safe, stop and tell the client. Their money is not worth your life.
Lead in paint
The Ghana position (verified from a 17 July 2026 EPA report). Ghana's standard sets a lead limit of 90 parts per million (ppm) in paint (GS 180 for solvent-based paint, compulsory from February 2023). The EPA says Ghana has the standard but no law to enforce it; a draft regulation was expected in Parliament before the end of 2026. A 2023 study found 6 of 59 home paints, or 10%, above 90 ppm. The Ghana Standards Authority has closed sellers of substandard paint under the Standards Act, Act 1078.
What this means for you:
- Buy from reputable dealers and ask if the product meets the Ghana lead limit; ask for the SDS or TDS
- Treat old paint as possibly leaded. Paint on older houses, doors, gates and playground equipment may be leaded (foreign guidance; Ghana prevalence not verified)
- Children are most at risk. There is no known safe level of lead exposure
- You cannot see lead. Test kits exist abroad; whether they are sold in Ghana was not verified
Lead-safe method for sanding or scraping old paint (foreign practice, NCHH/WHO-based).
Lead-safe preparation, step by step
- Assume the old paint contains lead. Tell the client and move children, pregnant women and pets out of the area.
- Cover floors and furniture with plastic or heavy sheets, taped at the edges.
- Wet the surface with a spray bottle (mist it). Wet-scrape and wet-sand. Do not dry sand, burn with a flame or heat gun, or pressure-wash.
- Wear a P2 respirator at minimum, P3 if lead is likely, with gloves and washable overalls.
- No dry sweeping. Wet-wipe or use a HEPA vacuum if you have one; collect scrapings and sheets in sealed plastic bags.
- Wash hands and face before eating, drinking or smoking. Do not take dusty work clothes home.
- Change out of work clothes on site; wash them separately.
- Keep a lead log: date, area, method, who, waste bags and where they went.
Solvents, fumes and fire
Solvent-based paints (oil gloss, some primers, thinners) give off vapour that can cause headaches, dizziness and long-term harm. They also catch fire. Rules:
- Read the label and the SDS for every product; keep SDS in a folder on site
- Ventilate: open windows and doors; use a fan that blows out, not in
- No flames, sparks, cigarettes, phones charging near open tins or grinders in a room where solvent vapour is present
- Rags soaked in solvent or oil-based finish can self-heat and catch fire. Spread them flat outside to dry, or keep them in a sealed metal can with water
- Never decant solvents into drinking bottles
- Wash skin with soap and water, not with solvent
- If solvent splashes in an eye, rinse with clean water for at least 15 minutes and go to a clinic (general first-aid practice; follow the SDS)
Isocyanates. Some two-pack polyurethane and single-pack moisture-curing paints contain isocyanates, which can cause asthma. The UK HSE says air-fed breathing apparatus should be used for spray application, and that brush or trowel application is lower risk. At this level: do not spray two-pack paints. Brushing small areas with the right respirator and good ventilation is the most you should do, and only after reading the label and SDS.
Respirators: a programme, not just a mask
Foreign guidance; Ghana-specific rule not verified.
| Task | Minimum | Notes |
|---|---|---|
| Brushing water-based paint in a ventilated room | None needed beyond good air; a dust mask for sanding | Read the SDS |
| Sanding dry filler or paint | P2 | P3 if lead is possible |
| Solvent paint (brush or roller) | Reusable half-mask with A1P2 cartridges | A = organic vapour, P2 = dust |
| Spraying | A2P3 and eye protection | Not for two-pack paints at this level |
| Lead-possible scraping | P3 | Wet method too |
A disposable FFP2 mask with a carbon layer only takes the edge off odours: it does not protect against solvent vapour, and the maker warns not to use it for lead-based paint.
Fit-check and run a respirator register
- Choose the right cartridge for the task (table above). Check the date on the pack.
- No beard or stubble where the mask seals; the mask must seal to the skin.
- Put on the mask. Do a fit check: cover the filter openings with your hands and breathe in; the mask should pull gently onto your face and hold. Breathe out with the exhalation valve covered; no air should leak at the edges.
- Replace cartridges when you smell or taste solvent, or breathing is hard. Write the date started on the cartridge.
- Store the mask in a clean sealed bag away from paint fumes.
- Keep a register: name, mask size, cartridge type, date issued, date replaced, signature.
Dust and POP. Wear gloves and a dust mask whenever you mix POP. POP and filler dust must not be dry-swept. Cement dust and silica need good ventilation and a P2 mask (general). Wash tools in a bucket, not in a drain.
Bleach and fungicide. Wear rubber gloves and eye protection when using bleach solution. Never mix bleach with other chemicals.
Waste: paint, rags, tins and wash water
Legal position. Ghana's Environmental Protection Act 2025 (Act 1124) replaced the Environmental Protection Agency Act 490 and the Hazardous and Electronic Waste Act, Act 917, and the Environmental Protection Authority regulates hazardous waste. Whether household or trade paint waste is listed as hazardous in Ghana, and what permit applies, was not found. Ask the Western Regional EPA office (contact not found in this research) and do not burn paint tins.
Good practice (foreign guidance).
Handle paint waste properly
- Reuse: keep sealed leftover tins for touch-ups, label them, or give them to the client or a church or school.
- Water-based paint (emulsion): small leftovers can be dried out with sawdust, cat litter or paint hardener in a ventilated place for about 3 to 7 days, then put in the normal rubbish. Never pour into drains, rivers, the sea or onto soil.
- Solvent-based paint, thinners and sludge: these are hazardous waste; keep them in a closed, labelled container away from heat and children, and ask the EPA or your dealer where it can be collected.
- Rags soaked with solvent or oil: spread flat to dry outside, or seal in a metal can with water.
- Brushes and rollers: wash water-based paint out in a bucket; let solids settle and dispose of the solids as in step 2; reuse the water for the next wash. Do not tip into a drain.
- Dust and scrapings from old paint: assume lead; wet and bag them (see lead-safe method).
- Empty tins: dry, then give to a recycler or reuse if you know the product; never burn.
- Record every disposal in a waste log: date, type, amount, method, who.
Your compliance file
Keep one folder (paper or phone) for each business and each job:
- Registration papers, TIN, Assembly permit (Unit 5)
- Written safety policy (one page) and the job risk assessment
- Toolbox-talk log: date, topic, who attended
- PPE and respirator register
- Safety data sheets (SDS) for every product and a product list
- Lead log and waste log
- Accident book and a first-aid kit with at least a burn dressing, eye wash bottle, plasters, bandage and gloves
- Workers' written contracts and SSNIT numbers (Unit 5)
- Insurance papers (Unit 5)
Inclusion at work. The Persons with Disability Act 2006 (Act 715) bans job discrimination. A worker with a hearing impairment can do many painting tasks without adaptation, so show the task, use written lists and WhatsApp for instructions. For a worker who cannot climb or stand for long, give them seated or bench tasks (see Unit 5), and never push people into high work.
What nobody has told you. The "slow" hazards (lead, solvents, dust) hurt the lungs, nerves and blood of the whole gang over years, and children at home most of all. Nobody sees it on the day. Your respirator register and lead log are not paperwork: they are the proof that you cared, and your protection if there is a claim.
Exercise 3: risk, ladder and waste
- A ladder is 6 m long. At 1 in 4, how far from the wall should the base be? Why is that distance a guide only?
- You must repaint a 1970s school door frame. List the first four steps you would take before touching the paint.
- A helper wants to tip the leftover 5 L of oil gloss down the drain behind the shop. What do you say, and what do you do instead?
- What respirator and cartridge would you issue for brushing oil gloss indoors? For sanding old paint where lead is possible?
Safe site day
- Write a job risk assessment for a house repaint; brief the class in 5 minutes.
- Set up and inspect a ladder on level ground; practise the 1 in 4 angle; say which tasks you would not do from it.
- Fit-check a half-mask and fill in the register.
- Demonstrate wet-scraping on a test board with a mist bottle and bag the waste.
- Set up a waste log and a spill kit (sand, rags, bags, gloves) for a paint store.
Safety audit
Visit a paint shop or a site where you have permission. Write ten things that are done safely and five that are not, with one fix for each. Bring photos if allowed.
Check yourself
- What is Ghana's lead limit in paint, and what is the enforcement position?
- Why must you not dry sand or burn old paint?
- Where must solvent-soaked rags be kept or dried?
Unit 4 · Specialist work and quality assurance
A specialist finish earns more because it can go wrong in more ways. Control the ways it can go wrong, and you earn the difference.
Competency standard
| Learning outcome | Performance criteria — the trainee… |
|---|---|
| 4.1 Plan and paint a feature wall | chooses colour, sheen and edges, masks and paints a feature wall to a straight, clean standard |
| 4.2 Apply decorative effects | prepares test boards and applies at least two effects after a dealer or trainer demonstration |
| 4.3 Hang wallpaper | measures, marks a plumb line, pastes and hangs a wallpaper wall |
| 4.4 Install and finish a board or POP ceiling | marks, frames, fixes, jointing and finishes a gypsum or POP ceiling section |
| 4.5 Inspect and hand over | runs an inspection plan, tests, records and hands over with a defects period |
Range. A house, shop or small hotel room. Evidence. Test boards; feature wall; wallpaper wall; ceiling mock-up; inspection sheet; handover note.
Feature (accent) walls
A feature wall is one wall painted a stronger colour or a different finish. It looks simple, but small mistakes show: a wobbly edge, a drip, a patchy colour.
A feature wall, step by step
- Agree the colour code and sheen in writing. Paint a test patch about 50 cm square and look at it morning and evening; emulsions dry a different shade.
- Prepare the wall as for any finish: fill, sand, dust off, prime (Unit 1).
- Check with a spirit level or laser line where the colour stops at corners and edges.
- Mask with good tape. Press the edge down firmly with a plastic scraper. For a sharp edge, paint a thin coat of the old colour over the tape edge first, let it dry, then paint the new colour (general trade practice).
- Cut in with a brush, then roll with the right nap. Keep a wet edge: work in 1 m sections.
- Two coats minimum; dark colours may need three. Allow the recoat time on the TDS.
- Remove the tape while the last coat is slightly wet (general trade practice), pulling it back at a low angle. Touch up with a small brush.
- Photograph the wall from the same place at the same time of day for the portfolio.
Decorative effects
A decorative effect is a texture or finish made with special products or tools. Graffiato is a groove effect made by trowel or comb; ready-mixed 20 L tubs are sold in Ghana, one Jiji listing showed GH¢295 for 20 L (listing date not verified). A graffiato dealer exists in Takoradi on BusinessGhana (name and price not captured). Detailed application steps were not found in a source; ask a Takoradi dealer to demonstrate and write the steps as they show you.
Do not learn on a client's wall. For every effect, make a test board (at least 60 cm × 60 cm) on the same surface and let the client approve it in writing before you start. Follow the dealer's TDS for coverage and drying. The wall must be clean, sound and primed.
Common effects (general trade practice; ask your dealer for the product and method):
- Graffiato / textured trowel finish: comb or trowel grooves in a thick ready-mix
- Colour washing, sponging and ragging: glaze or thinned paint applied over a base coat with a sponge or rag
- Stencils and borders: repeating pattern masked or stencilled
- Metallic or pearl paints: need a very smooth base and one direction of rolling
- Two-tone stripes: need exact masking and a spirit level
Record every recipe. Write down product, quantity of any colorant, tools, time and coverage for each test board. You will use it to price the job.
Wallpaper (Level 2 recap with Level 3 checks)
Steps (from the wallpaper guides). Clean, fill and sand glossy spots; prime, or hang lining paper on uneven plaster; mark a plumb line (about 50 cm from the corner for a 53 cm roll); paste the wall with a roller, a couple of centimetres wider than the strip; hang the first drop on the plumb line with extra at top and bottom; smooth from the centre out and do not stretch the paper; match the pattern at each drop; trim with a sharp blade; wipe off paste. Humidity effects on paste and curling in a coastal home were not verified: test one strip in a corner and wait a day before you commit to the whole wall.
Ceilings: gypsum board and POP
Foreign specifications; Ghana practice for Gyproc and local POP bags and dealers in Takoradi was not verified.
Gypsum board ceiling (steps from the foreign specifications).
Board ceiling, step by step
- Mark the ceiling level with a level instrument or water level; fix the wall angle at that level.
- Hang suspension wires at about 600 mm spacing; fit carrying and furring channels crosswise. Keep the ceiling framing independent of the walls and braced.
- Fix boards before the wall finishes. Stagger joints; tight edges.
- Screw with 25 mm drywall screws at a maximum of 300 mm centres for a single layer on metal or wood; resilient furring at a maximum of 600 mm. The 150 mm and 400 mm figures sometimes quoted for ceilings were not verified.
- Joints: a thin coat of compound with a 6 in knife; press the tape in; embed with an 8 in knife; feather beyond; let each coat harden and dry; finish with a 10 in knife on joints and a 6 in on screw heads; sand only when fully dry. Do not use setting compound over drying compound and do not mix old with new. Humidity makes drying slower.
- Control joints about every 15 m on ceilings.
- Cornice: mix the bonding compound as on the bag; spread a bead along the full length; press the cornice into the angle until excess squeezes out; nail temporarily at top and bottom; wipe the excess; when set, remove nails, fill with stopping compound slightly proud, trim and finish flush with a steel trowel.
- Paint: water-based primer first on plasterboard, then 2 coats.
POP (plaster of Paris). POP is calcium sulfate hemihydrate; with water it hardens to dihydrate. The bag instructions override everything below, and the sources were weak:
- Water first, then sprinkle the powder in; stir until smooth and creamy; stir slowly to avoid bubbles
- Mix only what you can use before it sets; fresh POP with no additive sets in about 30 minutes
- A commonly cited ratio is about 2 parts plaster to 1 part water; a thin 1:1 mix is weak and porous and not for ceilings. The ceiling-grade ratio was not verified
- A retarder (vinegar, borax or an industrial product) slows setting; warm water (about 40 °C) shortens working time; old set material in the bucket speeds setting, so clean the tools and the bucket
- Wear gloves and a dust mask
Cove and recessed lights. A cove light or recessed spotlight in a ceiling needs wiring. Only an electrician certified by the Energy Commission may do the wiring. You make the space and the safe cut-out; the electrician fits and tests the cable. Do not close the ceiling before the electrician has finished, and do not cut into a ceiling where a cable runs without checking.
Heavy ornamental POP. Large cast ornaments and chandelier centrepieces can be heavy. Fix them to the structure above, not to the board alone. If you are not sure the roof or slab above can carry the load, ask the site engineer or the builder. You are a finisher, not a structural designer. Check the space above for leaks and moisture before you close it: a wet ceiling void will fail.
Estimating boards (worked example B, checked by script). Ceiling 5 m × 4 m = 20 m². A board 1.2 m × 2.4 m = 2.88 m². 20 ÷ 2.88 = 6.94, so 7 boards before waste; with 10% waste (example) 7.64, so 8 boards. Cornice for a room 5 m × 4 m: perimeter 18 m; with 10% for mitres and waste 19.8 m; in 3 m lengths = 6.6, so 7 lengths. Board sizes sold in Ghana were not verified; ask your dealer.
Quality assurance and handover
Quality assurance (QA) means you plan and record your checks so the quality is not left to luck. Use an inspection and test plan:
| Stage | What to check | How | Record |
|---|---|---|---|
| Before starting | Surface dry, clean, sound; moisture; cure time | Meter; TDS; touch; tape pull on old paint (general practice) | Survey sheet |
| After preparation | Cracks filled, sanded, dust off, bare patches primed | Eye and hand; raking light | Hold-point tick |
| After primer | Even cover, no missed spots | Eye; raking light | Hold-point tick |
| After each coat | Cover, sheen, runs, brush marks, edges | Daylight at an agreed viewing distance | Daily diary |
| Ceilings | Level, joints flush, no ghosting, cornice straight | Straight-edge; raking light; string line | Ceiling sheet |
| Final | Colour match to the approved sample; sheen; touch-ups; cleanliness | Compare with a test patch; client walk | Snag list |
| Handover | Leftover tins, TDS, care advice, defects period | Handover pack | Signed note |
Agree a viewing standard in the contract so the client and you judge the wall the same way, for example "in normal daylight, standing 2 m from the wall" (example; set your own). Without it, an argument over "can I see the joint" has no end.
Wet film thickness and adhesion. A wet film comb is a cheap tool that measures wet paint thickness while you apply it; you can then compare with the TDS. A cross-cut tape test on a cured test patch (cut a small grid, press tape on, pull off) shows whether the paint is gripping. Both are general trade practice; we did not verify them in a source, and whether the tools are sold in Takoradi is not verified.
What nobody has told you. Customers rarely complain on the day. They complain two months later, when the paint peels at the sink or the joint shows in the evening light. The cure is a record: photos, product and batch numbers, moisture readings, dates. Records win disputes. A signed handover note ends the story.
Handover pack. Put in a folder (paper or PDF on WhatsApp): the signed contract and variations; the colour schedule with codes; the product list with TDS; the snag list and handover note; the defects period and what it covers; leftover tins, labelled; care advice; your phone number.
Defects period. A period (for example 3 months, set by you in the contract) during which you fix defects caused by your work free of charge. Write what is not included: new leaks, client damage, tenant knocks. Visit once at the end of the period and photograph the walls.
Exercise 4: ceiling quantities and a QA plan
(Example numbers.) A room is 6 m × 4 m with a board ceiling. Boards are 1.2 m × 2.4 m. Allow 10% waste for boards and for cornice.
- Ceiling area? Boards before waste (round up)? Boards with waste (round up)?
- Cornice: perimeter and length with waste; how many 3 m lengths (round up)?
- Wall angle: if suspension wires are at 600 mm spacing, how many wires in a 6 m run (including both ends)?
- Name three records you would put in the handover pack.
- A client says the new ceiling "shows lines" in the evening. List the first three checks you would make.
Specialist day
- Paint a feature wall on a board or wall section with masked edges; photograph it.
- Make two test boards of different effects after a dealer or trainer demonstration; write the recipe on the back.
- Hang one strip of wallpaper on a plumb line.
- On a low frame, mark, fix and joint one board; mix POP for a small cornice section and fix it.
- Prepare an inspection and test plan for a house; then inspect a partner's work and write a snag list.
- Write a one-page handover note.
Your portfolio
Take before and after photos (same angle, same time of day) of one job, with the area in m² and time taken. Write four lines on the problem, the method, the result and what you would do differently.
Check yourself
- Why make a test board before a decorative effect?
- What must you check before closing a ceiling void?
- Name two items you put in a handover pack.
Unit 5 · Establish a painting and decorating business
A good painter with no paperwork earns a wage. A painter with a registered name, honest books and a signed contract builds a business.
Competency standard
| Learning outcome | Performance criteria — the trainee… |
|---|---|
| 5.1 Choose a business model and legal form | compares models and forms and picks one with reasons |
| 5.2 Register and get permits | lists each registration step, body and fee, and which licences apply |
| 5.3 Plan premises, tools and start-up money | builds a start-up budget and a finance plan |
| 5.4 Hire, supervise and protect people | follows Labour Act basics, SSNIT and PAYE, and arranges insurance |
| 5.5 Market and include | markets honestly and makes the business accessible |
| 5.6 Write a one-page plan and pitch | presents customers, services, money, rules and risks on one page |
Range. A one-to-six-person painting and decorating business (house painting, POP and board ceilings, textured finishes, small repairs) in Sekondi-Takoradi or nearby. Evidence. Registration checklist; start-up budget; one-page business plan and pitch.
Business models for a decorator
- Painting gang: you plus 2 to 4 workers; jobs from homes, landlords, shops and churches
- Subcontractor to builders: price per m² or per room; stage payments; you must be reliable and on time
- Specialist: POP and gypsum ceilings, graffiato and textured finishes, waterproofing coatings
- Supply and service shop: sells paint, brushes, filler and offers a painting service (more money tied up in stock, more records) (general trade models; no Takoradi data on margins or demand was verified)
On Jiji Greater Accra on 9 October 2026 there were 715 painting-service results and 318 POP ceiling ads on the supply side; in Takoradi we found one seller (Riche Monde) with POP and interior decoration ads, "contact for price". This means Takoradi may have room for a decorator who publishes a clear "from GH¢x per m²" price with conditions and shows before-and-after photos; Takoradi demand numbers were not verified.
Choose a legal form
| Form | ORC registration | Key point |
|---|---|---|
| Sole proprietor (business name) | GH¢130; renewal GH¢70 a year | Easy; you carry unlimited liability |
| Partnership | GH¢270; renewal GH¢100 a year; 2 to 20 partners; Form B | Needs a partnership agreement stamped by the Lands Commission |
| Company limited by shares | GH¢585 plus 1% capital duty on stated capital (the page says 1%; check the PDF) | At least 2 directors and a secretary; a consent letter from an ICAG chartered accountant; first annual return 18 months after incorporation |
| Company limited by guarantee | GH¢490 | For NGOs, churches, social enterprises; no profit to members |
| Cooperative | Not registered at ORC; organisational TIN from GRA | Route with the Department of Co-operatives not verified |
Annual returns cost GH¢175 a year; late filing costs GH¢1,000 (1 to 4 years) or GH¢2,000 (5 years or more). For a first business, a sole proprietor or a partnership is simplest. Move to a company when you take large contracts, work for companies that want a limited company, or want to limit your risk.
Registration, step by step
Register your business
- Choose a name and check that nobody else has it. Register it at the Office of the Registrar of Companies (ORC).
- Get your tax identity: your Ghana Card PIN is your individual TIN since 1 April 2021; a company gets a GRA TIN after ORC registration.
- Get the Sekondi-Takoradi Metropolitan Assembly (STMA) business operating permit through the portal tcc.stma.gov.gh. Fees follow the STMA fee-fixing resolution for 2025; we did not read the fee, so the figure in our budget is an example. Renew each year; the deadline is 31 March (confirm with STMA).
- Trade licences: we found no licence specific to painting and decorating, and no FDA or GSA licence for a painting service (not verified). If you sell paint, buy only products that meet the Ghana lead limit; the GSA has closed substandard paint sellers. If you store a lot of paint and thinners in a shop, ask GNFS about a fire certificate: published fees were GH¢250 residential, GH¢500 non-residential and GH¢1,000 commercial, plus processing fees; check today's fees. Ask the Western Regional EPA about any rule for paint waste and for a shop.
- Register your workers with SSNIT when you hire.
- Open a business bank or mobile money account, separate from your personal one.
- Keep photocopies of everything in your compliance file (Unit 3).
Tax: choose the route carefully
Read this before you choose the Modified Taxation Scheme. The Modified Taxation Scheme (MTS) is for residents with business income only who are not VAT-registered. Up to GH¢20,000 turnover you pay fixed instalments; from GH¢20,001 to GH¢750,000 you pay 3% of turnover (or use the Modified Cash Basis). The ceiling was raised from GH¢500,000 to GH¢750,000 by the Income Tax (Amendment) Act 2026, Act 1178; GRA's own page still showed 500,000 on 8 October 2026. Professionals, owners of several businesses or outlets, and partners are excluded.
VAT. From 1 January 2026 the VAT Act 2025 (Act 1151) charges VAT 15% plus NHIL 2.5% plus GETFund levy 2.5%, a 20% effective rate. The registration threshold for goods is GH¢750,000. For services there is no turnover threshold: a taxable person making taxable supplies of services must register within 30 days of starting. A VAT-registered business cannot use the MTS.
Open question for this trade. A painting job is clearly work done for a client, but we could not verify whether GRA treats contract painting and decorating as a taxable "service", or as "works" with some other rule. If it is a service, a painter must register for VAT from day one and cannot use the MTS. The book uses the MTS only for arithmetic practice. Before you pick a route, ask GRA Takoradi in writing, and keep the reply.
Withholding tax. When a client that is a withholding agent pays you, they may withhold tax: goods 3%, works 5%, services 7.5% (for a payee over GH¢2,000 a year). Which rate applies to painting was not verified; ask the client for the basis and for a withholding tax certificate, which you keep as a tax credit record. Companies pay 25% standard income tax, with other rates for some sectors, and annual returns within four months after year-end.
Premises and location
Start from home or a shared store with a phone, a ladder and a small kit. Rent a small store only when you have 3 or more jobs a month. Good locations are near new housing estates, hotels and guesthouses, schools, churches and clinics. In a hot coastal climate exterior paint needs renewing often (general; no local data verified), so keep a list of past clients and call them each year. Store tins in a shaded, cool, dry, lockable place off the ground, away from heat and children (Unit 2); never sleep in the store.
Tools and start-up budget
Hand tools and PPE a gang needs: brushes (3 in, 2 in and 1.5 in synthetic brush sets are sold; one Jiji listing showed GH¢130 for a set, Source: Jiji emulsion), 9 in rollers with extension poles, scrapers and filler knives (6 in and 8 in for tape, 10 in for finishing joints, 6 in for screw heads, Source: Joint compound TDS), sandpaper (120 grit on wood, Source: Wood prep guide), a wire brush for rust, a spirit level or plumb line, a moisture meter, buckets, mixing paddle for a drill, dust sheets and masking tape, ladders, and PPE (half-mask respirators with A1P2 cartridges, goggles, gloves, boots). Hire scaffold towers rather than buy them until you have steady exterior work.
Example start-up budget for a 3-to-4-person gang. All figures are examples (ask three local dealers for real prices):
| Item | GH¢ |
|---|---|
| Business name registration (ORC) | 130 |
| Assembly permit (example; fee not verified) | 400 |
| Two extension ladders | 650 |
| Roller and brush kits | 240 |
| Orbital sander | 450 |
| Mixing drill and paddles | 380 |
| Filler knives and scrapers | 150 |
| Dust sheets and masking tape | 300 |
| Half-mask respirators and cartridges | 1,120 |
| Goggles, gloves, work boots | 400 |
| Moisture meter | 500 |
| Laser measure | 350 |
| Spirit level | 120 |
| Phone data, printing, business cards | 600 |
| First-aid kit and work clothes | 300 |
| Materials float (paint and sundries for the first jobs) | 3,000 |
| Working cash for two months | 6,000 |
| Total | 15,090 |
Financing
Own savings; a susu or VSLA group; microfinance; bank loans; the Ghana Enterprises Agency (GEA), which offers SME GO, Business-in-a-Box, SME High Growth and Kaizen, with Business Advisory Centres in Takoradi, Shama, Effia-Kwesimintsim, Mpohor and Ahanta West. The 2026 Budget set aside GH¢170 million for a National Apprenticeship Programme and GH¢160 million for Adwumawura. The Assemblies' disability fund can help persons with disabilities; the 2026 rate was not verified, so ask the Assembly. Start free and cheap; borrow only when you have jobs lined up. A deposit from the client is the cheapest finance you have: put 30% in the contract (Unit 2).
Hire, supervise and protect
The Labour Act requires a written contract for work of six months or more (s.12), a written statement of terms within two months (s.13), 15 working days of paid leave (s.20) and 12 weeks of maternity leave (s.57); casual workers get the full minimum for each day worked (s.74). Minimum wage is GH¢21.77 a day in 2026. SSNIT: employee 5.5% and employer 13% of basic salary, total 18.5%; pay within 14 days after month-end; late payment costs 3% a month. PAYE is due by the 15th of the next month.
Apprentices: teach safety first; start them on preparation and cleaning; never put a new person on a ladder alone; give a written agreement and a clear end date. A national apprenticeship programme was funded in the 2026 Budget. Supervising: give one task at a time; show the standard; check at the hold points (Unit 2); praise and correct in private; pay on time; keep a daily diary.
Insurance. Use only insurers licensed by the National Insurance Commission; check at nic.gov.gh. Which covers are compulsory for a small painter was not verified; ask the NIC. Consider: public liability (if you damage a client's property), tools and equipment, and workers' injury cover (injured workers must be compensated whoever was at fault, Source: Citi Newsroom WCA).
Market yourself
Marketing in a week
- Take before and after photos of three jobs: same angle, same time of day; note the area and time taken. Ask the client for permission to use them.
- Set up a WhatsApp Business profile with a catalogue of services and a price guide.
- Set up a free Google Business Profile with your area, hours, photos and phone.
- Publish a "from GH¢ per m²" price with conditions (for example "interior emulsion, two coats, you supply nothing but water and power, prepared surfaces"). Jiji ads mostly say "contact for price".
- Ask every happy client for a referral and one short written comment. Give them a card with your name and number.
- Put a sign on the job site (with the client's permission) and a name on your gang's shirts or your pickup.
Accessibility and inclusion
The Persons with Disability Act 2006 (Act 715) bans job discrimination. Painting tasks that can suit many people with mobility difference include mixing and tinting, filling and sanding at a bench or low height, cutting in at low height with an extension pole, cornice cutting and POP casting at a table, estimating and quote writing, shop attendance, social media and the portfolio, and supervising with a ladder-spotter. This is the author's judgement, not a sourced list. A Brazilian study found that workers with hearing impairment could do construction tasks without adaptation, while leg or foot amputees needed suitable prostheses and adaptations, but the evidence for painters was thin (one worker). A Solomon Islands man who is deaf, with a Certificate III in Painting and Decorating, runs his own business and gives job experience to other deaf people. Adjustments: show tasks instead of only telling; give written quotes and instructions; use WhatsApp; set ground-level or seated work. Visual impairment limits painting roles; data are not verified. Work at height, scaffolds and two-pack spraying are not suitable without adaptation and should not be pushed. For women, only 2 to 6% of female YIEDIE trainees chose painting, masonry, tiling or electrical trades, so a woman-led gang that does finishing can find clients who prefer it; set clear rules on site against harassment.
One-page business plan and pitch
Fit on one page: customers (who and why); services and prices (per m², per room, per ceiling); location and store; start-up cost and finance; monthly costs and break-even (Unit 6); permits, tax route and insurance; gang, safety and quality rules; how you will advertise; 12-month cash plan (Unit 7).
Exercise 5: start-up and fees
(Example numbers.)
- Add the first six lines of the start-up budget (ORC fee, permit, ladders, kits, sander, drill). What is the total?
- Total start-up is GH¢15,090. You have savings of GH¢6,000, a susu payout of GH¢4,000 and the rest comes from a loan. How big is the loan?
- The loan is repaid over 12 months with a flat interest of 24% a year on the amount borrowed (example; ask the lender how interest is worked out). Find total interest, total repaid and the monthly payment.
- Sole proprietor: ORC cost in year 1 and in year 2? A partnership of two painters: ORC cost in year 1?
- A company with stated capital of GH¢10,000: ORC fee plus 1% capital duty (if the page rate holds)?
Register on paper and pitch
- Fill in a registration checklist for a sole proprietor and for a partnership: body, step, fee, document needed, who does it, date.
- Build your own start-up budget with three local price quotes for the five biggest items.
- Write a one-page plan and pitch it for two minutes to a partner.
- Write one rule for the gang on safety, one on honesty and one on harassment.
Ask GRA
Write a short letter or WhatsApp message to GRA Takoradi asking: (a) is contract painting a taxable service for VAT, (b) is a painter eligible for the Modified Taxation Scheme, and (c) which withholding rate applies to a client's payment. Bring any reply to class.
Check yourself
- How much does it cost to register a sole-proprietor business name in 2026?
- What is the Modified Taxation Scheme rate for turnover from GH¢20,001 to GH¢750,000?
- Who must you ask about the VAT position of a painting service?
Unit 6 · Accounting and bookkeeping for a decorator
A job that makes a profit on paper and loses money in the bank is still a job that sinks you. Learn to see both.
See the hub's Money Skills Level 2 and Entrepreneurial Thinking Level 2 for the basics. This unit goes deeper and uses a painter's numbers. All figures are examples; the arithmetic was checked by script.
Competency standard
| Learning outcome | Performance criteria — the trainee… |
|---|---|
| 6.1 Cost and price a job | builds a job costing sheet and a quote with overhead and profit, and tells mark-up from margin |
| 6.2 Handle deposits, stages, retention and variations | records stage payments, retention and extras |
| 6.3 Keep daily records and control stock | keeps a cash book, receipts, invoices, petty cash, materials stock cards and a debtors list |
| 6.4 Pay wages and keep tax records | works out pay, SSNIT and PAYE, and lists what to file and when |
| 6.5 Close the month | reconciles, does a trial-style check, income statement and simple balance sheet |
| 6.6 Plan break-even and cash | calculates depreciation, break-even and a monthly cash plan |
Range. A small painting and decorating business (the example business is a sole proprietor). Evidence. Costing sheet; cash book; stock card; wage sheet; month-end pack.
The core rule
Assets = Liabilities + Equity. Debits increase assets and expenses; credits increase liabilities, capital and income; the trial balance checks totals but cannot catch every error. Keep owner money and business money apart: pay yourself a fixed drawing.
Step 1: Job costing and quoting
A job costing sheet adds up every cost of one job. Use one sheet per job.
Worked example A (example numbers). The house job in Unit 2 (485 m² of surface, 11 days, gang of 4: a foreman at GH¢200 a day and three painters at GH¢150 a day).
| Cost line | GH¢ |
|---|---|
| Paint (5 tins interior at 350 + 4 tins exterior at 480) | 3,670 |
| Sundries (filler, tape, sandpaper, dust sheets, consumables) | 850 |
| Hired scaffold gang | 900 |
| Labour: 11 days × (200 + 3 × 150 = 650) | 7,150 |
| Transport and delivery | 400 |
| Direct cost | 12,970 |
| Overhead share 12% of direct cost (store, phone, insurance, tools wear) | 1,556.40 |
| Total cost | 14,526.40 |
Mark-up and margin. Mark-up is profit ÷ cost. Margin is profit ÷ selling price. With a 25% mark-up the price is 14,526.40 × 1.25 = GH¢18,158.00. If you want a 25% margin the price is 14,526.40 ÷ 0.75 = GH¢19,368.53. They are different. A 25% margin is a mark-up of 33.3%. We round to GH¢19,400, which is exactly GH¢40 per m² on 485 m². The profit is 19,400 − 14,526.40 = GH¢4,873.60, which is a margin of 25.1%.
VAT on the quote (only if you are registered). VAT effective 20% of the net price in this book (15% VAT + 2.5% NHIL + 2.5% GETFund levy). On GH¢19,400, VAT = 3,880 and the client pays GH¢23,280. You collect it for GRA and file monthly; it is not your income. If you are not sure whether you must register, see Unit 5 and ask GRA. Withholding: if the client withholds 5% of GH¢19,400 (the "works" rate; applicability to painting not verified) that is GH¢970 withheld and paid to GRA for you; ask for the certificate.
What nobody has told you. Do not price by asking what other painters charge. Price by cost plus a margin you choose. If your price is lower than cost plus overhead, every job makes you poorer, and the more jobs you win, the faster you sink.
Step 2: Deposits, stages, retention, debtors
Record each stage as a receipt. From the contract in Unit 2: deposit 5,820 (30%), stage 2 7,760 (40%), completion 4,850 (25%), retention 970 (5%) = 19,400. Keep a debtors list:
| Debtor | Job | Amount GH¢ | Due | Age at 31 Mar | Action |
|---|---|---|---|---|---|
| Mr A | Job A completion | 4,850 | 14 April | 0 days | Invoice sent |
| Mr A | Job A retention | 970 | 30 June | not due | Diary note |
| School C | Job C | 6,400 | 20 April | 11 days | Call on due date |
| Total | 12,220 |
A customer advance (a deposit for a job not yet started) is not income yet. It is a liability: you owe the work or the money back.
Step 3: Daily records
- Cash book: every receipt and payment in date order, with a running balance (cash and MoMo; or two columns).
- Receipts and invoices: number them in order; keep copies; sign and date. E-VAT invoices are verified by QR code if you are registered.
- Petty cash: a small float with a voucher for every spend; top it up to the same amount.
- Materials stock card: for each paint product: date, in, out, balance, unit cost.
- Job sheets: all costs and hours for each job.
- Debtors and creditors: who owes you and whom you owe, with due dates.
Stock card with the average cost (example). Product: 20 L white emulsion. Opening 6 tins at GH¢340 = 2,040. Buy 10 tins at GH¢360 = 3,600. Now 16 tins worth 5,640; average cost = 5,640 ÷ 16 = GH¢352.50 a tin. Issue 8 tins to a job: 8 × 352.50 = 2,820, leaving 8 tins worth 2,820. Buy 4 more at GH¢380 (1,520): now 12 tins worth 4,340; average = GH¢361.67. Issue 5 tins: 5 × 361.67 = 1,808.33; balance 7 tins worth 2,531.67. Do a physical count each month and compare with the card; a missing tin is cash gone.
Step 4: Wages, SSNIT and PAYE (employee example)
For a salaried foreman. 2026 PAYE monthly bands: first GH¢588 at 0%; next 80 at 5%; next 100 at 10%; next 2,900 at 17.5%; next 16,000 at 25%; next 30,332 at 30%; above 50,000 at 35%. Deduct SSNIT 5.5% first to get taxable pay. Example: basic GH¢2,400.
| Line | GH¢ |
|---|---|
| Basic pay | 2,400.00 |
| SSNIT employee 5.5% | 132.00 |
| Taxable pay | 2,268.00 |
| Tax: 588 × 0% | 0.00 |
| Next 80 × 5% | 4.00 |
| Next 100 × 10% | 10.00 |
| Remaining 1,500 × 17.5% | 262.50 |
| PAYE | 276.50 |
| Net pay | 1,991.50 |
| SSNIT employer 13% (paid by you) | 312.00 |
| Cost to you | 2,712.00 |
Pay SSNIT by the 14th and PAYE by the 15th of the next month. Casual daily workers: GRA's PAYE page lists a 5% rate for casual workers; ask GRA how it applies to a day-by-day gang. A casual worker must still get at least the daily minimum, GH¢21.77 in 2026.
Step 5: Depreciation, break-even
Depreciation (straight line) = (cost − salvage) ÷ useful life. Example: an aluminium tower scaffold at GH¢6,000, salvage GH¢1,000, 5 years: GH¢1,000 a year, GH¢83.33 a month. Ladders, sander, drill and meters, together GH¢2,800, salvage GH¢400, 3 years: GH¢800 a year, GH¢66.67 a month. Total GH¢150 a month.
Break-even. Fixed monthly costs in the example: overhead GH¢1,285 plus owner's drawing GH¢4,000 = GH¢5,285. Profit before overhead on Job A is (19,400 − 12,970) ÷ 485 = GH¢13.26 per m². Break-even = 5,285 ÷ 13.26 = about 399 m² a month. If you can paint 485 m² in 11 days, you cover the month in about one job; but you must find the jobs.
Step 6: A month of books: the example business
Example business: a sole proprietor, March. Opening position at 1 March: cash and MoMo GH¢6,500; debtors GH¢2,500 (from February); equipment net GH¢8,500 (cost 8,800, depreciation so far 300). No loans. Owner's equity = 6,500 + 2,500 + 8,500 = GH¢17,500.
Cash book for March (full page).
| Date | Details | Receipts GH¢ | Payments GH¢ | Balance GH¢ |
|---|---|---|---|---|
| 1 Mar | Opening balance | 6,500 | 6,500 | |
| 2 Mar | Job A deposit (30%) | 5,820 | 12,320 | |
| 3 Mar | Job A paint and sundries | 4,520 | 7,800 | |
| 5 Mar | Hired scaffold gang, Job A | 900 | 6,900 | |
| 7 Mar | Wages week 1 | 2,600 | 4,300 | |
| 9 Mar | Job B (shop) paid in full | 3,600 | 7,900 | |
| 10 Mar | Job B paint and sundries | 950 | 6,950 | |
| 11 Mar | Job C paint and sundries | 1,780 | 5,170 | |
| 12 Mar | February debtor pays | 2,500 | 7,670 | |
| 14 Mar | Wages week 2 | 3,900 | 3,770 | |
| 16 Mar | Job A stage 2 (40%) | 7,760 | 11,530 | |
| 18 Mar | Store rent | 600 | 10,930 | |
| 20 Mar | Wages week 3 | 2,600 | 8,330 | |
| 22 Mar | Transport for jobs A, B, C | 650 | 7,680 | |
| 24 Mar | Other transport and fuel | 300 | 7,380 | |
| 25 Mar | Phone and data | 150 | 7,230 | |
| 26 Mar | Wages week 4 | 1,750 | 5,480 | |
| 28 Mar | Job D deposit (customer advance) | 2,000 | 7,480 | |
| 30 Mar | MoMo charges | 85 | 7,395 | |
| 31 Mar | Owner's drawing | 4,000 | 3,395 | |
| Totals | 21,680 | 24,785 | 3,395 |
Check: 6,500 + 21,680 − 24,785 = GH¢3,395. Count your cash and check your MoMo app: it must say the same.
Job summary for March.
| Job | Price | Direct cost | Gross profit | Status |
|---|---|---|---|---|
| A: house repaint | 19,400 | 12,970 | 6,430 | Finished 31 March; 4,850 + 970 still owed |
| B: shop interior | 3,600 | 2,450 | 1,150 | Paid in full |
| C: school classrooms | 6,400 | 4,230 | 2,170 | Finished; invoiced 20 March; unpaid |
| Total | 29,400 | 19,650 | 9,750 |
Income statement, March (accrual basis: income counted when the job is finished and invoiced).
| Line | GH¢ |
|---|---|
| Income (jobs finished) | 29,400 |
| Direct costs (materials, wages, scaffold, transport) | 19,650 |
| Gross profit (33.2% margin) | 9,750 |
| Store rent | 600 |
| Phone and data | 150 |
| Other transport and fuel | 300 |
| MoMo charges | 85 |
| Depreciation (tower, tools) | 150 |
| Net profit before tax | 8,465 |
| MTS tax 3% of turnover (arithmetic practice; see Unit 5 caution) | 882 |
| Net profit after tax | 7,583 |
| Owner's drawing | 4,000 |
| Kept in the business | 3,583 |
Why is cash only GH¢3,395 when profit is GH¢7,583? Because GH¢12,220 of the income is still owed by customers, and GH¢2,000 was a deposit for April. Profit is not cash.
Simple balance sheet at 31 March.
| Assets | GH¢ | Liabilities and equity | GH¢ |
|---|---|---|---|
| Cash and MoMo | 3,395 | Customer advance (Job D deposit) | 2,000 |
| Debtors | 12,220 | MTS tax owed | 882 |
| Equipment: cost 8,800 less depreciation 450 | 8,350 | Total liabilities | 2,882 |
| Owner's equity | 21,083 | ||
| Total assets | 23,965 | Total liabilities and equity | 23,965 |
Equity check. Opening equity 17,500 + profit after tax 7,583 − drawing 4,000 = 21,083 ✓.
Trial-style check. Total of debits = total of credits = 50,232.
| Debits | GH¢ | Credits | GH¢ |
|---|---|---|---|
| Cash and MoMo | 3,395 | Accumulated depreciation | 450 |
| Debtors | 12,220 | Customer advance | 2,000 |
| Equipment at cost | 8,800 | MTS tax owed | 882 |
| Direct costs | 19,650 | Sales (March) | 29,400 |
| Overheads (incl. depreciation) | 1,285 | Opening equity | 17,500 |
| MTS tax expense | 882 | ||
| Owner's drawing | 4,000 | ||
| Total | 50,232 | Total | 50,232 |
Step 7: The month-end routine
Close the month in 8 steps
- Total the cash book; count cash in hand and agree it. Agree the MoMo balance with the app.
- Reconcile the bank or MoMo statement to the cash book: tick matching lines; list unrecorded fees or deposits; correct the book.
- Update the stock cards; count the tins and compare.
- Update the debtors and creditors lists; chase anything overdue.
- Do the trial-style check (debits = credits).
- Write the income statement (income − costs = profit) and a balance sheet.
- Compare with last month and with your forecast; note two things to fix.
- File receipts, copies, payslips and tax papers; back up the spreadsheet or phone photos.
Reconciliation example. Cash book MoMo balance 2,860. Statement balance 3,310. Differences: a client paid GH¢500 on 29 March that you did not write in the book (+500); MoMo fees of GH¢50 not in the book (−50); statement shows 3,310; book corrected = 2,860 + 500 − 50 = 3,310 ✓.
Tax records and the law
Keep records in Ghana for at least six years from the end of the year of assessment or VAT period. Filing calendar: SSNIT by the 14th; PAYE and withholding tax by the 15th; VAT by the last working day of the next month; provisional tax quarterly (companies); annual return within four months of year-end; STMA permit by 31 March; ORC annual return yearly. Free tools: Excel or Google Sheets, Zoho Books free plan (1 user plus accountant, 1,000 invoices a year, revenue under US$50,000) and Wave (summary only). From 1 January 2027 the 2025 edition of IFRS for SMEs applies for companies using it.
Exercise 6: price, pay and close
(Example numbers.)
- A room job: paint GH¢420, sundries GH¢90, labour 2 painters × 2 days × GH¢150 = ?, transport GH¢40. Find direct cost.
- Overhead 10% of direct cost; find the cost. Price with a 25% mark-up. Price with a 25% margin. Which is higher?
- Stock: opening 4 tins at GH¢350; buy 6 at GH¢365. Average cost per tin? Issue 5 tins: value issued and balance?
- Foreman basic GH¢1,200. SSNIT employee 5.5%, taxable pay, PAYE using the bands in this unit, net pay, employer SSNIT 13%.
- A paint-mixing machine costs GH¢3,600, salvage GH¢600, life 5 years. Depreciation per year and per month?
- Fixed costs GH¢3,000 a month; profit before fixed costs GH¢12 per m². Break-even m²?
- Cash book at 1 June: 2,000. Receipts: 6,800 (deposit 2,400, completion 4,400). Payments: materials 3,100, wages 2,600, rent 500, transport 250. Closing cash? A client owes GH¢1,800. Is that GH¢1,800 cash yet?
Close a month
- Complete a cash book from a list of 20 transactions; check the closing balance.
- Make a job costing sheet and a quote with 12% overhead and a 25% margin.
- Fill in a stock card with two purchases and two issues.
- Work out one payslip and the employer's cost.
- Reconcile a given MoMo statement and prepare an income statement, a balance sheet and a trial-style check.
Your own book
Start a real cash book now. Record every spend and every receipt for one week, including MoMo fees. Count what is in your wallet and phone at the end and compare it with the book.
Check yourself
- What is the difference between mark-up and margin?
- Why is a customer's deposit for a job not yet started a liability?
- How long must business records be kept in Ghana?
Unit 7 · Grow, tender and present your plan
Quality and honesty grow a painting business. Shortcuts end it.
Competency standard
| Learning outcome | Performance criteria — the trainee… |
|---|---|
| 7.1 Run quality and customer care | uses checklists, feedback and complaint handling |
| 7.2 Price and grow | sets a pricing strategy and plans how to scale |
| 7.3 Win and keep contracts | explains contracts, tenders, partnerships and records for loans |
| 7.4 Plan for ethics and succession | writes procedures and ethical rules |
| 7.5 Present a capstone | presents a plan with a 12-month cash-flow forecast |
Range. A painting and decorating business plan. Evidence. One-page plan; forecast; panel score sheet.
Quality systems and customer care
A quality system is just the habits in Units 2 and 4 written down: a survey sheet, a contract, hold points, a daily diary, a snag list and a handover note. Add:
- Customer feedback: ask every client to rate you from 1 to 5 and say one thing to improve
- Complaint handling: reply within two days, visit within a week, agree a fix in writing (good practice)
- A call-back after 3 months to check the paint and ask for a referral
- A training habit: a short talk with your gang each month on one skill, one fault and one safety topic
Pricing strategy
Price from cost, not from fear: include your time, labour, materials, transport, overhead and a margin (Unit 6). Offer packages: "Home refresh" (interior walls and ceilings), "Landlord pack" (apartment turnaround in 3 days), "Exterior protect" (wash, fungicide, masonry paint), "Ceiling and cornice". Raise prices when you are always booked. Never compete only on being the cheapest: a very low price means short cuts and failures. Offer an annual repaint contract to landlords and shops.
Scaling
- Train a second foreman so two jobs can run at once
- Build a specialist niche: textured finishes, POP ceilings, waterproofing coatings, painting for hotels
- Partner with a builder, an electrician (certified by the Energy Commission) and a plumber so you refer work to one another (do not do their work)
- Add a small shop only when your books show a steady profit and you can control stock
- Buy your own scaffold tower only when steady exterior work covers its depreciation
Contracts, tenders and partnerships
Put every job in writing (Unit 2). For bigger clients (schools, hotels, builders) expect a written contract, a programme, insurance and a price schedule. Bigger firms may ask for tax clearance, registration documents, insurance and proof of past work (not verified). Public tenders: whether and how a small painter can bid for Assembly or school painting work, and the registration with the Public Procurement Authority, was not verified; ask the STMA procurement unit. A tender is a written offer to do work at a price. To prepare one, you need: the bill of quantities or schedule, your measured quantities, rates, programme, method statement, safety plan, references, and registration papers.
Withholding tax may be deducted from your fees: works 5%, services 7.5%; applicability to painting is not verified. Ask for the certificate.
Records for a loan
Lenders ask for registration, TIN, 6 to 12 months of cash book and MoMo statements, signed contracts, a list of debtors, a plan, and a guarantor or security. Tidy books are your best collateral (judgement). The Ghana EXIM Bank offers SME and export facilities, with an office in Takoradi; GIRSAL gives guarantees for agricultural loans only, so it is not for a painter. The Bank of Ghana policy rate was 14.00% and inflation 5.2%; interest rates charged to small firms are higher, so borrow only what you can repay from a clear contract.
Succession and ethics
Write your procedures down so the business runs without you: survey sheet, price list, supplier list, client list, forms, passwords, where tools are kept. Name the person who takes over if you are ill. Ethics: never paint over damp and claim it is fine; never use paint you know contains lead; never tip paint into drains; never tell a client a product has a warranty that it does not; never pay below the minimum wage; never pass off someone else's work as your own; respect clients' homes and privacy; do not post photos of homes without permission; say "I cannot do this safely" when you cannot.
Capstone: 12-month cash-flow forecast
A cash-flow forecast lists, month by month, opening cash, expected receipts, expected payments and closing cash. Seasonality matters: dry-season months before Christmas and Easter are usually busier, and the rainy months slower for exterior work (a trade judgement; no Takoradi data was verified). Fill one row per month. Use example numbers in training and your own real ones in your plan.
Example forecast (all numbers examples; opening cash GH¢9,000 after set-up):
| Month | Opening cash | Receipts | Payments | Closing cash |
|---|---|---|---|---|
| 1 | 9,000 | 8,000 | 9,500 | 7,500 |
| 2 | 7,500 | 12,000 | 11,000 | 8,500 |
| 3 | 8,500 | 15,000 | 12,500 | 11,000 |
| 4 | 11,000 | 14,000 | 12,000 | 13,000 |
| 5 | 13,000 | 9,000 | 10,500 | 11,500 |
| 6 | 11,500 | 5,500 | 8,000 | 9,000 |
| 7 | 9,000 | 4,500 | 7,500 | 6,000 |
| 8 | 6,000 | 6,000 | 7,500 | 4,500 |
| 9 | 4,500 | 10,000 | 9,500 | 5,000 |
| 10 | 5,000 | 14,000 | 11,500 | 7,500 |
| 11 | 7,500 | 17,000 | 13,000 | 11,500 |
| 12 | 11,500 | 19,000 | 14,500 | 16,000 |
| Year | 134,000 | 127,000 | net +7,000 |
Read the forecast. The lowest closing cash is GH¢4,500 in month 8, after three slow months. Plan for it: collect debtors, delay buying a big tool, sell an annual contract, do indoor and ceiling work in the rains, and keep a reserve. Check any month where closing cash goes below zero and plan how to fix it (delay a purchase, collect a debt, ask for a bigger deposit, borrow a small amount).
Panel scoring (20 marks each): customer and problem; services, tax route and legal route (including permits); money (start-up, prices, break-even, forecast); safety, lead and waste rules and ethics; clarity and answers to questions. Competent: at least 60 of 100 with no zero in safety and ethics (author's rule).
Exercise 7: forecast and growth
(Example numbers.)
- Opening cash GH¢5,000. Month 1: receipts 6,000, payments 7,500. Month 2: receipts 9,000, payments 8,000. Month 3: receipts 3,500, payments 6,500. Find each closing cash. In which month is there a problem and by how much?
- Name three ways to fix it.
- You get an annual repaint contract from a landlord: 6 flats, 2 repaints a year at GH¢2,400 each. Annual value? Monthly average?
- You add a second gang. It costs GH¢9,000 more in payments per month and adds GH¢11,500 receipts per month. Monthly extra cash? Over 12 months?
Present to a panel
- Build a one-page plan with a 12-month forecast.
- Present for five minutes to a panel of three.
- Answer three questions, including one on what you will not do (for example, spraying two-pack paints, wiring lights, or painting over damp) and why.
Feedback fix
Write two things the panel said to improve, and your plan to fix each by a date.
Check yourself
- What is a cash-flow forecast, and why must you look for the lowest month?
- Name two things a lender may ask to see.
- Name two ethical rules for a decorator.
Glossary
| Term | Meaning |
|---|---|
| Competent / Not Yet Competent | The two possible results of a CBT assessment |
| Specification (spec) | The written description of surfaces, products, coats and standard of finish |
| TDS / SDS | Product data sheet / safety data sheet from the maker |
| Volume solids | The part of wet paint that stays on the wall as dry film |
| DFT | Dry film thickness, in microns |
| Coating system | Primer, undercoat and finish coats working together |
| Efflorescence | White powdery salts on masonry, pushed out by water |
| Hold point | A stage where work stops until it is checked |
| Variation | A change to the job after the contract |
| Retention | A small part of the price held back until the defects period ends |
| Snag / snagging | A small defect / the walk and list to find and fix them |
| Defects period | The time after handover when you fix defects free |
| Lead limit | Ghana's 90 ppm limit for lead in paint (GS 180) |
| Isocyanates | Chemicals in some two-pack paints that can cause asthma |
| Mark-up / Margin | Profit as a share of cost / of selling price |
| Reconciliation | Matching your records to the bank or MoMo statement |
| Depreciation | Spreading the cost of a tool over its useful life |
| Break-even | The sales at which profit is zero |
| MTS | Modified Taxation Scheme for small traders who are not VAT-registered |
Logbook
Copy these pages into an exercise book. Your logbook is part of your assessment evidence.
- Unit 1: specification query list; TDS summary sheets; system table; failure diagnosis reports
- Unit 2: survey sheet; estimate; programme; materials issue book; contract; snag list
- Unit 3: job risk assessment; respirator register; lead log; waste log; compliance file
- Unit 4: test boards; feature wall photos; ceiling mock-up record; inspection plan; handover note
- Unit 5: registration checklist; start-up budget; one-page plan; letter to GRA
- Unit 6: job costing sheet; cash book; stock card; payslip; month-end pack
- Unit 7: forecast; panel feedback
- Every homework, dated
Self-check quiz
- What is the formula for theoretical coverage from volume solids and DFT?
- Which document overrides this book when it comes to drying times and thinning?
- What is the first thing to find before repainting a wall with efflorescence?
- What are the four payment stages in the example contract?
- How should a ladder be angled, and how far above the landing should it extend?
- What is Ghana's lead limit in paint, and does a law enforce it yet?
- Why must you never dry sand old paint?
- Who may wire a cove light in a ceiling?
- What is the cost of registering a sole-proprietor business name in 2026?
- What is the difference between mark-up and margin?
- What makes the MTS an uncertain choice for a painting service?
- For how long must business records be kept?
Further reading and sources
What this module does not cover: spraying two-pack paints; scaffold building; electrical wiring; structural design; a CTVET standard for painting (none found); Ghana scaffold and ladder rules, PPE standards, paint-waste listing under Act 1124 and Western Regional EPA contacts (none verified); Ghana per-m² labour rates (none found); VAT treatment of painting services (to confirm with GRA).
Every source used in this manual is listed, with links, in the Teacher Copy.