About this module
A good printer makes good prints. A good shop owner makes good prints every day, on time, safely, legally and at a profit.
Who it is for. Printers and sign makers who have completed Screen Printing and Signage Level 2 or can show the same skills, including persons with disabilities, who want to supervise others or run their own business. In Ghana's TVET framework, National Proficiency II leads on to National Certificate I. This module works at about that advanced level: you handle non-routine problems, supervise others and can run an enterprise. It is not a CTVET curriculum and carries no accreditation.
Why go further
- Every colour is a separate screen and pass, so multi-colour orders need planning, people and space, not just skill.
- Sign work brings permits and penalties. In Sekondi-Takoradi, placing an advertisement without a permit or in the wrong place carried GH¢1,000 per case in 2025.
- Customers now choose between screen printing, vinyl transfers and direct-to-film (DTF) printing. A DTF printer was advertised in Ghana in October 2026 at GH¢45,000. An owner must choose wisely.
- The hub's Money Skills Level 2 and Entrepreneurial Thinking Level 2 courses teach general bookkeeping and venture basics. Units 5–7 here go deeper and are specific to a print and sign shop.
CTVET status. CTVET's approved list has no screen printing or sign-writing programme; the nearest are Multimedia Practice, Textiles Design Technology and Graphic Design Technology. This module is not a CTVET curriculum. It follows CTVET's format.
Bridge from Level 2: what you already know
- Choose mesh by ink and detail; coat with a scoop coater; calculate exposures and confirm with step tests
- Reclaim and de-haze safely; manage solvents, wastewater and hazardous waste
- Cure water-based and plastisol inks at the maker's settings; prove the cure with temperature, stretch and wash tests
- Print an underbase on dark shirts; mix and record colours
- Print two and three colours in register with trap and registration marks
- Trace, redraw and separate artwork in Inkscape and GIMP; make proofs; collect rights confirmation
- Set up a plotter; cut, weed and apply sign vinyl; press heat-transfer vinyl
- Plan signboards with letter-height sums; make and fix signs with a footed leaning ladder; name STMA sign permits
- Run a job ticket; check quality; keep a reject log; price with set-up costs
If any box is not ticked, your trainer will give you a short catch-up session before Unit 1.
How the module works
- Each unit has learning outcomes, performance criteria, a range and the evidence your assessor needs. CTVET assessment has two outcomes, achieved or not yet achieved; this manual says Competent or Not Yet Competent.
- You now work with little supervision and you supervise others.
- Numbers marked example are for practice. Business figures from official pages are cited; check them again before you use them, because fees and taxes change.
- Every unit ends with a Check yourself. Answers are in the Teacher Copy.
Unit 1 · Production planning and supervising a print and sign team
The squeegee is the easy part. Getting the right shirts, screens, ink and people to the right table at the right hour is the real skill.
Competency standard
| Learning outcome | Performance criteria: the trainee… |
|---|---|
| 1.1 Plan production | turns orders into a schedule with capacity, deadlines and material lists |
| 1.2 Organise the workflow | lays out the shop and job flow so jobs move without mix-ups |
| 1.3 Supervise and train | gives clear instructions, trains an apprentice step by step and checks work |
| 1.4 Lead safety and quality | runs a safety talk, keeps PPE and training records and samples quality during runs |
Range. A shop of two to five people, including at least one apprentice; a week of mixed orders (shirts, stickers, a sign). Evidence. Weekly schedule; job board; training record; safety talk record; quality sampling sheet; oral questions.
From order to delivery: the job flow
| Stage | Who | Output |
|---|---|---|
| 1 Enquiry and quote | Owner or supervisor | Written quote |
| 2 Rights check and deposit | Owner | Permission on file; deposit received |
| 3 Artwork and proof | Designer | Signed proof |
| 4 Films and screens | Screen maker | Exposed, checked screens |
| 5 Blanks and materials | Store keeper | Counted shirts by size, ink, vinyl |
| 6 Print or cut | Printer, cutter | Pieces |
| 7 Cure and test | Printer | Cure record; test piece |
| 8 Quality check and pack | Supervisor | Signed checklist; counted pack |
| 9 Deliver, install and get paid | Owner or installer | Delivery note; balance received |
(Example workflow by the author.)
Plan capacity
Capacity is how much your shop can produce in a day. Measure it, do not guess: time your team on a real job.
Capacity sums (example figures)
Your team prints 25 shirts an hour on a three-colour job with a carousel press, including flashing. You work 8 hours a day but lose 1.5 hours to set-up, cleaning and breaks. (a) How many shirts per day? (b) A school orders 500 three-colour shirts due in 6 working days. Screens take 1 day to prepare. Can you make it? (c) What would you do if a church then asks for 200 more shirts in the same week?
The job board
- A whiteboard with columns for each stage (artwork, screens, blanks, print, cure, QC, delivery).
- A card or line for each job with job number, customer, due date and quantity.
- Move the card as the job moves. Everyone can see what is late.
- A daily 10-minute start-up meeting at the board: today's jobs, who does what, safety point of the day.
Supervising people
- Clear instructions: what, how many, by when, to what standard, and what to do if something goes wrong.
- Show, then watch, then check: demonstrate, let the person try while you watch, then check the first pieces before they run the rest.
- One job, one person responsible: name who signs the quality check.
- Praise in public, correct in private.
- Fair pay and contracts. A worker employed for six months or more must have a written contract, and a written statement of terms within two months; workers get at least 15 working days' paid leave a year. The 2026 minimum wage is GH¢21.77 a day. Casual workers must be paid the full minimum for each day worked.
Training apprentices
- Write the skill as steps (the Level 1 and Level 2 practicals are a good start).
- Train one skill at a time: screen prep, then coating, then printing, then curing.
- Keep a training record: skill, date shown, date practised, date signed off, trainer.
- Sign off a skill only when the apprentice does it correctly three times without help (author's rule).
- Never leave an apprentice alone with emulsion remover, haze remover, solvents, the heat press or a ladder until signed off.
- The 2026 Budget allocated GH¢170 million to the National Apprenticeship Programme; ask the Ghana TVET Service or your Assembly whether your shop can host funded apprentices (not verified).
Leading safety
- Daily: PPE on; chemical lids closed; wash area clear; irons and presses unplugged at night.
- Weekly: check ladders, hinges, electrical cords and the first-aid kit; clean the workroom.
- Skin and lungs: the UK safety body advises health checks for dermatitis and asthma where these are likely, and training workers to spot early signs of dermatitis. In a small shop, ask every worker once a month about rashes, cracked skin, wheezing or chest tightness, record the answer, and move anyone with symptoms away from chemicals and to a clinic.
- Records: PPE issued, training given, accidents and near misses. Keep inspection records (the HSE says at least five years for equipment tests).
- UV and heat: exposure lamps behind a closed lid or curtain; heat press guards; no loose clothing near conveyors.
Quality sampling during a run
- First piece: check against the signed proof before the run continues
- Every 10th piece (or every 25th on long runs): position, register, coverage, edges
- One cure test per batch or per shift: temperature recorded, stretch test, and a wash test piece set aside
- Count by size before packing
- Reject log: what, how many, why, fix
Run the shop for a week
- Take three practice orders (a 200-shirt three-colour job, 100 stickers and one signboard) and build a weekly schedule with capacity sums.
- Set up a job board and run a daily start-up meeting.
- Train a Level 1 trainee in one skill, using show–watch–check, and fill a training record.
- Run one safety talk (10 minutes) and record attendance.
- Run quality sampling on the 200-shirt job and complete the reject log.
Shop layout
Draw a floor plan for a 6 m × 4 m print and sign room: coating and drying, exposure, print, flash and cure, wash-out, packing, vinyl and computer, store. Show how a job moves through without crossing back.
Check yourself: Unit 1
- What three numbers do you need to work out daily capacity?
- What must a worker employed for six months or more receive under the Labour Act?
- Name two things you check on the first piece of a run.
Unit 2 · Advanced printing: halftones, special inks and troubleshooting
When a print goes wrong on a 500-piece order, you must find the cause in minutes, not hours.
Competency standard
| Learning outcome | Performance criteria: the trainee… |
|---|---|
| 2.1 Print halftones | prepares a one-colour halftone and prints it on suitable mesh |
| 2.2 Use special inks | prints at least one special effect (puff, glitter, shimmer or discharge) safely |
| 2.3 Troubleshoot | diagnoses print faults from screen, ink, press, substrate or curing and fixes them |
| 2.4 Control quality on long runs | keeps a print stable over 100+ pieces with records |
Range. One halftone job; one special-effect job; one long run; cotton and cotton-polyester blends. Evidence. Halftone prints; special-effect print with cure record; troubleshooting log; oral questions.
Halftones and process printing
- Halftones make shades from dots. Four-colour (CMYK) process printing separates artwork into four colours that combine to imitate a full-colour image, using halftones; the inks are more see-through, so colours are less bright.
- Fine dots need about 280–305 mesh, and yellow mesh is preferred for precise exposure.
- Dots too small for the mesh will not expose. Make dots bigger (coarser screen) for shirts.
- Expose carefully: over-exposure closes small dots.
- Steps: in GIMP or another editor, convert the photo to greyscale, raise contrast, then convert to a halftone (dot) pattern at the size you will print; print the film solid black; expose on high mesh; print with a hard, sharp squeegee and light, even pressure.
Full process and simulated-process work is a specialist skill. Start with one-colour halftones on light shirts.
Special inks and effects
| Effect | What it is | Mesh / notes |
|---|---|---|
| Glitter | Large glitter flakes in clear base | About 36–64 mesh so flakes pass |
| Shimmer | Finer metallic particles | About 86 mesh |
| Puff | Additive that makes the print rise for a raised 3D look | Test the cure; over-heating flattens it |
| Suede | Additive mixed into plastisol at up to about 50% for a soft suede feel | Test small batches |
| Discharge | Removes dye from the fabric; works best on dark 100% cotton; needs good ventilation | Read the safety data sheet; supervisor only |
| Low-cure plastisol | Cures at lower heat, for example about 127 °C | For heat-sensitive fabrics |
Discharge and special inks. Discharge inks need good ventilation. Read the safety data sheet of every special ink before use and follow its gloves, mask and ventilation advice. Where no ventilation is available, do not use discharge inks.
Blends and polyester
Cotton-polyester blends and polyester shirts are common in Ghana's markets. They need care: too much heat can scorch, and dyes in polyester can move into the ink (dye migration), turning white prints pink or grey (not verified: supplier guidance seen only as a search summary). Use low-cure inks or the maker's polyester ink, print a test, cure at the lowest proven temperature, and wash-test before the run.
Screen tension
Tension is measured in newtons per centimetre with a tensiometer. Slack mesh blurs prints, stretches images and spoils registration. If you have no meter, compare by feel against a new screen, retire screens that have gone slack, and re-stretch or replace them.
Troubleshooting matrix
| Fault | Check first | Then |
|---|---|---|
| Blurred edges | Off-contact too low; too much pressure; slack screen | Raise off-contact slightly; less pressure; re-tension |
| Ink pooling or skips | Off-contact too high; stroke too light | Lower off-contact; more pressure |
| Prints fading during the run | Water-based ink drying in mesh | Mist with water; flood promptly; retarder |
| Pinholes appearing | Stencil breaking down | Expose longer; post-expose; patch |
| Lost fine detail | Over-exposure; mesh too low | Shorter exposure; higher mesh |
| Print washes out | Under-cure | Raise time or temperature; test full ink thickness |
| Registration drifting | Loose hinges or pallet; shirt moving | Tighten; pallet adhesive; re-register |
| Colour looks dull on dark shirts | No or thin underbase | 110 mesh white underbase, flash, then colour |
Method: change one thing at a time, print a test, and record what you changed in a troubleshooting log.
Hard prints
- Make and print a one-colour halftone of an original photo (with the subject's permission) on a 280–305 mesh screen.
- Print one special effect (glitter, shimmer or puff) with the right mesh and cure; record settings.
- Run 100 pieces of a two-colour job; sample every 10th; record any faults, causes and fixes in the troubleshooting log.
- Test one cotton-polyester shirt for scorching and dye migration at two temperatures.
Fault cards
Write ten "fault cards" for your shop wall: one fault per card, with a photo or drawing, the likely causes and the fixes in order.
Check yourself: Unit 2
- Which mesh range do halftones need?
- Why must discharge inks only be used with good ventilation?
- What is the golden rule when troubleshooting?
Unit 3 · Signage projects: survey, permits, contracts, height and rights
A sign that falls, a billboard without a permit or a logo you had no right to use can close your business. Plan the whole project.
Competency standard
| Learning outcome | Performance criteria: the trainee… |
|---|---|
| 3.1 Survey and design | surveys a site, measures, photographs and designs a sign for its reading distance and the site |
| 3.2 Permits and approvals | lists the Assembly permits and documents needed and the charges for missing them |
| 3.3 Safe installation plan | plans access, fixings and team for the job, and refers what is beyond the shop's competence |
| 3.4 Contracts and rights | writes a quote and contract with rights, approval, warranty and payment terms |
Range. One shop-front sign, one roadside or directional sign, and one billboard enquiry (planned, not built). Evidence. Site survey sheet; design with sums; permit checklist; installation plan; quote and contract; oral questions.
Site survey checklist
- Customer, location, landmarks; photos from the road at the reading distance
- Wall or post material, condition and height; measurements of the space
- Reading distance and speed of traffic; day and night visibility
- Overhead power lines, road edges, drains and the public footpath
- Access for ladders: ground firm and level? space for the 1-in-4 angle?
- Who owns the wall or land? Written consent from the owner
- Existing signs and permits on the site
Design for the site
- Letter height about 1 inch (2.5 cm) per 10 feet (3 m) of reading distance; short messages; strong contrast; plain sans-serif letters; lighting for night reading.
- For drivers, fewer words: a passing driver has only a moment.
- Choose materials for sun, rain and salt air near the coast. Sign vinyl is rated up to 6 years on vertical surfaces in a mild climate; give a shorter warranty for Ghana's coast (not verified).
Permits in Sekondi-Takoradi (2025 list)
The STMA fee-fixing resolution is made under the Local Governance Act, 2016 (Act 936) and applies across the Sekondi, Takoradi and Essikado-Ketan sub-metros.
| Item | 2025 STMA charge |
|---|---|
| Ordinary signboard | GH¢8.00 per square foot |
| LED illuminated signboard | GH¢9.60 per square foot |
| Ordinary facial (wall) sign | GH¢4.80 per square foot |
| Illuminated facial sign | GH¢5.40 per square foot |
| Movable sign | GH¢24.00 per square foot |
| Billboards | Building permit charged per square metre, with rates by road class and for LED screens |
| Wrongful siting of an advertisement | GH¢1,000 per case |
| Placing an advertisement without a permit | GH¢1,000 per case |
The billboard rate lines in the published table are hard to read; get the exact current rate from the STMA Physical Planning or revenue office before you quote. Other Assemblies (Ahanta West for Akwidaa, Shama, Effia-Kwesimintsim) have their own fee-fixing resolutions: ask each one.
Permit and material sums
(a) A shop wants an illuminated facial sign 12 ft × 3 ft. What was the 2025 STMA fee? (b) A roadside sign 6 m × 3 m: what is its area in square metres and in square feet (1 m² = 10.764 sq ft)? (c) You quote the customer GH¢4,500 for making and fixing the roadside sign but forget the permit and it is put up without one. What could the business owner be charged per case?
Safe installation: know your limit
- Ladders are for short, light work. Follow the leaning ladder rules: 1 in 4, at least 1 m above the work point, three points of contact, no top three rungs, no overreaching, nothing movable under the feet.
- Plan the team: an installer, a person footing the ladder and passing materials, and a person keeping the public away below.
- Refer out (author's rules for this hub): billboards, roof signs, gantries, any sign needing scaffold or a lifting platform, and any large structure go to a qualified engineer and installer. Large sign structures need a building permit from the Assembly.
- Electricity: wiring illuminated signs to the mains is electrical installation work. In Ghana it must be done by an Energy Commission-certified electrical wiring professional (see the hub's Workplace Safety course; not re-verified here). Your shop supplies the sign; the electrician connects it.
- Overhead lines: no work within reach of power lines; call ECG.
- Weather: no work at height in rain or strong wind.
Rights and contracts
Rights. Every design must be cleared before work starts:
- Customer's own logo: ask for a short written statement that they own it or are licensed to use it.
- Brand or franchise signs (telecom, drinks, banks): only with written authority from the brand owner. Trade marks are registered at the Trade Mark Registry in the Registrar-General's Department.
- Photos and illustrations: buy a licence or get written permission from the owner; copyright in artistic works lasts the author's life plus 70 years.
- Folklore designs for sale: written permission from the National Folklore Board.
- Official emblems, crests and badges: never without authority.
The penalties are real: copyright offences can bring fines of 500 to 1,000 penalty units, up to three years in prison, or both, and courts can order forfeiture of the equipment used. The cedi value of a penalty unit was not verified here.
Quote and contract: what to include
- Description, sizes, materials, colours, quantity and drawings or proof
- Price, what is included (design, permit, installation, transport) and what is not
- Deposit (for example 50%) and when the balance is due
- Who gets and pays for permits and the landowner's consent
- Customer's statement that they own or are licensed to use all logos and images, and agree to pay any claim if that is false
- Approval: work starts only after a signed proof
- Delivery or installation date, and what happens if the customer delays approval
- Warranty: for example, "vinyl lettering against peeling for 12 months, not against vandalism or accident" (example wording)
- Cancellation terms
- Signatures and dates
Plan a signage project
- Survey a real shop front (with the owner's permission) and fill the survey checklist.
- Design the sign with letter-height sums and a materials list.
- Write the permit checklist, with the STMA category and fee, and the landowner's consent.
- Write the installation plan: team, ladder, fixings, public safety, weather, and what is referred out.
- Write the quote and contract. Have a partner play the customer and question every clause.
Ask the Assembly
Visit or phone your Assembly's Physical Planning or revenue office. Ask: what is the current fee for an ordinary sign, an illuminated sign and a banner, what documents are needed, and how long approval takes. Write the answers and the officer's title (not their personal number).
Check yourself: Unit 3
- Name four items on a site survey.
- Who should wire an illuminated sign to the mains?
- Why put the customer's rights statement in the contract?
Unit 4 · Equipment, technology choices and maintenance
Buy the machine your orders need, not the machine you dream of. Then look after it so it pays you back.
Competency standard
| Learning outcome | Performance criteria: the trainee… |
|---|---|
| 4.1 Compare methods | compares screen printing, HTV, DTF and outsourced large-format printing for a given job |
| 4.2 Cost a buy-or-outsource decision | works out the cost per piece and the payback time for a machine |
| 4.3 Maintain equipment | keeps a maintenance schedule and log for presses, cutters and heat equipment |
| 4.4 Buy safely | checks condition, warranty, spares and power needs before buying |
Range. Screen press and flash; heat press; vinyl cutter; DTF or large-format (as an outsourcing choice). Evidence. Comparison table; buy-or-outsource calculation; maintenance log; oral questions.
Which method for which job?
| Method | Best for | Weak for |
|---|---|---|
| Screen printing | Runs of many identical pieces; bright, durable prints | Small quantities (set-up per colour); photo-like images unless halftoned |
| Heat-transfer vinyl | Names and numbers; one to ten pieces; simple shapes | Big runs (slow weeding); detailed multi-colour art |
| DTF transfers | Small runs of full-colour art | High machine cost; needs its own consumables and training |
| Large-format print (outsourced) | Banners, posters, vehicle wraps | Owning the machine needs big volume |
(Author's comparison; test with your own customers.)
October 2026 equipment prices seen online
| Item | Asking price | Where | Source |
|---|---|---|---|
| 4 colour 2 station press with flash dryer | GH¢9,000 | Kumasi | |
| 6 colour 6 station screen printing machine | GH¢16,999 | Accra | |
| A2/A3 DTF machine | GH¢45,000 | Accra | |
| 2 ft vinyl cutting plotter | GH¢4,600 | Accra | |
| 4 ft contour cutting plotter | GH¢6,800–6,860 | Accra, Kumasi | |
| Heat press 38 × 38 cm | GH¢2,200 | Accra | |
| Exposure ("shooting") box | GH¢400 | Kumasi |
These are sellers' asking prices, not checked in person. Inspect before you pay, and never pay the full price before seeing the machine.
Buy or outsource? (example figures)
You outsource 600 full-colour DTF transfers a year at GH¢18 each. Owning a DTF machine (GH¢45,000) would cost GH¢7 per transfer in film, ink and powder, plus GH¢300 a month for power and maintenance (example). (a) What is the yearly saving per transfer and in total, before the machine cost? (b) What is the yearly cost of power and maintenance? (c) How many years to pay back the machine? (d) Is it worth it at 600 a year? At 3,000 a year?
Maintenance schedule (example)
| Equipment | Daily | Weekly | Monthly |
|---|---|---|---|
| Screens | Clean after use; store flat or upright, dust-free | Check tension and tears | Retire slack screens |
| Press | Wipe pallets; check hinges tight | Lubricate as the maker says; check registration | Check bolts and arms |
| Flash dryer / heat press | Check cords and plugs; clean platen | Check temperature with a thermometer | Inspect wiring by a qualified electrician if faulty |
| Vinyl cutter | Clean rollers; remove scraps | Check blade sharpness | Replace blade as needed; update settings card |
| Ladders | Inspect before use | Full check and log | Retire damaged ladders |
(Author's schedule; always follow the maker's manual first.) Keep equipment in good working order and check control equipment for damage before starting work.
Buying second-hand: checklist
- See it working on your own design; check the heat reaches and holds the set temperature
- Power: voltage, current and plug; can your supply carry it with the other machines?
- Spares and consumables: blades, elements, pallets, software and drivers available in Ghana?
- Seller's receipt, warranty and a written description
- Safety: cords, guards and earthing in good order
Equipment plan
- For a shop you might open, list the jobs you expect for a year and choose the methods.
- Make a buy-or-outsource calculation for one machine.
- Write a maintenance schedule and start a maintenance log for the training shop.
- Inspect one machine with the second-hand checklist and write a report.
Supplier list
Build a supplier list: for shirts, ink, emulsion, mesh, vinyl, HTV, boards, paint and large-format printing, write two suppliers each with location, price and delivery time.
Check yourself: Unit 4
- When is screen printing better than HTV?
- What is payback time?
- Name three checks before buying a second-hand heat press.
Unit 5 · Establish your own print and sign business
A registered business with clear permits, honest staff contracts and a written plan can borrow, tender and grow. An informal one stays small.
Competency standard
| Learning outcome | Performance criteria: the trainee… |
|---|---|
| 5.1 Choose a legal form | compares sole proprietor, partnership, company and cooperative for a print shop |
| 5.2 Register and get permits | lists the registration steps, bodies and current fees |
| 5.3 Budget and finance | prepares a start-up budget and a funding plan |
| 5.4 Staff, insure and comply | sets up staff contracts, SSNIT and PAYE, insurance and safety |
| 5.5 Plan and market | writes a one-page business plan and marketing plan, including accessibility |
Range. The trainee's own planned print and sign business in Western Region. Evidence. Legal form choice; registration checklist with fees; start-up budget; one-page plan; oral questions.
Choose the legal form
| Form | ORC fee 2026 | Notes |
|---|---|---|
| Sole proprietor (business name) | GH¢130; renewal GH¢70 a year | You and the business are the same; unlimited liability |
| Partnership | GH¢270; renewal GH¢100 a year | 2–20 partners; partnership agreement |
| Company limited by shares | GH¢585 plus capital duty | At least 2 directors and a secretary; annual returns |
| Company limited by guarantee | GH¢490 | For NGOs and social enterprises; no profit to members |
| Cooperative | Not registered at ORC | Route through the Department of Co-operatives not verified |
Annual returns for companies cost GH¢175 a year; late filing GH¢1,000 (1–4 years) or GH¢2,000 (5 years or more). Most new print shops start as a sole proprietor and become a company when they win larger contracts.
Register step by step
- Ghana Card. Your Ghana Card PIN is your individual tax number (TIN).
- ORC. Register the business name (or company) online with the Office of the Registrar of Companies. Renew yearly; USSD *222# is available for renewals.
- Assembly. Register with the Metropolitan, Municipal or District Assembly and pay the business operating permit by 31 March each year. STMA has an online portal. STMA's categories include signage makers, signage writers, printing houses, graphic design companies and advertising companies.
- Your own shop sign. Get a sign permit for your shop sign.
- Tax. Choose the tax route (below) and register.
- SSNIT as an employer when you hire your first worker.
- Trade mark (optional). Protect your own brand at the Trade Mark Registry; registration lasts 10 years and can be renewed.
- Ask about: whether your chemical use or waste needs an Environmental Protection Authority permit under Act 1124, and whether your premises need a Ghana National Fire Service certificate. Both were not verified for a small print shop: ask the Takoradi offices.
Tax route
- Modified Taxation Scheme (MTS): for residents with business income only, not VAT-registered. Turnover up to GH¢20,000: fixed instalments; GH¢20,001–750,000: 3% of turnover, or the modified cash basis. Pay by *880# or the MTS app. GRA's own MTS page still showed GH¢500,000 in October 2026; the GH¢750,000 ceiling comes from the Income Tax (Amendment) Act 2026 (Act 1178).
- VAT: 20% in total from 2026 (15% VAT + 2.5% NHIL + 2.5% GETFund). The registration threshold for goods is GH¢750,000, but there is no threshold for taxable services: a person supplying taxable services must register within 30 days of starting. A VAT-registered business cannot use MTS.
- What this means for a print and sign shop: selling printed shirts you bought is a supply of goods; printing on a customer's own shirts, designing, or installing signs for a fee may be a supply of services. Whether your mix counts as services that must register for VAT was not verified: ask GRA in writing before you start, and keep the answer.
- Withholding tax: bigger customers may withhold 3% on goods, 7.5% on services and 5% on works when they pay you; ask for a withholding certificate.
- Companies pay 25% corporate tax; manufacturers in regional capitals other than Accra and Tema pay 18.5%. Whether a print shop counts as a "manufacturer" was not verified.
Premises and location settings that give good returns
- Close to schools, churches, offices, markets and the central business area, but rent you can carry
- Water for washing screens; drainage that does not flood the street; reliable power for the flash, heat press and computer
- A dark, dry room for coating and drying; good ventilation for cleaning
- A front window or wall that shows your best sign
- Secure storage for blanks, chemicals and machines
- Step-free entrance for staff and customers with disabilities
Start-up budget (example)
| Item | GH¢ | Note |
|---|---|---|
| 4 colour 2 station press with flash | 9,000 | Asking price |
| 2 ft vinyl cutter | 4,600 | Asking price |
| Heat press | 2,200 | Asking price |
| Exposure box | 400 | Asking price |
| 20 screens (frames and mesh) | 3,000 | Example |
| Squeegees, scoop coaters, tools | 600 | Example |
| Computer and printer for films | 6,000 | Example |
| Sign tools, brushes, ladder | 1,800 | Example |
| PPE, first-aid kit, fire extinguisher | 900 | Example |
| Business name and Assembly permit | 630 | ORC 130 + Assembly 500 (example) |
| Opening stock (shirts, ink, vinyl) | 5,000 | Example |
| Working capital (2 months' costs) | 6,000 | Example |
| Subtotal | 40,130 | |
| Contingency 10% | 4,013 | |
| Total | 44,143 |
Fund the start-up (example terms, not a real quote)
You have savings of GH¢14,143. Your susu group lends GH¢10,000. A microfinance institution offers GH¢20,000. (a) Does this cover the budget? (b) What share of the money is your own? (c) The MFI wants GH¢1,950 a month for 12 months. What is the total repaid and the total cost of the loan in cedis?
Funding options
- Savings, susu and VSLA groups: cheapest, but slower.
- Microfinance and banks: check licensing and total cost. The Bank of Ghana policy rate was 14.00% when checked.
- Ghana Enterprises Agency (GEA): programmes include SME GO, Business-in-a-Box, SME High Growth and Kaizen, with Business Advisory Centres in Takoradi, Shama, Effia-Kwesimintsim, Mpohor and Ahanta West.
- 2026 Budget programmes: GH¢401 million for a Women's Development Bank, GH¢160 million for Adwumawura and GH¢170 million for the National Apprenticeship Programme. Ask how to apply.
- Assemblies' disability fund: 5% of the District Assembly Common Fund for persons with disabilities from 2026, up from 3%.
Staff and apprentices
- Contracts: written contract for six months or more; written terms within two months; 15 working days' paid leave; 12 weeks' maternity leave; notice rules.
- Minimum wage: GH¢21.77 a day in 2026, about GH¢587.79 a month at 27 days.
- SSNIT: employee 5.5% and employer 13% of basic salary; employer pays Tier 1 within 14 days after month-end; late payment attracts 3% a month.
- PAYE: deduct SSNIT first; first GH¢588 a month is tax-free; due by the 15th of the next month.
Insurance
Buy cover only from insurers licensed by the National Insurance Commission; check the list at nic.gov.gh. Ask about fire and theft for stock and machines, public liability (a sign that falls on someone), and goods in transit. Which covers are compulsory for a small print shop was not verified.
Market the business
- A strong shop sign (your best advert) and a printed vehicle sticker for your own van or motorbike box.
- WhatsApp Business catalogue and price list; Google Business Profile.
- Portfolio of real jobs (with permission) and a sample board in the shop.
- Partnerships with tailors, event planners, schools, churches and photographers.
- See the hub's Social Media and Canva Design courses for online marketing.
Accessibility
Ghana's Persons with Disability Act, 2006 (Act 715) set a 10-year window to retrofit public buildings, but a 2025 audit of over 60 public places found only 14% had some retrofitting and 8% had accessible toilets. As an employer you can do better. Many print and sign tasks are workable: artwork and separations at a computer (screen readers help blind designers with admin and files), vinyl weeding, HTV pressing, folding and packing, quality checks, customer service and bookkeeping. Helpful adjustments: step-free entrance; work tables at seated height; tools within reach; high-contrast and tactile labels; flashing as well as beeping timers; written and picture job tickets for Deaf staff; a partner for ladders, heavy screens and the wash-out. (Author's advice.)
The one-page business plan
| Heading | What to write |
|---|---|
| Business name and form | Name; sole proprietor or company |
| What you sell | Screen printing, vinyl, HTV, signs, installation |
| Customers | Schools, churches, events, shops; why they buy from you |
| Location | Where and why |
| Competition | Who else, their prices, your edge |
| Team | Owner, staff, apprentices; skills |
| Equipment and start-up cost | From the budget |
| Funding | Sources and repayments |
| Sales and profit (year 1) | From the forecast (Unit 7) |
| Permits and compliance | ORC, Assembly, tax route, SSNIT, rights policy |
| Risks and answers | Power cuts, slow months, late payers, copy designs |
Register and plan
- Choose a legal form and explain why.
- Write the registration checklist with each body, fee and due date.
- Prepare your own start-up budget with at least three real local quotes.
- Draft the one-page plan.
Three visits
Visit (or phone) the ORC regional office or website, your Assembly revenue office and a GEA Business Advisory Centre. Write what each told you and what documents they need.
Check yourself: Unit 5
- What is the 2026 ORC fee for registering a business name?
- Why might a print and sign shop need to register for VAT even with small sales?
- Name two adjustments that let a Deaf worker do production work safely.
Unit 6 · Bookkeeping and accounts for a print and sign shop
If the books are not kept, you cannot tell a busy shop from a profitable one.
Competency standard
| Learning outcome | Performance criteria: the trainee… |
|---|---|
| 6.1 Keep daily records | keeps a job book, cash book (cash and MoMo), receipts and invoices |
| 6.2 Control stock, debtors and deposits | keeps stock cards for blanks and consumables, a debtors list and a deposits list |
| 6.3 Prepare monthly accounts | prepares a profit and loss and a balance sheet that balances |
| 6.4 Pay staff and tax correctly | calculates SSNIT and PAYE and keeps the filing calendar |
| 6.5 Price and analyse | uses break-even, depreciation and reconciliation |
Range. One month of a small print and sign shop (example figures); the trainee's own records for a week. Evidence. Completed cash book, P&L and balance sheet; payroll sheet; reconciliation; oral questions.
The daily set of records
| Record | What goes in it |
|---|---|
| Job book | Job number, customer, items, price, deposit, due date, status |
| Cash book | Every receipt and payment the same day; cash and MoMo in separate columns |
| Receipts and invoices | Numbered copies for every sale and deposit; supplier receipts filed |
| Stock cards | Blank shirts by size and colour; ink, emulsion, vinyl, HTV |
| Debtors list | Who owes, how much, since when |
| Deposits list | Money received for jobs not yet delivered (you owe the job) |
| Petty cash | Small cash spends with slips |
Every entry has two sides: when cash comes in, either income rises or something else changes; Assets = Liabilities + Equity. See the hub's Money Skills Level 2 for the basics.
Deposits are not sales yet
A 50% deposit is money you owe as a job until you deliver. Record it as a liability ("customer deposits"). When you deliver, move it to sales. This stops you spending a June order's deposit in May and then having no money to buy the shirts.
A month for Kwesi's Print and Sign (example numbers)
Kwesi runs a print and sign shop with one printer, one helper and himself. Everything is invented for practice.
At 1 May. Cash and MoMo 8,000. Stock: 100 blank shirts at 35 = 3,500; ink, emulsion and film 1,200; vinyl and HTV 900: total 5,600. Equipment cost 24,000 less depreciation so far 4,000 = 20,000. He owes a shirt supplier 1,000 and holds a church deposit of 1,500 (half of a 3,000 order). Owner's capital and profits kept: 31,100.
During May.
- Buys 300 blank shirts at 35 = 10,500: pays 9,500 and owes 1,000; pays the old 1,000.
- Buys ink, emulsion and film 1,400; vinyl and HTV 1,100; boards and paint 900 (all cash).
- Delivers the church order (50 shirts, 3,000): uses the 1,500 deposit and the church pays 1,500.
- Delivers a school order: 150 shirts at 58 = 8,700; the school pays 5,000 and owes 3,700.
- Walk-in jobs: 60 shirts at 65 = 3,900 (cash).
- Stickers and vinyl lettering: 1,800 (cash).
- Three signboards: 2,400 (cash), using all the boards and paint.
- Takes a 2,000 deposit for a funeral order to be made in June.
- Uses 260 shirts (50 + 150 + 60), ink etc. 1,300, vinyl 1,000, boards and paint 900.
- Pays the printer 1,500 gross and the helper 600 gross (payroll below).
- Pays rent 800, electricity 600, water 150, transport 400, phone and data 150, cleaning and waste 120, marketing 200; takes his own wage 1,500.
Closing count, 31 May. Shirts 140 at 35 = 4,900; ink etc. 1,300; vinyl 1,000: total 7,200.
Stock check: opening 5,600 + bought (10,500 + 1,400 + 1,100 + 900) 13,900 − used (9,100 + 1,300 + 1,000 + 900) 12,300 = 7,200, which matches the count.
Payroll. Printer: SSNIT 5.5% = 82.50; taxable 1,417.50; PAYE = 0 on 588 + 4.00 on 80 + 10.00 on 100 + 113.66 on 649.50 = 127.66; net 1,289.84; employer SSNIT 13% = 195.00. Helper: SSNIT 33.00; taxable 567, below 588, so PAYE nil; net 567.00; employer SSNIT 78.00.
| Profit and loss for May | GH¢ |
|---|---|
| Church order | 3,000.00 |
| School order (150 × 58) | 8,700.00 |
| Walk-in shirts (60 × 65) | 3,900.00 |
| Stickers and vinyl | 1,800.00 |
| Signboards | 2,400.00 |
| Sales | 19,800.00 |
| Shirts used (260 × 35) | 9,100.00 |
| Ink, emulsion and film used | 1,300.00 |
| Vinyl and HTV used | 1,000.00 |
| Boards and paint used | 900.00 |
| Cost of sales | 12,300.00 |
| Gross profit (37.9% of sales) | 7,500.00 |
| Wages (printer 1,500 + helper 600) | 2,100.00 |
| Employer SSNIT (195 + 78) | 273.00 |
| Rent | 800.00 |
| Electricity | 600.00 |
| Water | 150.00 |
| Transport | 400.00 |
| Phone and data | 150.00 |
| Cleaning and waste | 120.00 |
| Marketing | 200.00 |
| Depreciation ((24,000 − 2,400) ÷ 5 years ÷ 12) | 360.00 |
| Fees set aside ((500 + 70) ÷ 12) | 47.50 |
| Total other costs | 5,200.50 |
| Net profit before owner's wage | 2,299.50 |
| Owner's wage | 1,500.00 |
| Profit kept in the business | 799.50 |
Depreciation is straight line: (cost − scrap value) ÷ years of use. The set-aside uses an example Assembly fee of 500 and the ORC renewal of 70.
| Cash book for May | GH¢ |
|---|---|
| Opening cash and MoMo | 8,000.00 |
| In: church balance | 1,500.00 |
| In: school part-payment | 5,000.00 |
| In: walk-in shirts | 3,900.00 |
| In: stickers and vinyl | 1,800.00 |
| In: signboards | 2,400.00 |
| In: funeral deposit | 2,000.00 |
| Total in | 16,600.00 |
| Out: old supplier debt | 1,000.00 |
| Out: shirts (part) | 9,500.00 |
| Out: ink, emulsion, film | 1,400.00 |
| Out: vinyl and HTV | 1,100.00 |
| Out: boards and paint | 900.00 |
| Out: printer's net pay | 1,289.84 |
| Out: helper's net pay | 567.00 |
| Out: rent 800, electricity 600, water 150, transport 400, data 150, cleaning 120, marketing 200 | 2,420.00 |
| Out: owner's wage | 1,500.00 |
| Total out | 19,676.84 |
| Closing cash and MoMo (8,000 + 16,600 − 19,676.84) | 4,923.16 |
At month-end Kwesi still owes PAYE 127.66, SSNIT 388.50 (employees 82.50 + 33.00; employer 195.00 + 78.00) and the 47.50 fee set-aside: 563.66 in total, paid in June by the due dates.
| Balance sheet at 31 May | GH¢ | GH¢ | |
|---|---|---|---|
| Cash and MoMo | 4,923.16 | Supplier owed | 1,000.00 |
| Debtors (school) | 3,700.00 | Customer deposit (funeral) | 2,000.00 |
| Stock | 7,200.00 | PAYE, SSNIT and fees owed | 563.66 |
| Equipment 20,000 less 360 | 19,640.00 | Owner's capital and profits at start | 31,100.00 |
| Profit kept in May | 799.50 | ||
| Total assets | 35,463.16 | Total liabilities and equity | 35,463.16 |
The two sides match. If they did not, look for an entry made once, in the wrong place, or not at all.
Why did cash fall by 3,076.84 when the business made a profit of 799.50? Profit kept 799.50 + depreciation 360 (not a cash cost) + new funeral deposit 2,000 − church deposit used 1,500 + PAYE, SSNIT and fees still owed 563.66 − school still owing 3,700 − stock built up 1,600 = −3,076.84. Profit is not cash. Kwesi must chase the school and avoid buying more shirts than June needs.
Stock and debtors (example)
(a) Shirt card for June: opening 140, bought 300, issued to jobs 380, counted at month-end 55. How many shirts are missing, and what is the loss at GH¢35 each? (b) Debtors at 30 June: the school owes GH¢3,700 for 45 days, a hotel GH¢1,200 for 20 days, a church GH¢900 for 75 days. Group them 0–30, 31–60 and over 60 days. Whom do you chase first?
Pay staff correctly: PAYE and SSNIT
Deduct employee SSNIT (5.5%) first. The 2026 monthly PAYE bands: first GH¢588 at 0%; next 80 at 5%; next 100 at 10%; next 2,900 at 17.5%; next 16,000 at 25%; next 30,332 at 30%; above 50,000 at 35%. Act 1178 raised the tax-free amount to GH¢588 a month from 1 September 2026. The employer pays SSNIT within 14 days after month-end and PAYE by the 15th.
Payroll for a supervisor on GH¢2,200 a month (example)
Work out: (a) employee SSNIT; (b) taxable pay; (c) PAYE; (d) net pay; (e) employer SSNIT; (f) total cost to the business.
Pricing, break-even and depreciation
- Mark-up = profit ÷ cost; margin = profit ÷ price. A 40% mark-up is only a 28.6% margin.
- Break-even sales = fixed costs ÷ gross margin (as a fraction). For Kwesi: fixed costs (other costs 5,200.50 + owner's wage 1,500) = 6,700.50; gross margin 7,500 ÷ 19,800 = 37.9%; break-even ≈ 6,700.50 ÷ 0.3788 ≈ GH¢17,689 of sales a month, if the mix of work stays the same. May's 19,800 is only about GH¢2,100 above it: a thin cushion.
- Price per job must cover set-up per screen, so small orders need a minimum charge.
Depreciation (example)
(a) A 4-colour press cost GH¢9,000, scrap value GH¢1,000, life 5 years: depreciation per year and per month? (b) A vinyl cutter cost GH¢4,600, scrap value GH¢600, life 4 years: per year and per month?
Reconcile MoMo (example)
Your cash book shows a MoMo balance of GH¢2,480. The MoMo statement shows GH¢2,705. A sticker customer's GH¢150 and a deposit of GH¢100 are on the statement but not in your book, and the network took a GH¢25 charge you did not record. Do they agree after you correct the book?
Month-end routine
- Count cash; reconcile MoMo and bank statements
- Add up the cash book and carry the balance forward
- Count blanks by size and colour and all consumables; compare with stock cards; investigate gaps
- Move deposits to sales for jobs delivered; update the deposits list
- List debtors by age and chase the oldest; list creditors
- Prepare the profit and loss and the balance sheet; check they balance
- Pay SSNIT and PAYE on time; set aside yearly fees and tax
- File receipts, invoices, payslips, job tickets, permission letters and tax papers; back up phone records
Tax records and the filing calendar
Keep records in Ghana for at least six years from the end of the year of assessment or VAT period, longer if under dispute. If May is typical, Kwesi's yearly turnover is about 19,800 × 12 = GH¢237,600, inside the MTS band of GH¢20,001–750,000, so MTS at 3% would be about GH¢7,128 a year, unless GRA says his printing and installation services must register for VAT (no threshold for taxable services).
| When | What |
|---|---|
| 14 days after month-end | SSNIT |
| 15th of next month | PAYE and withholding tax |
| Last working day of next month | VAT return, if registered |
| End of March, June, September, December | Provisional tax, companies |
| 31 March | Assembly permit |
| Yearly | ORC renewal or annual return; income tax return within four months after year-end |
From 1 January 2027, the 2025 edition of IFRS for SMEs applies where that standard is used. A small shop does not need it, but clear books help with lenders. Free tools: a spreadsheet, Zoho Books' free plan or Wave's free starter plan. A paper book you use beats software you do not.
Close a month
- Rebuild Kwesi's May cash book, profit and loss and balance sheet, and check they balance.
- Keep a job book, cash book, deposits list and shirt stock card for a week of real or practice work.
- Reconcile a MoMo statement and age a debtors list.
- Run payroll for a supervisor, a printer and a helper and list the due dates.
Keep a week
Keep your own (or a family business's) cash book for seven days with cash and MoMo columns. At the end of the week, count and reconcile.
Check yourself: Unit 6
- Why is a customer's deposit a liability and not a sale?
- Kwesi made a profit but his cash fell. Give two reasons.
- What is the break-even formula?
Unit 7 · Grow, sustain and present your plan
Grow on proven orders, protect your name, and show your numbers honestly. That is how a lender, a partner or a big customer comes to trust you.
Competency standard
| Learning outcome | Performance criteria: the trainee… |
|---|---|
| 7.1 Run a quality system | sets standards, checks and customer feedback for every product line |
| 7.2 Set a pricing strategy | sets price lists with minimum charges, quantity breaks and rush fees |
| 7.3 Plan growth | chooses growth routes, partnerships and tenders and knows the records lenders need |
| 7.4 Present the plan | presents a one-page plan and 12-month cash-flow forecast to a panel and answers questions |
Range. The trainee's own planned business. Evidence. Quality standards sheet; price list; growth plan; forecast; capstone presentation and panel score sheet.
A simple quality system
- Standards written for each product: print position, size tolerance, cure temperature and test, sign letter height and fixing method
- Checks at first piece, every 10th piece and final count (Unit 1)
- Records: cure logs, reject log, troubleshooting log, maintenance log
- Customer feedback after every big job: one short WhatsApp question ("How were the shirts after washing?")
- Monthly review: rejects, complaints and their causes; one improvement each month
Customer care and pricing strategy
- Minimum charge for small screen jobs, so set-up is always paid; offer HTV for under about 8 pieces (Level 2).
- Quantity breaks: for example, price per shirt for 24, 50, 100 and 250+.
- Rush fee for jobs needed in less than your normal turnaround.
- Deposits: 50% before work; balance on delivery; no credit to customers with old debts.
- Clear warranty in writing for signs and vinyl.
- Fair complaint handling: look, listen, fix or reprint quickly if the fault is yours, and record it.
Ways to grow
| Route | What it needs | Risk |
|---|---|---|
| More customers of the same kind | Marketing, samples, referrals | Low |
| New products (HTV names, stickers, banners) | Small equipment, skills | Low to medium |
| Contracts with schools, churches, companies | Quality, capacity, paperwork | Medium (late payment) |
| A second press or a second shop | Staff, supervision, capital | Medium to high |
| Outsourcing partners (large format, DTF, embroidery) | Trusted partners, clear prices | Low |
Tenders and contracts
- Large customers and public bodies buy through quotations and tenders. Prepare a company profile: registration documents, tax and SSNIT papers, past jobs, references, equipment list and staff.
- Public bodies usually withhold tax when they pay; keep withholding certificates.
- Read the payment terms: 30–90 days to pay is common for big buyers (author's experience; not verified). Price in the cost of waiting, and never take a tender you cannot finance.
Records for loans, succession and ethics
- Lenders ask for: registration, tax and permit papers, 6–12 months of cash book and bank or MoMo statements, profit and loss, balance sheet, the business plan and a cash-flow forecast. Keep records at least six years.
- Succession: train a deputy who can run the shop for a week; write procedures; keep files and passwords where a trusted person can find them.
- Ethics: no copy logos or fake jerseys, ever; honest descriptions of durability; fair wages paid on time; proper waste disposal; no "small chop" to win contracts.
Your 12-month cash-flow forecast (example)
Kwesi plans to buy a bigger press in March with a loan. Assumptions (all example figures): opening cash GH¢5,000; sales follow the seasons (school reopening, Easter, Christmas); materials 55% of sales after he starts buying shirts by the bale; fixed costs (staff, rent, power and running costs) GH¢4,700 a month; owner's wage GH¢1,500 a month; MTS at 3% of sales; a GH¢15,000 loan received in March to buy a GH¢17,000 press; loan repayments GH¢1,400 a month from April. All sales are treated as cash in the same month (a simplification).
| Month | Opening | Sales in | Loan in | Materials | Fixed + owner | Press | Loan repaid | MTS 3% | Closing |
|---|---|---|---|---|---|---|---|---|---|
| Jan | 5,000 | 22,000 | 0 | 12,100 | 6,200 | 0 | 0 | 660 | 8,040 |
| Feb | 8,040 | 15,000 | 0 | 8,250 | 6,200 | 0 | 0 | 450 | 8,140 |
| Mar | 8,140 | 18,000 | 15,000 | 9,900 | 6,200 | 17,000 | 0 | 540 | 7,500 |
| Apr | 7,500 | 20,000 | 0 | 11,000 | 6,200 | 0 | 1,400 | 600 | 8,300 |
| May | 8,300 | 19,800 | 0 | 10,890 | 6,200 | 0 | 1,400 | 594 | 9,016 |
| Jun | 9,016 | 16,000 | 0 | 8,800 | 6,200 | 0 | 1,400 | 480 | 8,136 |
| Jul | 8,136 | 15,000 | 0 | 8,250 | 6,200 | 0 | 1,400 | 450 | 6,836 |
| Aug | 6,836 | 17,000 | 0 | 9,350 | 6,200 | 0 | 1,400 | 510 | 6,376 |
| Sep | 6,376 | 24,000 | 0 | 13,200 | 6,200 | 0 | 1,400 | 720 | 8,856 |
| Oct | 8,856 | 18,000 | 0 | 9,900 | 6,200 | 0 | 1,400 | 540 | 8,816 |
| Nov | 8,816 | 20,000 | 0 | 11,000 | 6,200 | 0 | 1,400 | 600 | 9,616 |
| Dec | 9,616 | 28,000 | 0 | 15,400 | 6,200 | 0 | 1,400 | 840 | 13,776 |
| Year | 232,800 | 15,000 | 128,040 | 74,400 | 17,000 | 12,600 | 6,984 |
The lowest point is GH¢6,376 in August, and the year ends at GH¢13,776. The plan works on paper, but only because materials fall to 55% of sales; at the 62% Kwesi saw in May, cash would run out by July (check it yourself in the exercise).
Stress-test the forecast (example)
(a) Check the July closing cash: opening 8,136 + sales 15,000 − materials 8,250 − fixed and owner 6,200 − loan 1,400 − MTS 450. (b) Add up the year's total cash in and total cash out, and check: opening 5,000 + in − out = closing 13,776. (c) If materials stay at 62% of sales all year, what would January's closing cash be? (d) Name two actions Kwesi could take if the bigger press arrives late and March–April sales are 20% lower.
Capstone: present to a panel
Present for 10 minutes to a panel of three (a business adviser, a printer or sign maker, and a customer), then answer questions for 10 minutes.
- Your one-page business plan (Unit 5)
- Start-up budget and funding plan
- Your 12-month cash-flow forecast with the lowest month and what you will do about it
- Your price list with minimum charge and quantity breaks
- Your quality system and safety rules (chemicals, UV, heat, height)
- Your rights policy: how you check that every design may be printed
- Registration and permits: what is done and what is next
- Accessibility: how your shop includes workers and customers with disabilities
Present your plan
- Build your own 12-month forecast in a spreadsheet using your own prices and seasons.
- Stress-test it: sales 20% lower for two months; materials 7 points higher.
- Prepare the capstone presentation and rehearse it with a partner.
- Present to the panel and record the panel's three main suggestions in your logbook.
Ask a customer
Ask three possible customers (a school, a church and a shop) what they would need from you to give you their next order. Add their answers to your plan.
Check yourself: Unit 7
- Name three records a lender will ask for.
- Why set a minimum charge for screen printing?
- In the example forecast, what is the lowest closing cash, and in which month?
Glossary
| Term | Meaning |
|---|---|
| Ageing (debtors) | Grouping amounts owed by how long they have been owed |
| Balance sheet | A list of what the business owns and owes, and the owner's share, on one date |
| Break-even | The sales level at which the business makes neither profit nor loss |
| Capacity | How much the shop can produce in a day or week |
| Customer deposit | Money paid in advance for a job not yet delivered; a liability |
| Depreciation | Spreading the cost of equipment over its useful life |
| Discharge ink | Ink that removes the fabric's dye, used on dark cotton |
| DTF | Direct-to-film: printed transfers pressed onto garments |
| Gross margin | Gross profit as a share of sales |
| Halftone | Dots that make shades in a print |
| MTS | Modified Taxation Scheme for small businesses |
| Payback time | How long a machine takes to pay for itself |
| Penalty unit | A unit used in Ghana's laws to set fines |
| Tensiometer | A meter that measures screen tension in N/cm |
| Withholding tax | Tax deducted by a customer from a payment and paid to GRA for you |
Logbook
- Unit 1: weekly schedule; job board photo; training record; safety talk record; quality sampling sheet; shop layout
- Unit 2: halftone and special-effect records; troubleshooting log; fault cards
- Unit 3: site survey; sign design with sums; permit checklist; installation plan; quote and contract; Assembly notes
- Unit 4: method comparison; buy-or-outsource sums; maintenance log; supplier list
- Unit 5: legal form; registration checklist; start-up budget; one-page plan; notes from three visits
- Unit 6: Kwesi's month rebuilt; your week's records; payroll; reconciliation
- Unit 7: quality system; price list; forecast and stress test; capstone feedback
- Every homework, dated
Self-check quiz
- How do you work out daily capacity?
- Name two Labour Act duties of an employer.
- Which mesh do glitter inks need, and why?
- What did STMA charge in 2025 for placing an advertisement without a permit?
- Who connects an illuminated sign to the mains?
- Name four clauses in a sign contract.
- When does owning a DTF machine make sense?
- What is the 2026 ORC fee for a sole proprietor, and the yearly renewal?
- What is the MTS turnover band at 3% after Act 1178?
- Calculate employee SSNIT, PAYE and net pay on GH¢1,500.
- How long must business records be kept?
- Why can a profitable month still leave less cash?
Further reading and sources
Best next reads: the hub's Money Skills Level 2 and Entrepreneurial Thinking Level 2; the STMA fee-fixing resolution for the current year; GRA's MTS, PAYE and VAT pages; the HSE COSHH essentials sheet P24.
What this module does not cover: legal advice; structural engineering of billboards; electrical installation; automatic presses and industrial conveyor lines; full simulated-process colour separation; export (see the agencies named and the hub's other manuals).
Every source used in this manual is listed, with links, in the Teacher Copy.